CN101824930B - Operation method of 10kV common-pylon double-circuit line charged vertical pylon - Google Patents

Operation method of 10kV common-pylon double-circuit line charged vertical pylon Download PDF

Info

Publication number
CN101824930B
CN101824930B CN2009101111547A CN200910111154A CN101824930B CN 101824930 B CN101824930 B CN 101824930B CN 2009101111547 A CN2009101111547 A CN 2009101111547A CN 200910111154 A CN200910111154 A CN 200910111154A CN 101824930 B CN101824930 B CN 101824930B
Authority
CN
China
Prior art keywords
iron tower
double
tower
insulation
common
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009101111547A
Other languages
Chinese (zh)
Other versions
CN101824930A (en
Inventor
李伟新
潘小山
林毓强
蔡俊宇
张世国
庄德金
吕伟庭
方光辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical Xiamen Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority to CN2009101111547A priority Critical patent/CN101824930B/en
Publication of CN101824930A publication Critical patent/CN101824930A/en
Application granted granted Critical
Publication of CN101824930B publication Critical patent/CN101824930B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The invention discloses a vertical iron tower live working method of a 10kV double-circuit line on the same tower comprising the following steps: 1 mounting a lower segment and a middle segment of the iron tower, and performing insulation screen for the wires near a work station; 2 hoisting an upper segment of the iron tower, and fixing the upper segment and the middle segment; 3 mounting a double cross arm and insulators at the upper layer of the iron tower, and getting the insulation screen of the double cross arm and the insulators done well, hoisting a middle phase wire of the double-circuit line on the insulators, fixing firmly and temporarily fixing the circuit near the inside of the iron tower on an upper cross arm by using an insulated rope, then mounting the double cross arm and insulators at a lower layer, and getting the insulation screen of the cross arm and the insulators well, then placing the lower layer wires in the circuit on the insulators and fixing, removing the insulation screen. The invention has advantages that the method of the invention mainly performs muti-screen for the wires near the work station, adopts a reasonable working step, realizes the charged set vertical tower of the multi-circuit line on the same tower by using simple configuration.

Description

The charged upright iron tower operational method of 10kV common-tower double-return circuit
Technical field
The present invention relates to a kind of 10kV common-tower double-return line live-line work method, the charged upright iron tower operational method of particularly a kind of 10kV common-tower double-return circuit.
Background technology
Two distribution lines that return of wiring on the same tower are more and more in the application study in the city, compare with single back line, and it saves line channel more, and the iron tower height can be alleviated tree and line contradiction, Safe Vertical Distance when satisfying city overline bridge and overpass bridge and setting up.But it has also brought new problem, once a loop line road power failure operation needs double-circuit line to have a power failure simultaneously, thereby enlarges the power failure influence area.Therefore press for a kind ofly at the charged upright iron tower operational method of 10kV common-tower double-return circuit, realizing charging construction, not to be subjected to the restriction that has a power failure, reduction of erection time, quickening progress improve the method for power supply reliability greatly.
Summary of the invention
The objective of the invention is to overcome the deficiencies in the prior art part, and the restriction that provides a kind of and can realize charging construction, is not subjected to have a power failure, reduction of erection time, quickening progress improve the charged upright iron tower operational method of 10kV common-tower double-return circuit of power supply reliability greatly.
The objective of the invention is to be achieved by the following scheme:
The charged upright iron tower operational method of 10kV common-tower double-return circuit, its method is as follows, 1, the following joint and the middle joint of iron tower are installed, near the setting lead insulated cover, 2, save on the lifting iron tower, and will go up joint and fix with middle joint, 3, install two cross-arms in iron tower upper strata and insulator, and the insulation of carrying out cross-arm and insulator promotes the middle phase conductor of double-circuit line after covering and places on the insulator, and fixation will be restricted with insulating near the loop of iron tower inboard and will be temporarily fixed on cross-arm, install two cross-arms of lower floor and insulator again, and the insulation of carrying out cross-arm and insulator covers, and the more following layer conductor in the loop placed on the insulator fixingly, removes insulation and covers.
Because the distance between the double-circuit line of wiring on the same tower, the lead is short, in order to prevent that when the operation, lead rocks and causes phase fault, therefore need take insulation to cover near the lead the setting.For iron tower down joint and middle joint, because its top distance of wire distance surpasses the distance of " safety " regulation, so need not just cover and can assemble in advance lead.
Near the described setting wire insulation covers for adopting double insulation to cover.
Described double insulation covers for the mode that adopts wire insulation mask and insulated target to combine and carries out, and insulated target wraps in the outside of lead mask.
The wire insulation mask is the important insulating tool of isolated high-voltage trolley line, it has installs fast, convenient disassembly, advantage such as material is light, but there is potential discharge channel in wire insulation mask opening part, carries out double insulation so add the bag insulated target at the insulation mask.
Joint is slowly to be put down in the middle of the lead of double-circuit line by lead top on the described iron tower, to finish docking and fixing of joint and middle joint on the iron tower.
Described lead places the permanent order on the insulator fixing laterally by the iron tower inboard.
During operation, operating personnel and adjacent electrical body safe distance should keep 0.6m, should keep 0.4m with ground connector, will take the quarantine measures that insulate when not enough.
The lifting of iron tower adopts crane to carry out, and crane needs temporary grounding, and arm should keep 1.0m and above safe distance with electrical body all the time.
The personnel of high-rise working need put on the insulating protection apparatus, enter aerial lift device with insulated arm work.
When removing the insulation screening,, remove in proper order from high to low and cover by by as far as closely.
In sum, the invention has the advantages that:
Livewire work has not only improved power supply reliability but also has effectively reduced power off time, improves the economic benefit of power industry and other every profession and trade.The charged upright iron tower operational method of 10kV common-tower double-return circuit of the present invention, not only filled up domestic blank technically, and enterprise and society had a good economic benefit, 1, charged upright iron tower operation can increase distribution transforming, increase power supply capacity, the power supply area of common-tower double-return circuit is wide, raising along with the resident living level, power consumption is soaring year by year, each power office can only be by newly-increased distribution transforming to alleviate the situation of shortage of electric power, consider power supply reliability, the distribution transforming engineering can only be at the other upright iron tower of double-circuit line on the newly-increased bar in the past, and then receive on the double-circuit line iron tower by charged personnel T, this method takies unnecessary line channel, and it is big to implement difficulty, after promoting the charged upright tower of double-circuit line of wiring on the same tower, promptly can utilize original line channel project implementation simple, can avoid too much branch line to influence the city city appearance environment again, reduce maintenance cost.2, charged upright iron tower increases interconnection switch, the electrical network reliability is provided, along with urban development is more and more higher to the requirement of power supply reliability, increasing distribution network adopts structure structures such as () three segmentations, three contacts of multi-ring network formula, can increase block switch on the post by upright iron tower, interconnection switch is transformed traditional common ring web frame, improves the distribution reliability.3, charged upright iron tower T connects the service cable inlet wire, and the migration iron tower is widened a series of industries such as road surface and expanded engineerings can satisfy the large user under power-off condition not electricity consumption application, shortens industry and expands flow process.
The specific embodiment
Below in conjunction with embodiment the present invention is described in more detail.
Embodiment 1
Be the charged upright iron tower working system of 10kV common-tower double-return circuit:
1. near the lead the setting is insulated and cover: the electrician puts on the insulating protection apparatus in the aerial lift device with insulated arm, carries insulating tool and enters in the work bucket, and the arm that will struggle against is raised to correct position.The electrician carries out two insulation isolation with lead mask (also claiming the lead isolated tube), insulated target with six leads in the bucket, in the course of the work, should adopt insulation to restrict when noting upper and lower transmissions of insulating tool and material, the operating personnel is when carrying out the lead isolation with insulation mask and insulated target, movement range is little, for degree is wanted evenly to prevent phase fault.Should be according to from the near to the remote when insulation is covered, principle is from low to high carried out.
2. save on the lifting iron tower, and fixing: crane slowly lifts by crane on the iron tower and saves, and is slowly put down in the middle of the lead in two loops by the top of lead, and the electrician will be docked and fix the top of finishing iron tower that cooperatively interacts with the lower part of iron tower in the aerial lift device with insulated arm.After the iron tower assembling finished, bucket people electrician broke away from the suspension hook of crane, removed short jack line, and crane leaves from the scene.In the work engineering, crane is when carrying out the iron tower lifting, and arm should keep 1.0m and above safe distance with electrical body all the time.Should note when standing up iron tower can not allowing iron tower roll or tilting, stand up and want steadily.
3. cross-arm and insulator are installed: install two cross-arms in iron tower upper strata and insulator, and the insulation of carrying out cross-arm and insulator is covered, after the middle phase conductor of double-circuit line promoted place on the insulator, fixation, to be temporarily fixed on cross-arm with exhausted with the insulation rope near the loop of iron tower inboard again, and install lower floor's pair cross-arms and insulator again, and the insulation of carrying out cross-arm and insulator is covered, again the following layer conductor in the loop is placed on the insulator and fix, remove insulation and covers.The electrician cooperatively interacts and installs two cross-arms in upper strata and insulator in the bucket, and the insulation of carrying out horizontal back and insulator is covered, the middle phase conductor lifting in two loops is placed on the insulator, colligation is firm, the electrician cooperatively interacts two loops near the iron tower inboard is temporarily fixed on cross-arm with the insulation rope in the bucket, the electrician cooperatively interacts and installs two cross-arms of lower floor and insulator in the bucket, and the insulation of carrying out cross-arm and insulator is covered.Four leads of lower floor in two loops are placed on the insulator, and colligation is firm, and the order of colligation is inboard to the outside by iron tower, in the operation process, operating personnel and adjacent electrical body safe distance should keep 0.6m, should keep 0.4m with ground connector, should carry out the insulation quarantine measures when not enough.
4. after the electrician checks installation qualification in the bucket, remove cross-arm insulation mask, insulation materials on the towers such as empire cloth has or not tool materials not tear open on the inspection bar, and after finishing, aerial lift device with insulated arm is withdrawn the scene.
It is same as the prior art that present embodiment is not stated part.

Claims (9)

1.10kV the charged upright iron tower operational method of common-tower double-return circuit, its method is as follows, 1, the following joint and the middle joint of iron tower are installed, near the setting lead insulated cover, 2, save on the lifting iron tower, and will go up joint and fix with middle joint, 3, install two cross-arms in iron tower upper strata and insulator, and the insulation of carrying out cross-arm and insulator promotes the middle phase conductor of double-circuit line after covering and places on the insulator, fixation, to be temporarily fixed on cross-arm with the insulation rope near the loop of iron tower inboard again, install two cross-arms of lower floor and insulator again, and the insulation of carrying out cross-arm and insulator covers, and the more following layer conductor in the loop placed on the insulator fixingly, removes insulation and covers.
2. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 1 is characterized in that: near the wire insulation the described setting covers for adopting double insulation to cover.
3. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 2 is characterized in that: described double insulation covers for the mode that adopts wire insulation mask and insulated target to combine and carries out, and insulated target wraps in the outside of lead mask.
4. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 3 is characterized in that: joint is slowly to be put down in the middle of the lead of double-circuit line by lead top on the described iron tower, to finish docking and fixing of joint and middle joint on the iron tower.
5. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 4 is characterized in that: described lead places the permanent order on the insulator fixing laterally by the iron tower inboard.
6. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 5 is characterized in that: during operation, operating personnel and adjacent electrical body safe distance should keep 0.6m, should keep 0.4m with ground connector, will take the quarantine measures that insulate when not enough.
7. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 1 is characterized in that: the lifting of iron tower adopts crane to carry out, and crane needs temporary grounding, and arm should keep 1.0m and above safe distance with electrical body all the time.
8. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 1, it is characterized in that: the personnel of high-rise working need put on the insulating protection apparatus, enter aerial lift device with insulated arm work.
9. the charged upright iron tower operational method of 10kV common-tower double-return circuit according to claim 1 is characterized in that: when removing the insulation screening, by by as far as closely, remove in proper order from high to low and cover.
CN2009101111547A 2009-03-05 2009-03-05 Operation method of 10kV common-pylon double-circuit line charged vertical pylon Active CN101824930B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101111547A CN101824930B (en) 2009-03-05 2009-03-05 Operation method of 10kV common-pylon double-circuit line charged vertical pylon

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101111547A CN101824930B (en) 2009-03-05 2009-03-05 Operation method of 10kV common-pylon double-circuit line charged vertical pylon

Publications (2)

Publication Number Publication Date
CN101824930A CN101824930A (en) 2010-09-08
CN101824930B true CN101824930B (en) 2011-06-22

Family

ID=42689074

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101111547A Active CN101824930B (en) 2009-03-05 2009-03-05 Operation method of 10kV common-pylon double-circuit line charged vertical pylon

Country Status (1)

Country Link
CN (1) CN101824930B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106711905B (en) * 2016-11-30 2024-06-11 国网新疆电力公司经济技术研究院 Flexible composite material-based wind deflection prevention pole tower for power transmission line and construction method thereof
CN113937653B (en) * 2021-09-18 2023-05-09 广东电网有限责任公司广州供电局 Distribution line migration method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1077371A (en) * 1963-01-31 1967-07-26 Rutenberg Abraham Improvements in or relating to high tension electric power conductor suspension
CN2909652Y (en) * 2006-05-31 2007-06-06 北京国电华北电力工程有限公司 Co-tower double-loop compact linear transmission pylon
CN1979988A (en) * 2005-12-08 2007-06-13 北京国电华北电力工程有限公司 Common-tower double-return compact type corner transmission iron tower

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1077371A (en) * 1963-01-31 1967-07-26 Rutenberg Abraham Improvements in or relating to high tension electric power conductor suspension
CN1979988A (en) * 2005-12-08 2007-06-13 北京国电华北电力工程有限公司 Common-tower double-return compact type corner transmission iron tower
CN2909652Y (en) * 2006-05-31 2007-06-06 北京国电华北电力工程有限公司 Co-tower double-loop compact linear transmission pylon

Also Published As

Publication number Publication date
CN101824930A (en) 2010-09-08

Similar Documents

Publication Publication Date Title
CN101958519B (en) Method for transforming tangent tower of double-circuit double-bundle transmission lines by lifting in electrified mode in another place
CN101277002B (en) Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever
CN203166366U (en) Mobile transformer station
CN103311844B (en) Alpine terrain crosses over the stringing method of live high voltage circuit
CN101824930B (en) Operation method of 10kV common-pylon double-circuit line charged vertical pylon
CN102426963B (en) Direct-current ice-melting isolating switch
CN102255261A (en) Shifting device for two-circuit hot-line work of transmission line
CN104295147B (en) A kind of framework being applicable to transformer station's outlet
CN204067880U (en) A kind of power distribution equipment arrangement back-to-back
CN115377862A (en) Bypass cable fixing operation method
CN102510029B (en) Ground potential electrified bar cutter device changing method
CN202058631U (en) Tension-resistant isolating switch
CN107237535A (en) A kind of unilateral cross-arm anchor support used for transmission line
CN105932602B (en) The method that three-phase conducting wire charges lifter and replaces insulator using the lifter
CN207459404U (en) Indoor GIS device roof outlet structure
CN208024006U (en) A kind of open air GIS device protection canopy
CN205713387U (en) A kind of four return cable terminal towers
CN207069293U (en) One kind uses distribution framework made of composite insulating material
CN201408936Y (en) Wire supporting device for insulating boom aerial
CN201191741Y (en) Three phase conductive wire insulation fixing rack
CN209730616U (en) A kind of buried outgoing line interval arragement construction of substation
CN219535583U (en) 110kV single-circuit flat-bed-free type cable terminal tower
CN216599019U (en) High-voltage reactive compensation composite device
CN204174995U (en) A kind of framework being applicable to transformer station's outlet
CN221896331U (en) Novel T-connection tower for overhead current collecting line of new energy station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: FUJIAN ELECTRIC POWER CO., LTD. XIAMEN ELECTRIC PO

Effective date: 20121218

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: XIAMEN ELECTRIC POWER INDUSTRY BUREAU FUJIAN

Effective date: 20121218

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 361009 XIAMEN, FUJIAN PROVINCE TO: 100031 DONGCHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20121218

Address after: 100031 West Chang'an Avenue, Beijing, No. 86

Patentee after: State Grid Corporation of China

Patentee after: Fujian Electric Power Co., Ltd.

Patentee after: Xiamen Electric Power Bureau of Fujian Electric Power Company Limited

Address before: Siming Lake Road Xiamen city Fujian province 361009 No. 21

Patentee before: Xiamen Electric Power Industry Bureau Fujian