US20070163783A1 - Method of abandoning a well - Google Patents

Method of abandoning a well Download PDF

Info

Publication number
US20070163783A1
US20070163783A1 US10/576,799 US57679904A US2007163783A1 US 20070163783 A1 US20070163783 A1 US 20070163783A1 US 57679904 A US57679904 A US 57679904A US 2007163783 A1 US2007163783 A1 US 2007163783A1
Authority
US
United States
Prior art keywords
well
annular chamber
pump
conduits
fluid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US10/576,799
Inventor
Philip Head
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20070163783A1 publication Critical patent/US20070163783A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like

Definitions

  • offshore structures may comprise production platforms which are either steel or concrete structures resting on the sea bed or floating platforms. Numerous conduits are connected to these offshore structures to carry the various fluids being gas, oil or water etc., which are necessary for the production of oil and/or gas from the well.
  • a typical production well will comprise a number of tubular conduits arranged concentrically with respect to each.
  • the method of abandoning the well which is presently known in the art involves the separate sealing of each of the concentric conduits which requires a large number of sequential steps.
  • the first step is to seal the first central conduit usually by means of cement or other suitable sealant.
  • the first annular channel between the first and second conduits is then sealed and the first central conduit is then cut above the seal and the cut section is removed from the well.
  • a method of abandoning a well comprising at least two concentric conduits defining a main bore and at least one annular chamber there between, comprising the steps of:
  • an apparatus for abandoning a well having at least two concentric conduits defining at least one annular chamber there between, the apparatus including a pump and a perforation forming device.
  • FIG. 1 is a side view of a typical subsea well showing a vessel situated over it and with a well intervention package attached.
  • FIG. 2 is a plan view of the multi barrel storage and launching assembly, located above the wellhead and below the blow out preventors.
  • FIG. 3 is a side view of the wellhead, with a well intervention system connected and a tool assembly being lowered from the vessel above.
  • FIG. 4 is a side view of the wellhead, with a well intervention system connected and a tool assembly installed in the pressure vessel (lubricator) section of the well intervention package.
  • FIG. 5 is a cross section of a well showing the typical components and there relative depth.
  • FIG. 6 shows the same cross section of the well as the figure above, but with a tool assembly lowered to its tailpipe
  • FIG. 7 shows the same cross section of the well as the figure above, displacing fluid into the reservoir section and lowering an electric pump
  • FIG. 8 shows the same cross section of the well as the figure above, the lower tubing and tubing annuli evaculated of fluid by the electric pump.
  • FIG. 9 a shows a cross section of the umbilical power cable
  • FIG. 9 b shows a cross section of the umbilical power cable of another embodiment of the well system, shown in FIGS. 13 to 16
  • FIG. 10 Shows the lower voids filled with sealing material
  • FIG. 11 shows the electric pump and hole making system moved up the well and new holes perforated through all the sections of casing
  • FIG. 12 shows all the annuli perforated, voided of fluid by allowing to flow to the sump below and by using the electric pump, and finally filled with sealing material
  • FIGS. 13 to 16 shows the stages of another embodiment of the method.
  • FIG. 1 to 4 shows the well intervention package.
  • This consists of a wellhead connector adaptor 10 , an optional wellhead plug retrieval and plug launcher carousel 11 fitted directly above this, blow out preventors 12 , high pressure wellbore extension (more commonly know as the lubricator) 13 , and a funnel guide 14 to provide easy access for the tools when lowered from the vessel 15 .
  • Guide lines 16 are shown, but are not essential.
  • a tool assembly 20 is prepared on the vessel and lowered on an umbilical 21 . It is also lowered with the dynamic umbilical seal 22 , a guide means 23 and a method of docking and retaining itself 24 into an internal profile 25 at the top of the lubricator 13 .
  • the wellhead plug 30 ensures the well is safe for normal production operations, but can be removed to enable the well to be accessed.
  • a tool can either be activated from the tool carousel 11 or lowered from the vessel. In either case the plug 17 can be stored in one of the empty barrels 16 of the tool carousel. This saves considerable tripping time for the operating tool 20 .
  • FIG. 5 to 12 shows the well abandonment process in greater detail.
  • the main objectives are to isolate all zones and casing annuli with a multi interval 100% permanent seal or seals, prohibit the return of well bore hydrocarbon fluids to surface, eliminate the need to pull out of the well the production tubing and disposal of it. How this is achieved is described as follows.
  • FIG. 5 shows a well which is to be abandoned and made safe by the method and apparatus described herein.
  • the well has production tubing 30 installed above the production perforations 56 , the production tubing being sealed from an annulus by a production packer 26 .
  • material may be placed in the annular area 40 around the tailpipe, then a tailpipe seal 41 is lowered on an umbilical and it is landed in a tailpipe nipple (not shown) to hold it in place. This is not essential, but it provides an ideal sealing and anchor point.
  • a seal assembly 39 includes a tailpipe seal 41 at its lower end which plugs the end of the production tubing 30 .
  • the seal assembly 39 includes a hole making system such as a perforating charge 42 . This is used to make holes 43 in the tailpipe to permit the flow of the existing well fluids therethrough.
  • the tailpipe seal also has a dual check valve 45 to provide a means permitting flow from the production tubing into the lower part of the well and of preventing fluid from flowing back into the production tubing.
  • This dual check valve is preferably mechanical, which may in its simplest form be a spring loaded ball biased against a sealing seat.
  • the seal assembly 39 is lowered into position by means of a conveyance tool 50 , suspended from the end of an the umbilical 49 . After the seal assembly is fixed in position the umbilical 49 and conveyance tool 50 are recovered back to surface.
  • the pump assembly includes a pump 53 below which is provided tube holing means and below the holing means well sealing material 52 is provided. At the lowermost end of the well sealing material a bottom plug 51 is provided.
  • the pump assembly is forced down the production tubing by the pressure of a displacement fluid provided above the pump assembly.
  • the displacement fluid could be seawater or even nitrogen.
  • the bottom plug 51 seals against the internal wall of the production tubing so that the contents of the production tubing 55 are then displaced back into the lower part of the well and into the reservoir through the reservoir perforations 56 .
  • the well sealing material has passed through the plug assembly and into the lowermost part of the well. This sealing material cures in time and provides a permanent seal of the formation.
  • FIG. 9 a shows the structure of the umbilical 63 , comprising an outer armoured supporting layer, and an inner layer of lower cables 67 surrounding the bore 64 .
  • plug, sealing, holing and pumping actions are carried out in that particular sequence using a single pump assembly tool, it is also possible to use separate tools for the separate steps and variations to the sequence.
  • the pump can be moved up the hole and sealing material pumped down the production tubing annulus 62 . This will equalise in both the tubing annulus and tubing ID at equal levels and form a perfect second barrier 70 to the reservoir.
  • a new set of perforations 80 are made and the residual mud in chambers 81 and 82 is allowed to drain into the sump 83 and 84 .
  • the next set of perforations is made at a depth where as many casing can be perforated as possible.
  • sealing material 90 can be pumped into any of the voided chambers 91 or 92 and fill all the voided chambers 93 and 94 via the equalisation holes 95 .
  • the wellhead and multi casing string could then be safely removed, for example by abrasive jet cut off of the conductor below the mud line and safely recovered back to the vessel.
  • an electric pump 53 is lowered through the production tubing 30 of a cased well.
  • a tailpipe seal assembly 102 is connected below the pump by a space out tube 103 .
  • the umbilical does not have an through bore, and may simply comprise power cables 67 surrounded by a layer of armoured supporting cables 66 , as shown in FIG. 9 b.
  • anchors 104 on the tailpipe assembly 102 engage to secure the pump and tailpipe assembly.
  • Perforation means 121 and 101 on the pump 53 and tailpipe assembly 102 are activated to create holes 110 , 120 in the production tubing 30 .
  • the tailpipe assembly 102 includes upper and lower seals 106 , 109 to isolate the area above and below the holes 110 .
  • the pump 53 then forces any well fluid 131 in the production tube above the pump, and the first annulus 132 , through the space out tube 103 and check valve 108 to exit the tailpipe assembly and pass into the bottom of the well.
  • cemet or other sealing material is then pumped or poured into the production tubing 30 bore 131 , the first tubing annulus 132 , or both to form a seal above the production packer 45 .
  • the pump then pumps a predetermined volume of cement through the tailpipe assembly's check valve and thence beneath the tailpipe assembly 102 .
  • the cement is left to set to produce a plug of material at the bottom of the production tubing 30 , the first annulus 131 , and beneath the tailpipe to the well bottom 140 .
  • the a volume of cement sufficient to reach and seal the perforations 56 may be pumped into the bottom of the well.
  • a pressure test or a tag test may be carried out to confirm the cement's location and pressure holding capability. If such testing is not required, then the space out tube 103 and pump 53 may be pulled free of the tailpipe assembly and can be moved up the hole, as shown in FIG. 10 .
  • the top of the concrete seal may be typically at a depth of 10,000 feet.
  • the pump is raised to between 500-1000 feet from the surface, and then the tube holing means 101 on the pump 53 make a series of holes 111 through the production tubing 30 and casing tubes 31 , 32 . Provided the fluid remaining the upper portions of annuli 145 , 146 etc. are smaller than the voided volume of the lower part of annulus 141 and the production tube bore 140 , this fluid will all drain into the lower part of annulus 141 and the production tube bore 140 .

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Reciprocating Pumps (AREA)
  • Jet Pumps And Other Pumps (AREA)
  • Earth Drilling (AREA)

Abstract

A method of abandoning a well, said well comprising at least two concentric conduits (28,30) defining a main bore and at least one annular chamber (40) there between, comprising the steps of providing a perforation in one or more of the conduits, pumping out the fluiti from the annular chamber and/or main bore to create a fluiti-free void, inserting sealing material in the annular chamber and/or main bore to seal it/them. There is also provided an apparatus for abandoning a well having at least two concentric conduits defining at least one annular chamber there between, the apparatus including a pump (50) and a perforation forming device (42).

Description

  • Over the past 20 years or so a large number of offshore structures have been constructed which are now or will soon be exhausted and will need to be abandoned. These offshore structures may comprise production platforms which are either steel or concrete structures resting on the sea bed or floating platforms. Numerous conduits are connected to these offshore structures to carry the various fluids being gas, oil or water etc., which are necessary for the production of oil and/or gas from the well.
  • In abandoning a well, consideration has to be given to the potential environmental threat from the abandoned well for many years in the future.
  • In the case of offshore structure there is usually no rig derrick in place which can be used to perform the required well abandonment procedure. Therefore it is typically necessary to install a new derrick or alternatively a mobile derrick can be positioned above the well. This requirement adds considerable expense to the to the task of abandoning the offshore well, compared to a land based well.
  • A typical production well will comprise a number of tubular conduits arranged concentrically with respect to each. The method of abandoning the well which is presently known in the art involves the separate sealing of each of the concentric conduits which requires a large number of sequential steps.
  • In the abandonment method known in the art the first step is to seal the first central conduit usually by means of cement or other suitable sealant. The first annular channel between the first and second conduits is then sealed and the first central conduit is then cut above the seal and the cut section is removed from the well.
  • The second annular channel between the second and third conduits is then sealed and the second conduit cut above the seal and the cut section is removed from the well.
  • This process is repeated until all the conduits are removed. The number of separate steps required is typically very large indeed and the number of separate operations is five times the number of conduits to be removed. This adds considerably to the cost of the well abandonment due to the time taken and the resources required at the well head.
  • It is the purpose of the present invention to provide a method of abandoning a well which avoids the disadvantageous and numerous operations which are required by the existing known methods. This will greatly reduce the costs of safely abandoning a well. It is a further objective of the invention to provide a method of abandoning a well without the requirement of a rig which involves significant expense particularly in sea based wells.
  • It is a further advantage of the invention to isolate all the conduits and annuli with no return of the well bore or annular fluids to the surface. Additionally if required all tubing and casing can remain in the well. Further more the method of abandonment of the well will comply with all the regulatory guidelines for the isolation of a well.
  • According to the present invention there is provided a method of abandoning a well, said well comprising at least two concentric conduits defining a main bore and at least one annular chamber there between, comprising the steps of:
      • providing a perforation in one or more of the conduits,
      • pumping out the fluid from the annular chamber and/or main bore to create a fluid-free void,
      • inserting sealing material in the annular chamber and/or main bore to seal it/them.
  • According to another aspect of the present invention there is provided an apparatus for abandoning a well having at least two concentric conduits defining at least one annular chamber there between, the apparatus including a pump and a perforation forming device.
  • Thus by means of the method according to the invention the number of operations required is greatly reduced thus resulting in a considerable reduction in the cost of carrying out the well abandonment.
  • The following is a more detailed description of an embodiment according to invention by reference to the following drawings in which:
  • FIG. 1 is a side view of a typical subsea well showing a vessel situated over it and with a well intervention package attached.
  • FIG. 2 is a plan view of the multi barrel storage and launching assembly, located above the wellhead and below the blow out preventors.
  • FIG. 3 is a side view of the wellhead, with a well intervention system connected and a tool assembly being lowered from the vessel above.
  • FIG. 4 is a side view of the wellhead, with a well intervention system connected and a tool assembly installed in the pressure vessel (lubricator) section of the well intervention package.
  • FIG. 5 is a cross section of a well showing the typical components and there relative depth.
  • FIG. 6 shows the same cross section of the well as the figure above, but with a tool assembly lowered to its tailpipe
  • FIG. 7 shows the same cross section of the well as the figure above, displacing fluid into the reservoir section and lowering an electric pump
  • FIG. 8 shows the same cross section of the well as the figure above, the lower tubing and tubing annuli evaculated of fluid by the electric pump.
  • FIG. 9 a shows a cross section of the umbilical power cable
  • FIG. 9 b shows a cross section of the umbilical power cable of another embodiment of the well system, shown in FIGS. 13 to 16
  • FIG. 10 Shows the lower voids filled with sealing material
  • FIG. 11 shows the electric pump and hole making system moved up the well and new holes perforated through all the sections of casing
  • FIG. 12 shows all the annuli perforated, voided of fluid by allowing to flow to the sump below and by using the electric pump, and finally filled with sealing material
  • FIGS. 13 to 16 shows the stages of another embodiment of the method.
  • Referring to the figures in more detail, FIG. 1 to 4 shows the well intervention package. This consists of a wellhead connector adaptor 10, an optional wellhead plug retrieval and plug launcher carousel 11 fitted directly above this, blow out preventors 12, high pressure wellbore extension (more commonly know as the lubricator) 13, and a funnel guide 14 to provide easy access for the tools when lowered from the vessel 15. Guide lines 16 are shown, but are not essential. A tool assembly 20 is prepared on the vessel and lowered on an umbilical 21. It is also lowered with the dynamic umbilical seal 22, a guide means 23 and a method of docking and retaining itself 24 into an internal profile 25 at the top of the lubricator 13. The wellhead plug 30 ensures the well is safe for normal production operations, but can be removed to enable the well to be accessed. A tool can either be activated from the tool carousel 11 or lowered from the vessel. In either case the plug 17 can be stored in one of the empty barrels 16 of the tool carousel. This saves considerable tripping time for the operating tool 20.
  • FIG. 5 to 12 shows the well abandonment process in greater detail. The main objectives are to isolate all zones and casing annuli with a multi interval 100% permanent seal or seals, prohibit the return of well bore hydrocarbon fluids to surface, eliminate the need to pull out of the well the production tubing and disposal of it. How this is achieved is described as follows.
  • FIG. 5 shows a well which is to be abandoned and made safe by the method and apparatus described herein. The well has production tubing 30 installed above the production perforations 56, the production tubing being sealed from an annulus by a production packer 26. If required, to ensure a good sealing, material may be placed in the annular area 40 around the tailpipe, then a tailpipe seal 41 is lowered on an umbilical and it is landed in a tailpipe nipple (not shown) to hold it in place. This is not essential, but it provides an ideal sealing and anchor point.
  • As shown in FIG. 6 a seal assembly 39 is provided includes a tailpipe seal 41 at its lower end which plugs the end of the production tubing 30. The seal assembly 39 includes a hole making system such as a perforating charge 42. This is used to make holes 43 in the tailpipe to permit the flow of the existing well fluids therethrough. The tailpipe seal also has a dual check valve 45 to provide a means permitting flow from the production tubing into the lower part of the well and of preventing fluid from flowing back into the production tubing. This dual check valve is preferably mechanical, which may in its simplest form be a spring loaded ball biased against a sealing seat. The seal assembly 39 is lowered into position by means of a conveyance tool 50, suspended from the end of an the umbilical 49. After the seal assembly is fixed in position the umbilical 49 and conveyance tool 50 are recovered back to surface.
  • Referring now to FIG. 7 a pump assembly 50 is then lowered down the main bore production. The pump assembly includes a pump 53 below which is provided tube holing means and below the holing means well sealing material 52 is provided. At the lowermost end of the well sealing material a bottom plug 51 is provided. The pump assembly is forced down the production tubing by the pressure of a displacement fluid provided above the pump assembly. The displacement fluid could be seawater or even nitrogen. The bottom plug 51 seals against the internal wall of the production tubing so that the contents of the production tubing 55 are then displaced back into the lower part of the well and into the reservoir through the reservoir perforations 56. When the pump assembly has been completely pushed down to the check valve 45, the well sealing material has passed through the plug assembly and into the lowermost part of the well. This sealing material cures in time and provides a permanent seal of the formation.
  • Holes are made in the production tubing 30, by the holing means. This could be any suitable holing means such as by using perforating charges 61. This is shown in FIG. 8. The pump is now activated and the pump causes the displacement fluid in the production tubing 63 to be pumped upwards through the bore in the umbilical 63 and out of the well and the fluids in the annulus 62 correspondingly drain into the production tubing and are similarly pumped out of the well up the umbilical 64 until all the fluid in annulus 62 is removed. There will be a small remainder of fluid in the annulus below the level of the perforations 60. FIG. 9 a shows the structure of the umbilical 63, comprising an outer armoured supporting layer, and an inner layer of lower cables 67 surrounding the bore 64. FIG. 9
  • Whilst in this embodiment the plug, sealing, holing and pumping actions are carried out in that particular sequence using a single pump assembly tool, it is also possible to use separate tools for the separate steps and variations to the sequence.
  • For example, the sealing material could be provided after the holing of the production tubing. The fluids could then be pumped downwards into the reservoir section also instead of out wards to surface, before a sealing material is placed behind them. This would avoid the need to make separate arrangements for the disposal of the fluids pumped out.
  • Referring back to the embodiment shown in the drawings, and in particular FIG. 10 Once the annulus 62 and the area around the holes 60 have been voided of fluids, the pump can be moved up the hole and sealing material pumped down the production tubing annulus 62. This will equalise in both the tubing annulus and tubing ID at equal levels and form a perfect second barrier 70 to the reservoir.
  • Referring to FIG. 11, subsequently, at a suitable depth, a new set of perforations 80 are made and the residual mud in chambers 81 and 82 is allowed to drain into the sump 83 and 84. Preferably the next set of perforations is made at a depth where as many casing can be perforated as possible.
  • If the drained fluid rises above the pump 53, then the excess fluid can be pumped out the well via the umbilical. Finally, Referring to FIG. 12, sealing material 90 can be pumped into any of the voided chambers 91 or 92 and fill all the voided chambers 93 and 94 via the equalisation holes 95. The wellhead and multi casing string could then be safely removed, for example by abrasive jet cut off of the conductor below the mud line and safely recovered back to the vessel.
  • Referring to FIG. 13, in an other embodiment an electric pump 53 is lowered through the production tubing 30 of a cased well. A tailpipe seal assembly 102 is connected below the pump by a space out tube 103. In this embodiment, the umbilical does not have an through bore, and may simply comprise power cables 67 surrounded by a layer of armoured supporting cables 66, as shown in FIG. 9 b.
  • Referring to FIG. 14, once the assembly is at the correct location anchors 104 on the tailpipe assembly 102 engage to secure the pump and tailpipe assembly. Perforation means 121 and 101 on the pump 53 and tailpipe assembly 102 are activated to create holes 110, 120 in the production tubing 30. The tailpipe assembly 102 includes upper and lower seals 106, 109 to isolate the area above and below the holes 110. The pump 53 then forces any well fluid 131 in the production tube above the pump, and the first annulus 132, through the space out tube 103 and check valve 108 to exit the tailpipe assembly and pass into the bottom of the well.
  • Referring to FIG. 15, cemet or other sealing material is then pumped or poured into the production tubing 30 bore 131, the first tubing annulus 132, or both to form a seal above the production packer 45. The pump then pumps a predetermined volume of cement through the tailpipe assembly's check valve and thence beneath the tailpipe assembly 102. The cement is left to set to produce a plug of material at the bottom of the production tubing 30, the first annulus 131, and beneath the tailpipe to the well bottom 140. The a volume of cement sufficient to reach and seal the perforations 56 may be pumped into the bottom of the well.
  • Once this cement has set, a pressure test or a tag test may be carried out to confirm the cement's location and pressure holding capability. If such testing is not required, then the space out tube 103 and pump 53 may be pulled free of the tailpipe assembly and can be moved up the hole, as shown in FIG. 10. The top of the concrete seal may be typically at a depth of 10,000 feet. The pump is raised to between 500-1000 feet from the surface, and then the tube holing means 101 on the pump 53 make a series of holes 111 through the production tubing 30 and casing tubes 31, 32. Provided the fluid remaining the upper portions of annuli 145, 146 etc. are smaller than the voided volume of the lower part of annulus 141 and the production tube bore 140, this fluid will all drain into the lower part of annulus 141 and the production tube bore 140.

Claims (15)

1. A method of abandoning a well, said well comprising at least two concentric conduits defining a main bore and at least one annular chamber there between, comprising the steps of:
providing a perforation in one or more of the conduits,
pumping out the fluid from the annular chamber and/or main bore to create a fluid-free void,
inserting sealing material in the annular chamber and/or main bore to seal it/them.
2. A method according to claim 1 wherein sealing material is inserted into the bore of the innermost conduit to seal it.
3. A method according to claim 1 wherein a tube is introduced and the fluid pumped to the surface through the tube.
4. A method according to claim 1 wherein the fluid is pumped downwards into the well.
5. A method according to claim 1 wherein the sealing material is inserted in the annular chamber before the fluid from the annular chamber is pumped out.
6. A method according to claim 1 wherein perforations are formed in at least one conduit and the annular chamber or chambers are sealed at one level in the well, and then further perforations are formed in a greater number of conduits at a second higher level in the well.
7. A method according to claim 6 wherein after forming the further perforations in the greater number of conduits at the second higher level, the annular chambers between these conduits are sealed.
8. An apparatus for abandoning a well having at least two concentric conduits defining at least one annular chamber there between, the apparatus including a pump and a perforation forming device.
9. An apparatus according to claim 8 wherein there is also provided a valve unit capable of securing itself in an innermost conduit and including a check valve to permit the one-way flow of fluids.
10. An apparatus according to claim 8 wherein the pump and the valve unit are separable.
11. An apparatus according to claim 8 wherein there is provided a cable on which the pump may be lowered into the well.
12. An apparatus according to claim 8 wherein the perforation forming device is incorporated into the pump.
13. An apparatus according to claim 8 wherein the perforation forming device is incorporated into the valve unit.
14. An apparatus according to claim 8 wherein the cable includes a through bore.
15. (canceled)
US10/576,799 2003-10-24 2004-10-22 Method of abandoning a well Abandoned US20070163783A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
GBGB0324823.4A GB0324823D0 (en) 2003-10-24 2003-10-24 A method of abandoning a well
GB0324823.4 2003-10-24
PCT/GB2004/004476 WO2005042918A1 (en) 2003-10-24 2004-10-22 A method of abandoning a well

Publications (1)

Publication Number Publication Date
US20070163783A1 true US20070163783A1 (en) 2007-07-19

Family

ID=29595740

Family Applications (1)

Application Number Title Priority Date Filing Date
US10/576,799 Abandoned US20070163783A1 (en) 2003-10-24 2004-10-22 Method of abandoning a well

Country Status (4)

Country Link
US (1) US20070163783A1 (en)
GB (3) GB0324823D0 (en)
NO (1) NO20062323L (en)
WO (1) WO2005042918A1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012105852A1 (en) * 2011-02-03 2012-08-09 Tco As Tool and method to plug and abandon a well
US20130112434A1 (en) * 2011-11-07 2013-05-09 Halliburton Energy Services, Inc. Apparatus and method of forming a plug in a wellbore
US20130299165A1 (en) * 2012-05-10 2013-11-14 Bp Corporation North America Inc. Methods and systems for long-term monitoring of a well system during abandonment
US20160060766A1 (en) * 2014-08-26 2016-03-03 Matcor, Inc. System including one-piece coiled vent pipe for deep anode cathodic protection and method of installing the same
US20160076341A1 (en) * 2014-09-16 2016-03-17 Wild Well Control, Inc. Cementing system for riserless abandonment operation
US9488024B2 (en) 2012-04-16 2016-11-08 Wild Well Control, Inc. Annulus cementing tool for subsea abandonment operation
WO2018084719A1 (en) * 2016-11-07 2018-05-11 Statoil Petroleum As Method of plugging and pressure testing a well
EP3325761A4 (en) * 2015-07-17 2018-11-14 ConocoPhillips Company Well abandonment using vibration to assist cement placement
US10214988B2 (en) 2015-08-12 2019-02-26 Csi Technologies Llc Riserless abandonment operation using sealant and cement
US10378299B2 (en) 2017-06-08 2019-08-13 Csi Technologies Llc Method of producing resin composite with required thermal and mechanical properties to form a durable well seal in applications
US10428261B2 (en) 2017-06-08 2019-10-01 Csi Technologies Llc Resin composite with overloaded solids for well sealing applications

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1982045A1 (en) * 2006-01-24 2008-10-22 Well Ops Sea PTY Ltd. Remote plugging device for wells
WO2014117848A1 (en) 2013-01-31 2014-08-07 Statoil Petroleum As A method of pressure testing a plugged well
WO2014117846A1 (en) 2013-01-31 2014-08-07 Statoil Petroleum As A method of plugging a well
NO20130438A1 (en) 2013-03-27 2014-09-29 Ikm Cleandrill As Method and apparatus for plugging and leaving operations for subsea wells
US20160348464A1 (en) * 2015-05-27 2016-12-01 Wild Well Control, Inc. Method of sealing wells by injection of sealant
NL2018116B1 (en) * 2017-01-03 2018-07-25 Adriaan Van Der Wal Jan Method for preparing a well for abandonment
KR102561222B1 (en) 2018-07-11 2023-07-28 주식회사 케이엠더블유 Phase shifter

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3939927A (en) * 1974-11-04 1976-02-24 Dresser Industries, Inc. Combined gravel packing and perforating method and apparatus for use in well bores
US4339000A (en) * 1980-08-28 1982-07-13 Cronmiller Clifford P Method and apparatus for a bridge plug anchor assembly for a subsurface well
US4510999A (en) * 1982-06-07 1985-04-16 Geo Vann, Inc. Well cleanup and completion method and apparatus
US4688640A (en) * 1986-06-20 1987-08-25 Shell Offshore Inc. Abandoning offshore well
US4718488A (en) * 1987-03-12 1988-01-12 Camco, Incorporated Pump-out plug system for a well conduit
US5372198A (en) * 1993-02-11 1994-12-13 Halliburton Company Abandonment of sub-sea wells
US5472052A (en) * 1993-06-19 1995-12-05 Head; Philip F. Method of abandoning a well and apparatus therefor
US6478088B1 (en) * 1998-05-04 2002-11-12 Norse Cutting & Abandonment A/S Method for the formation of a plug in a petroleum well
US6595289B2 (en) * 2001-05-04 2003-07-22 Weatherford/Lamb, Inc. Method and apparatus for plugging a wellbore
US7380603B2 (en) * 2002-08-14 2008-06-03 Well-Worx Limited Well abandonment apparatus

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2305683B (en) * 1993-06-19 1997-10-08 Philip Head A method of abandoning a well
GB2309717A (en) * 1996-02-02 1997-08-06 Uwg Ltd Method and apparatus for abandoning sub-sea wells

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3939927A (en) * 1974-11-04 1976-02-24 Dresser Industries, Inc. Combined gravel packing and perforating method and apparatus for use in well bores
US4339000A (en) * 1980-08-28 1982-07-13 Cronmiller Clifford P Method and apparatus for a bridge plug anchor assembly for a subsurface well
US4510999A (en) * 1982-06-07 1985-04-16 Geo Vann, Inc. Well cleanup and completion method and apparatus
US4688640A (en) * 1986-06-20 1987-08-25 Shell Offshore Inc. Abandoning offshore well
US4718488A (en) * 1987-03-12 1988-01-12 Camco, Incorporated Pump-out plug system for a well conduit
US5372198A (en) * 1993-02-11 1994-12-13 Halliburton Company Abandonment of sub-sea wells
US5472052A (en) * 1993-06-19 1995-12-05 Head; Philip F. Method of abandoning a well and apparatus therefor
US6478088B1 (en) * 1998-05-04 2002-11-12 Norse Cutting & Abandonment A/S Method for the formation of a plug in a petroleum well
US6595289B2 (en) * 2001-05-04 2003-07-22 Weatherford/Lamb, Inc. Method and apparatus for plugging a wellbore
US7380603B2 (en) * 2002-08-14 2008-06-03 Well-Worx Limited Well abandonment apparatus

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO335153B1 (en) * 2011-02-03 2014-10-06 Tco As Tool and method for shutting down a well
AU2012211550B2 (en) * 2011-02-03 2016-10-20 Tco As Tool and method to plug and abandon a well
WO2012105852A1 (en) * 2011-02-03 2012-08-09 Tco As Tool and method to plug and abandon a well
US9038740B2 (en) * 2011-11-07 2015-05-26 Halliburton Energy Services, Inc. Apparatus and method of forming a plug in a wellbore
AU2012336142B2 (en) * 2011-11-07 2015-12-24 Halliburton Energy Services, Inc. Apparatus and method of forming a plug in a wellbore
US20130112434A1 (en) * 2011-11-07 2013-05-09 Halliburton Energy Services, Inc. Apparatus and method of forming a plug in a wellbore
US9488024B2 (en) 2012-04-16 2016-11-08 Wild Well Control, Inc. Annulus cementing tool for subsea abandonment operation
US20130299165A1 (en) * 2012-05-10 2013-11-14 Bp Corporation North America Inc. Methods and systems for long-term monitoring of a well system during abandonment
US20160060766A1 (en) * 2014-08-26 2016-03-03 Matcor, Inc. System including one-piece coiled vent pipe for deep anode cathodic protection and method of installing the same
US9587466B2 (en) * 2014-09-16 2017-03-07 Wild Well Control, Inc. Cementing system for riserless abandonment operation
US20160076341A1 (en) * 2014-09-16 2016-03-17 Wild Well Control, Inc. Cementing system for riserless abandonment operation
EP3325761A4 (en) * 2015-07-17 2018-11-14 ConocoPhillips Company Well abandonment using vibration to assist cement placement
US10214988B2 (en) 2015-08-12 2019-02-26 Csi Technologies Llc Riserless abandonment operation using sealant and cement
WO2018084719A1 (en) * 2016-11-07 2018-05-11 Statoil Petroleum As Method of plugging and pressure testing a well
US11274515B2 (en) 2016-11-07 2022-03-15 Equinor Energy As Method of plugging and pressure testing a well
US11680454B2 (en) 2016-11-07 2023-06-20 Equinor Energy As Method of plugging and pressure testing a well
US10378299B2 (en) 2017-06-08 2019-08-13 Csi Technologies Llc Method of producing resin composite with required thermal and mechanical properties to form a durable well seal in applications
US10428261B2 (en) 2017-06-08 2019-10-01 Csi Technologies Llc Resin composite with overloaded solids for well sealing applications

Also Published As

Publication number Publication date
WO2005042918A1 (en) 2005-05-12
NO20062323L (en) 2006-05-22
GB0423522D0 (en) 2004-11-24
GB2426535B (en) 2008-07-23
GB0612195D0 (en) 2006-08-30
GB0324823D0 (en) 2003-11-26
GB2407835A (en) 2005-05-11
GB2426535A (en) 2006-11-29

Similar Documents

Publication Publication Date Title
US20070163783A1 (en) Method of abandoning a well
US4396075A (en) Multiple branch completion with common drilling and casing template
US5456317A (en) Buoyancy assisted running of perforated tubulars
RU2660704C2 (en) Barrier testing method
EP2013446B1 (en) Wellbore system
US5472052A (en) Method of abandoning a well and apparatus therefor
US7549479B2 (en) Tubular flotation with pressurized fluid
NO852498L (en) PROCEDURE AND DEVICE FOR GRILL PACKAGING THROUGH CONNECTIONS.
US6871708B2 (en) Cuttings injection and annulus remediation systems for wellheads
US3459259A (en) Mudline suspension system
US11767732B2 (en) Systems and methods for plugging a well
US20150136406A1 (en) Subsea Intervention Plug Pulling Device
US10107067B2 (en) Methods for placing a barrier material in a wellbore to permanently leave tubing in casing for permanent wellbore abandonment
US3482408A (en) Telescoped caisson
GB2305683A (en) Method of abandoning a well
US3373806A (en) Apparatus and method for drilling wells
US10392885B2 (en) Method and apparatus for plugging a well
US8448709B1 (en) Method of killing an uncontrolled oil-gas fountain appeared after an explosion of an offshore oil platform
US20240368961A1 (en) Protecting the casing-casing annulus in hydrocarbon producing wellbores
US20210396096A1 (en) Method of Maintaining Constant and Elevated Flowline Temperature of Well
CN111727299A (en) Offshore process

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION