JPS6140820B2 - - Google Patents

Info

Publication number
JPS6140820B2
JPS6140820B2 JP4517179A JP4517179A JPS6140820B2 JP S6140820 B2 JPS6140820 B2 JP S6140820B2 JP 4517179 A JP4517179 A JP 4517179A JP 4517179 A JP4517179 A JP 4517179A JP S6140820 B2 JPS6140820 B2 JP S6140820B2
Authority
JP
Japan
Prior art keywords
concrete
water
tremie pipe
liquid
stop bag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4517179A
Other languages
Japanese (ja)
Other versions
JPS55138517A (en
Inventor
Kimihiko Terada
Juichi Sasaki
Hiroshi Matsudate
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP4517179A priority Critical patent/JPS55138517A/en
Publication of JPS55138517A publication Critical patent/JPS55138517A/en
Publication of JPS6140820B2 publication Critical patent/JPS6140820B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

【発明の詳細な説明】 この発明は、根固めコンクリートの打設方法に
関し、特に、掘削穴内に打設する根固めコンクリ
ートの打設終期に、トレミー管内に残留するコン
クリートを、その天端を測定しつつ、液体を内在
した止水袋により、該液体の重量で押し下げて、
液体とコンクリートの干渉を遮断し、以つて、ト
レミー管内の残留コンクリートの天端を、所定位
置まで、液体がコンクリートに悪影響を及ぼさな
い状態で押し下げる。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for placing foot protection concrete, and in particular, at the final stage of placing foot protection concrete in an excavated hole, the concrete remaining in a tremie pipe is measured at its top. while pressing down with the weight of the liquid using a water stop bag containing the liquid,
To block interference between liquid and concrete and push down the top end of residual concrete in a tremie pipe to a predetermined position in a state where the liquid does not adversely affect the concrete.

掘削穴に鋼管、鉄骨柱等からなる杭を建込み、
これをコンクリートで根固めする場合は、第1図
の如くトレミー管2を掘削穴3底部に臨させて、
根固めコンクリート1を打設する。そして打設終
期において、所定量のコンクリートをトレミー管
2内に投入し終ると、トレミー管2内には、特に
第1図Aに示すように、コンクリート1′が残留
した状態となる。これは掘削穴3内の泥水9とト
レミー管2内のコンクリート1′の比重差、およ
びコンクリート1′とトレミー管2の付着抵抗が
原因であり、その結果、打設されたコンクリート
1の天端と、トレミー管2内のコンクリート1′
の天端との間には、高さhの差が生じる。これは
杭の長さが100mにもなると前記高さhは50mに
も及ぶ。
Piles made of steel pipes, steel columns, etc. are erected in the excavated hole.
When cementing this with concrete, place the tremie pipe 2 facing the bottom of the excavation hole 3 as shown in Figure 1.
Place foot protection concrete 1. At the final stage of pouring, when a predetermined amount of concrete has been poured into the tremie pipe 2, concrete 1' remains inside the tremie pipe 2, particularly as shown in FIG. 1A. This is caused by the difference in specific gravity between the muddy water 9 in the excavated hole 3 and the concrete 1' in the tremie pipe 2, and the adhesion resistance between the concrete 1' and the tremie pipe 2. As a result, the top of the poured concrete 1 and concrete 1' in tremie pipe 2.
There is a difference in height h between the top and the top. If the length of the pile is 100 m, the height h will be 50 m.

そこで従来は、トレミー管内のコンクリートを
押し上げるためにトレミー管の上端から水または
泥水等の液体を直接注入し、その重量で押し下げ
る方法と、第1図Bに示すように、特殊な栓Pを
介して同様に液体7により押し下げる方法とがあ
つた。液体を直接注入する方法は、該液体によ
り、トレミー管2内に付着しているコンクリート
が洗に落され、コンクリートのアルカリ成分によ
り劣化、ゲル化した泥水と、管内に付着していた
コンクリートの骨材等とが混合されてスライム状
Sとなる。そして既に打設してあるコンクリート
内に混入し、また該コンクリートの上面に堆積す
ることが多発した。したがつて、このスライム状
のものがコンクリート内に混入した場合には、コ
ンクリートの強度低下を余儀なくされ、また、コ
ンクリート上面に堆積した場合には、壁などの本
体を形成するための、次に打設されるコンクリー
トと、根固めコンクリートとの連続部分が前記堆
積物のために脆弱となる欠点があつた。また、特
殊な栓を介した場合も、栓は順次下方へ移動させ
なければならないから、それ自体をトレミー管に
密着させることはできないため、トレミー管との
間に隙間があつて、結局液体とコンクリートの干
渉を遮断することはできない。したがつて、程度
の差こそあれ、液体を直接注入する前記方法と同
様な欠点が存在した。
Conventionally, in order to push up the concrete inside the tremie pipe, a liquid such as water or muddy water is directly injected from the upper end of the tremie pipe, and the concrete is pushed down by its weight. Similarly, there was a method of pressing down with liquid 7. In the method of directly injecting liquid, the concrete adhering to the inside of the tremie pipe 2 is washed away by the liquid, and the muddy water that has deteriorated and gelled due to the alkaline components of the concrete and the concrete bones adhering to the inside of the pipe are removed. The materials are mixed to form a slime S. It often got mixed into the concrete that had already been placed and was deposited on the upper surface of the concrete. Therefore, if this slime-like material mixes into concrete, it will inevitably reduce the strength of the concrete, and if it accumulates on the top of the concrete, it will become difficult to use next time to form the main body such as a wall. There was a drawback that the continuous portion between the poured concrete and the foot protection concrete became brittle due to the deposits. In addition, even when a special stopper is used, the stopper must be moved downward one after another, so it cannot be brought into close contact with the tremie tube, so there is a gap between the stopper and the tremie tube, and the liquid ends up It is not possible to block concrete interference. Therefore, to a lesser extent, the same disadvantages as the above-mentioned method of directly injecting liquid existed.

またこれら従来の方法によれば、トレミー管内
のコンクリート天端の、打設されたコンクリート
天端との高さの関連を、液体注入とは別個に測定
しなければならない欠点も併存した。
Furthermore, these conventional methods also have the disadvantage that the relationship between the height of the concrete top in the tremie pipe and the poured concrete top must be measured separately from the liquid injection.

そこでこの発明は、これらの欠点を除去するた
めに提供されたものであり、その目的は、トレミ
ー管内においてコンクリートとこれを押下げるた
めの液体との干渉を遮断して、根固めコンクリー
トの強度を確保するとともに、根固めコンクリー
トの上面におけるスライム状沈澱物の発生を防止
することにあり、またその目的は、トレミー管内
のコンクリート押し下げと併行して該コンクリー
トの天端高さを測定し、以つて前記押し下げ位置
を的確に把握することにある。
Therefore, this invention was provided in order to eliminate these drawbacks, and its purpose is to increase the strength of foot-protected concrete by blocking interference between the concrete and the liquid used to push it down in the tremie pipe. The purpose of this is to measure the height of the top of the concrete while pushing down the concrete in the tremie pipe, and to prevent the generation of slime-like precipitates on the top surface of the concrete. The object is to accurately grasp the pressed down position.

すなわちこの発明は、第2図の実施例の如く、
所定量の根固めコンクリート1を、トレミー管2
を介し掘削穴3内に投入した後、トレミー管2内
にその上端から止水袋4を挿入するとともに、該
挿入と同時または前後してトレミー管2内のコン
クリート1′天端を測定するための検尺用重錘5
を紐体6に連結した状態で止水袋4内に挿入し、
該止水袋4内には別に水または泥水等の液体7を
注入して、前記検尺用重錘5によりトレミー管2
内のコンクリート1′天端を測定しながら該液体
7の重さによりトレミー管2内の残留コンクリー
ト1′を押し下げることを特徴とする根固めコン
クリートの打設方法に係る。
That is, this invention, as in the embodiment shown in FIG.
Add a predetermined amount of concrete 1 to the tremie pipe 2
After inserting the concrete into the excavated hole 3 through the tremie pipe 2, insert the waterproof bag 4 into the tremie pipe 2 from its upper end, and measure the top of the concrete 1' inside the tremie pipe 2 at the same time or before or after the insertion. Measurement weight 5
Insert it into the waterproof bag 4 while connected to the string 6,
Separately, a liquid 7 such as water or muddy water is injected into the water-stop bag 4, and the tremie tube 2 is inserted with the measuring weight 5.
The present invention relates to a method of pouring concrete for pouring concrete, which is characterized in that the remaining concrete 1' in the tremie pipe 2 is pushed down by the weight of the liquid 7 while measuring the top of the concrete 1' inside.

つぎにこの発明を第2図に示す実施例にもとづ
いて説明する。
Next, the present invention will be explained based on the embodiment shown in FIG.

掘削穴3内にトレミー管2を介して根固めコン
クリート1を投入する。掘削穴3は、例えば、連
続中壁を構築するための基準杭をなす鋼杭8が建
込まれる。根固めコンクリート1は投入された一
部がトレミー管2内に残留する。これは、前記の
ように、掘削穴3内の泥水9とトレミー管2内の
残留コンクリート1′との比重差、および該コン
クリート1′とトレミー管2との間の付着抵抗が
主とした原因である。
Foot protection concrete 1 is poured into the excavated hole 3 via the tremie pipe 2. In the excavated hole 3, for example, a steel pile 8, which serves as a reference pile for constructing a continuous inner wall, is built. A part of the foot protection concrete 1 that has been poured remains in the tremie pipe 2. As mentioned above, this is mainly caused by the difference in specific gravity between the muddy water 9 in the excavated hole 3 and the residual concrete 1' in the tremie pipe 2, and the adhesion resistance between the concrete 1' and the tremie pipe 2. It is.

そこで、該トレミー管2内にその上端から止水
袋4を挿入する。止水袋4は塩化ビニール樹脂、
ポリエチレン樹脂等からなる可撓性および止水性
のある袋であり、好適には、トレミー管2の形状
に見合う形状とすることが望ましい。この止水袋
4の挿入と同時または前後して、トレミー管2内
の残留コンクリート1′の天端を測定するための
検尺用重錘5を、紐体6に連結した状態で止水袋
4内に挿入する。
Therefore, the water-stop bag 4 is inserted into the tremie tube 2 from its upper end. Water stop bag 4 is made of vinyl chloride resin,
It is a flexible and waterproof bag made of polyethylene resin or the like, and preferably has a shape that matches the shape of the tremie tube 2. At the same time or before or after inserting the water-stop bag 4, a measuring weight 5 for measuring the top of the residual concrete 1' in the tremie pipe 2 is connected to the string 6, and the water-stop bag 4 is inserted into the water-stop bag. Insert within 4.

止水袋4のトレミー管2への挿入前には検尺用
重錘5を予め止水袋4内に挿入しておき、その挿
入された止水袋4をトレミー管2内に挿入すれ
ば、検尺用重錘5は止水袋4の挿入のための重錘
も兼ねる。また、止水袋4のトレミー管2への挿
入と、検尺用重錘5の止水袋4への挿入とが同時
である場合も同様である。さらに止水袋4のトレ
ミー管2への挿入が先行する場合は、止水袋4内
に適宜量の液体7を入れれば、これが重錘の作用
をなす。
Before inserting the water stop bag 4 into the tremie tube 2, the measuring weight 5 is inserted into the water stop bag 4 in advance, and the inserted water stop bag 4 is inserted into the tremie tube 2. The measuring weight 5 also serves as a weight for inserting the water stop bag 4. The same applies when the water-stop bag 4 is inserted into the tremie tube 2 and the measuring weight 5 is inserted into the water-stop bag 4 at the same time. Further, when the water-stop bag 4 is inserted into the tremie tube 2 first, if an appropriate amount of liquid 7 is placed in the water-stop bag 4, this acts as a weight.

検尺用重錘5を先端に連結した紐体6は、これ
に目盛が付されていて、掘削穴3上端においてこ
れを読みとる形式のものでもよく、また、後端が
ドラムに巻かれていて、その繰り出した長さを機
械的に検知する形式のものでもよい。
The string 6 connected to the measuring weight 5 at its tip may have a scale attached thereto and be read at the upper end of the excavated hole 3, or the string 6 may have a rear end wound around a drum. , it may be of a type that mechanically detects the extended length.

そして止水袋4内には、水または泥水等の液体
7を注入する。このときは、止水袋4の底部を介
して、液体7の重量が残留コンクリート1′に可
及的に負荷される。而して液体7により残留コン
クリート1′を押し下げ、該コンクリート1′を掘
削穴3底部に打設する。
Then, a liquid 7 such as water or muddy water is injected into the water-stop bag 4. At this time, the weight of the liquid 7 is applied to the residual concrete 1' as much as possible through the bottom of the water-stop bag 4. The remaining concrete 1' is then pushed down by the liquid 7, and the concrete 1' is poured into the bottom of the excavated hole 3.

かかる液体7による残留コンクリート1′の押
し下げは、検尺用重錘5により天端位置を測定し
ながら、該天端が所定位置に至るまでなされる。
所定位置とは、掘削穴3底部に打設された根固め
コンクリート1の天端と同一高さを意味すること
が通常であるが、他の位置関係である場合もあ
る。かかる所定位置までの押し下げにより根固め
コンクリート1の打設は終了する。
The remaining concrete 1' is pressed down by the liquid 7 while measuring the top position with the measuring weight 5 until the top reaches a predetermined position.
The predetermined position usually means the same height as the top of the foot protection concrete 1 cast at the bottom of the excavated hole 3, but it may be in another positional relationship. By pressing down to this predetermined position, the pouring of the foot protection concrete 1 is completed.

この終了時におけるトレミー管2の下端開口
は、第2図のように、根固めコンクリート1内に
突入している場合と、該コンクリート1の天端に
ある場合とがある。後者の場合は残留コンクリー
ト1′の天端が根固めコンクリート1の天端に近
接するに伴い、トレミー管2を引き上げることに
より前記の位置にする。
At the end of this process, the opening at the lower end of the tremie pipe 2 may protrude into the foot hardening concrete 1, as shown in FIG. 2, or may be at the top end of the concrete 1. In the latter case, as the top of the residual concrete 1' approaches the top of the foot protection concrete 1, the tremie pipe 2 is pulled up to the above position.

ついで、紐体6を引き上げて検尺用重錘5を取
り出し、止水袋4が沈まないように上部に空気が
入つたままで、止水袋4の上部を塞ぎ、止水袋4
が内在する状態のままトレミー管2を掘削穴3か
ら撤去する。しかる後、トレミー管2から止水袋
4を取出し、これを再使用する。
Next, pull up the string 6 to take out the measuring weight 5, close the top of the water stop bag 4 while keeping air in the top so that the water stop bag 4 does not sink, and close the water stop bag 4.
The tremie tube 2 is removed from the excavated hole 3 while still remaining inside. Thereafter, the water stop bag 4 is taken out from the tremie tube 2 and reused.

前記検尺用重錘5の取出しと、トレミー管2の
撤去と、止水袋4の取出しの順序は適宜変えるこ
とができる。しかし止水袋4が内在するままトレ
ミー管2を撤去すれば、液体7が内在するまま止
水袋4を掘削穴3内のトレミー管2から単独で撤
去する場合よりも、止水袋4の撤去は容易であ
り、且つ止水袋4の保護にもなる。また、止水袋
4は液体7を内在させたまま撤去してもよいし、
逆に液体7を抜いた後に撤去してもよい。
The order of taking out the measuring weight 5, removing the tremie tube 2, and taking out the water-stop bag 4 can be changed as appropriate. However, if the tremie tube 2 is removed with the water-stop bag 4 still inside, the water-stop bag 4 will be removed more easily than when the water-stop bag 4 is removed alone from the tremie tube 2 in the excavated hole 3 with the liquid 7 still inside. It is easy to remove and also protects the water stop bag 4. Further, the water stop bag 4 may be removed with the liquid 7 still inside, or
Conversely, it may be removed after the liquid 7 has been drained.

而してこの発明によれば、止水袋により液体と
トレミー管内残留コンクリートとを遮断するから
液体がコンクリートのアルカリ成分により劣化ま
たはゲル化することもなく、これがコンクリート
の骨材と混合されてスライム状となることもな
い。したがつて根固めコンクリート内にこれが混
入してその強度を低下させることもなく、また該
コンクリート上面に堆積することもないから、根
固めコンクリートの強度が確保されるとともに、
次に、根固めコンクリートの上に打設されるコン
クリートの連続部分も強固となる。
According to this invention, since the water-stop bag blocks the liquid from the concrete remaining in the tremie pipe, the liquid does not deteriorate or gel due to the alkaline components of the concrete, and the liquid is mixed with the concrete aggregate to form slime. There will be no condition. Therefore, it does not mix into the foot protection concrete and reduce its strength, nor does it accumulate on the top surface of the concrete, so the strength of the foot protection concrete is ensured, and
Next, the continuous part of the concrete poured on top of the foot protection concrete will also become stronger.

また、この発明によれば、検尺用重錘により常
時残留コンクリートの天端を測定し得るから、該
コンクリートを押し下げ過ぎて、液体がトレミー
管下端開口から根固めコンクリート中に混入され
ることがない。したがつて、該コンクリートの強
度がこの点においても確保されるばかりでなく、
該根固めコンクリートとその上に打設されるコン
クリート連続部分の処理が容易となる。
Further, according to the present invention, since the top of the remaining concrete can be constantly measured using a measuring weight, there is no possibility that the concrete will be pushed down too much and liquid will be mixed into the foot protection concrete from the opening at the lower end of the tremie pipe. do not have. Therefore, not only the strength of the concrete is ensured in this respect, but also
This facilitates the treatment of the foot protection concrete and the continuous portion of concrete poured thereon.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の根固めコンクリートの打設方法
であり、Aは残留コンクリートの残留状態の説明
図、Bは、従来の根固めコンクリートの打設方法
を示す説明図、第2図はこの発明の方法の一実施
例を示す説明図である。 なお、図中1は根固めコンクリート、1′はト
レミー管内のコンクリート、2はトレミー管、3
は掘削穴、4は止水袋、5は検尺用重錘、6は紐
体、7は液体である。
Figure 1 shows the conventional method of placing concrete for foot protection, A is an explanatory diagram of the remaining state of residual concrete, B is an explanatory diagram showing the conventional method for placing concrete for foot protection, and Figure 2 is the invention. FIG. 2 is an explanatory diagram showing an example of the method. In addition, in the figure, 1 is foot protection concrete, 1' is concrete in the tremie pipe, 2 is tremie pipe, and 3 is concrete.
4 is a water stop bag, 5 is a measuring weight, 6 is a string, and 7 is a liquid.

Claims (1)

【特許請求の範囲】[Claims] 1 所定量の根固めコンクリートを、トレミー管
を介し掘削穴内に投入した後、トレミー管内にそ
の上端から止水袋を挿入するとともに、該挿入と
同時または前後してトレミー管内のコンクリート
天端を測定するための検尺用重錘を紐体に連結し
た状態で止水袋内に挿入し、該止水袋内には別に
水または泥水等の液体を注入して、前記検尺用重
錘によりトレミー管内のコンクリート天端を測定
しながら該液体の重さによりトレミー管内の残留
コンクリートを押し下げることを特徴とする根固
めコンクリートの打設方法。
1. After putting a predetermined amount of cemented concrete into the excavated hole through the tremie pipe, insert a water stop bag into the tremie pipe from its upper end, and measure the top of the concrete inside the tremie pipe at the same time or before or after the insertion. A measuring weight connected to a string is inserted into a water-stop bag, and a liquid such as water or muddy water is separately poured into the water-stop bag, and the measuring weight is connected to a string. A method for pouring concrete with foot protection, which comprises pressing down residual concrete in a tremie pipe by the weight of the liquid while measuring the top of the concrete in the tremie pipe.
JP4517179A 1979-04-13 1979-04-13 Casting method of root-consolidating cement Granted JPS55138517A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4517179A JPS55138517A (en) 1979-04-13 1979-04-13 Casting method of root-consolidating cement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4517179A JPS55138517A (en) 1979-04-13 1979-04-13 Casting method of root-consolidating cement

Publications (2)

Publication Number Publication Date
JPS55138517A JPS55138517A (en) 1980-10-29
JPS6140820B2 true JPS6140820B2 (en) 1986-09-11

Family

ID=12711810

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4517179A Granted JPS55138517A (en) 1979-04-13 1979-04-13 Casting method of root-consolidating cement

Country Status (1)

Country Link
JP (1) JPS55138517A (en)

Also Published As

Publication number Publication date
JPS55138517A (en) 1980-10-29

Similar Documents

Publication Publication Date Title
JPS6140820B2 (en)
CN211571665U (en) Fixing structure of concrete surface soil pressure cell
US1753776A (en) Filled concrete block and method of making the same
JPS5771923A (en) Construction work of continuous underground wall
US2050215A (en) Apparatus for driving pile shells
KR0148168B1 (en) Woorking method of underground foundation wall
JPS60129206A (en) Formwork for manufacturing cavity
JPS6160206B2 (en)
JPS56163327A (en) Repairing method for embedded concrete pipe
JPS60242217A (en) Formwork for pile head
KR101342180B1 (en) Hybrid shoe member for extracting pile and extracting method using thereof
JP2933418B2 (en) How to fill underground cavities
JP3756679B2 (en) Formwork for connecting manhole pipe and construction method using the same
JPS60109414A (en) Head treatment work of cast-in-place pile
JPH089226Y2 (en) Dual structure hardened soil cement extractor
JPS5685021A (en) Driving method of pile
JPH01223234A (en) Fixation of insertion pipe for sheath pipe
JPH037763B2 (en)
JPS609172B2 (en) How to build underground structures
JPS6312962B2 (en)
JPS5724720A (en) Increasing method for pull resistance of structure material driven into ground
JP2629438B2 (en) Grout filling method for rod drawing hole of concrete wall
JPS5842339B2 (en) A formwork for pouring concrete into the bottom of a pit to connect the lower half of three or more sewage pipes opened in a branched manner.
JPH0369716A (en) Method of processing upper defective concrete of cast-in-place underground concrete building
CS245853B1 (en) Subterranean wall's building process