JP3401282B2 - Construction method of soil between unit type buildings - Google Patents
Construction method of soil between unit type buildingsInfo
- Publication number
- JP3401282B2 JP3401282B2 JP01167293A JP1167293A JP3401282B2 JP 3401282 B2 JP3401282 B2 JP 3401282B2 JP 01167293 A JP01167293 A JP 01167293A JP 1167293 A JP1167293 A JP 1167293A JP 3401282 B2 JP3401282 B2 JP 3401282B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- foundation
- soil
- floor
- unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Floor Finish (AREA)
Description
【発明の詳細な説明】
【0001】
【産業上の利用分野】本発明は、ユニット式建物におけ
る土間の施工方法に関し、更に詳しくは、複数の建物ユ
ニットの組合せによって建てられるユニット式建物にお
いて、その建物内の少なくとも一部の建物ユニットの床
側に土間を形成する土間の施工方法に関する。
【0002】
【背景技術】従来、複数の建物ユニットの組合せによっ
て建てられるユニット式建物において、その建物内の少
なくとも一部の建物ユニットの床側に土間を形成する場
合、次の方法が採られている。まず、基礎上に土間を構
成する建物ユニットを据え付けたのち、その建物ユニッ
トの床梁内面側から基礎の内面に沿って所定の厚みを有
する発泡プラスチック系断熱材を貼り付け、この内部に
地盤より複数層の盛土をし、それぞれ充分締め固める。
ついで、砕石を搬入し、一様な厚さにならし作業を行
い、続いて、その上に防湿フィルムを全面に敷込んだの
ち、土間コンクリートを打設し、最後に仕上げモルタル
を打設して土間を形成する。
【0003】
【発明が解決しようとする課題】従来の土間の施工方法
では、基礎上に建物ユニットを据え付けたのち、各建物
ユニットの床側に砕石を搬入し、ならし作業を行い、そ
の上から土間コンクリートを打設しているため、砕石の
搬入作業において、建物ユニットの床梁を跨ぎながら砕
石を各建物ユニット内に搬入しなければならない。した
がって、このような従来方法では、砕石の搬入作業がや
りずらく面倒であった。
【0004】ここに、本発明の目的は、このような従来
の問題を解消し、簡易な作業方法によりユニット式建物
内の少なくとも一部の建物ユニットの床側に土間を形成
することができるユニット式建物における土間の施工方
法を提供することにある。
【0005】
【課題を解決するための手段】本発明のユニット式建物
における土間の施工方法は、上記課題を解決するため、
次の構成を備える。つまり、複数の建物ユニットの組合
せによって建てられるユニット式建物において少なくと
も一部の建物ユニットの床側に土間を形成する施工方法
であって、地盤に基礎を形成したのち、その基礎内にお
いて基礎上に据え付けられる建物ユニットの床梁が位置
しない場所に砕石を予め搬入しておき、建物ユニットを
基礎上に据え付けたのちに前記砕石をならし、このの
ち、砕石の上からコンクリートを打設することにより、
建物ユニットの床梁をコンクリート内に埋設した状態で
土間を形成することを特徴としている。
【0006】
【作用】土間の施工に当たっては、まず、地盤に基礎を
形成する。このとき、基礎の形成に先立って根切りによ
って発生した土を基礎内に積んでおく。また、基礎の立
ち上がり部の高さについては、通常の基礎の高さよりも
低く形成しておくと、最後の土間レベルを低くできる。
【0007】ついで、その基礎内において、基礎上に据
え付けられる建物ユニットの床梁が位置しない場所に予
め砕石を搬入しておく。このようにすると、建物ユニッ
トを基礎に据え付け後に砕石を搬入する方法の場合、建
物ユニットの床梁を跨いで砕石の搬入作業をしなければ
ならないから、これに比べ作業を楽に行える利点があ
る。
【0008】ついで、建物ユニットを基礎上に据え付け
たのちに前記砕石をならし、こののち、砕石の上からコ
ンクリートを打設することにより、建物ユニットの床梁
をコンクリート内に埋設した状態で、土間を形成する。
従って、建物ユニットの床梁が露出することがなく土間
への出入りに際して床梁を跨がなくてもよい。
【0009】
【実施例】以下、本発明のユニット式建物における土間
の施工方法を図を参照しながら詳細に説明する。まず、
図1(A)(B)に示す如く、地盤11を平面矩形状に
根切りし基礎成形用溝12を形成する。このとき、通常
の建物の基礎を形成する場合に比べ根切り幅も大きくか
つ根切底も深く形成しておく。従って、根切土13も大
量に発生するが、それは溝12によって囲まれた建物内
の地盤11上に積んでおく。基礎成形用溝12の底部に
は砕石14を敷き詰め、必要に応じて捨てコンクリート
を打つ。
【0010】次に、図2(A)(B)に示す如く、基礎
成形用溝12の底部に敷き詰めた砕石14の上に基礎2
1を形成する。これには、まず、フーチン部22を形成
したのち、その上に型枠を組んで立上がり部23を形成
する。このとき、立上がり部23の高さについては、通
常の基礎の高さよりも低く形成しておく。このようにす
ると、最後に形成される土間の床レベルを低くできる。
【0011】次に、図3(A)(B)に示す如く、基礎
21と基礎成形用溝12との隙間に根切土13を埋め戻
す。また、基礎21内の地盤11上において、根切土1
3を使って盛土31を形成する。この際、その根切土1
3が土間コンクリート下に使用するには不可な土質であ
れば、良土を別途使用する。良土であっても、転圧、水
締を確実に行っておく。これにより、土間コンクリート
の不同沈下およびクラックの発生を防げる。
【0012】また、盛土31には、基礎21上に据え付
けられる建物ユニットの床梁が位置する場所を予め確認
し、その場所を所定深さ掘り下げて溝32を形成してお
く。また、その溝32を除く他の場所、つまり、建物ユ
ニットの床梁が位置しない場所には、予め砕石33を各
建物ユニットごとに搬入しておく。このようにすると、
建物ユニットを基礎に据え付け後に砕石を搬入する場
合、建物ユニットの床梁を跨いで砕石の搬入作業をしな
ければならないから、これに比べ作業を楽に行える利点
がある。
【0013】次に、図4(A)(B)に示す如く、複数
の建物ユニット41を基礎21上の所定位置に据え付け
る。これには、クレーンを使用し、トラックなどで工場
から輸送されてきた建物ユニット41を順次吊り上げ、
基礎21上の所定位置まで搬入したのち、基礎21上に
据え付ける。各建物ユニット41は、四隅に配置された
複数の柱42、この柱42の上端間を連結する天井梁
(図示省略)および下端間を連結する床梁44によって
形成された直方体状の骨組みを備え、その骨組みに外壁
や内壁などが適宜取り付けられた構造である。各建物ユ
ニット41を基礎21上に据え付けたのち、建物ユニッ
ト41の隣接する床梁44に跨がって梁カバー45を被
せる。
【0014】最後に、図5(A)(B)に示す如く、各
建物ユニット41ごとに搬入した砕石33を一様な厚み
にならしたのち、その上から土間コンクリート51を打
設することにより、建物ユニット41の床梁44をコン
クリート51内に埋設した状 態で土間を形成する。従っ
て、建物ユニット41の床梁44が露出することがなく
土間への出入りに際して床梁を跨がなくてもよい。
【0015】なお、図6に示す如く、各建物ユニット4
1については、工場において、隣接する床梁44の上部
に軟質発泡スチロール板46を装着し、その周囲を耐水
シート47で覆っておく。これにより、土間からの力が
床梁44にかからないような構造になっている。また、
砕石33をならしたのち、その上から土間コンクリート
51を打設する前に、予め砕石33に目つぶし砂を入
れ、かつ、全面に防湿シート52を敷込んでおくととも
に、内部に補強鉄筋53を配置しておけば強度を確保で
きる。
【0016】従って、本実施例の施工方法によれば、建
物ユニット41の床梁44を土間内に埋設した状態とし
ているから、建物ユニットの床梁が露出することがなく
土間への出入りに際して床梁を跨がなくてもよい。もと
より、建築現場において床梁を取り外す必要もなく、ま
た、予め工場から床梁を取り付けないで建築現場まで輸
送した場合の不都合もない。
【0017】また、基礎21内の盛土31上には、建物
ユニットの床梁が位置する場所を予め確認し、建物ユニ
ット41の床梁44が位置しない場所に予め砕石33を
各建物ユニット41ごとに搬入しておくようにしたの
で、砕石33の搬入作業を楽に行うことができる。ちな
みに、建物ユニットを基礎に据え付け後に砕石を搬入し
ようとすると、建物ユニットの床梁を跨いで砕石の搬入
作業をしなければならないから、これに比べ作業を楽に
行える利点がある。
【0018】
【発明の効果】以上の通り、本発明のユニット式建物に
おける土間の施工方法によれば、簡易な作業方法により
建物内の一部の建物ユニットの床側に土間を簡単に形成
することができる。BACKGROUND OF THE INVENTION [0001] Field of the Invention The present invention relates to a method of constructing the dirt floor in unitary building, more particularly, in the unit formula buildings be built by combining a plurality of building units, The floor of at least some building units in the building
The present invention relates to a method for constructing a dirt between the sides . 2. Description of the Related Art Conventionally, in a unit-type building constructed by combining a plurality of building units, the following method is used when a floor is formed on the floor side of at least a part of the building units in the building. I have. First, after installing the building unit that constitutes the dirt on the foundation, paste a foamed plastic-based heat insulating material with a predetermined thickness along the inner surface of the foundation from the inner side of the floor beam of the building unit, and from inside the ground Fill multiple layers and squeeze each well.
Next, carry in the crushed stone, leveling work to a uniform thickness, then lay a moisture-proof film on the whole surface, then cast concrete between the soil, and finally cast a finishing mortar. To form a soil. [0003] In the conventional method of constructing a sill, a building unit is installed on a foundation, crushed stones are carried in to the floor side of each building unit, a leveling operation is performed, and then a work is performed. In order to carry in crushed stone, the crushed stone must be carried into each building unit while straddling the floor beam of the building unit . did
Therefore, in such a conventional method, the work of carrying the crushed stone is difficult and troublesome. [0004] It is an object of the present invention to solve such a conventional problem and to provide a unit capable of forming a dirt on the floor side of at least a part of building units in a unit building by a simple working method. It is an object of the present invention to provide a method for constructing a soil in a type building. [0005] The method for constructing a dirt floor in a unit-type building according to the present invention is intended to solve the above-mentioned problems.
The following configuration is provided. In other words, in a unit-type building constructed by a combination of a plurality of building units , at least a construction method of forming a soil on the floor side of some building units, and after forming a foundation on the ground, In the foundation, crushed stone is brought in advance to a place where the floor beam of the building unit installed on the foundation is not located, the crushed stone is leveled after the building unit is installed on the foundation, and then the concrete is crushed from the crushed stone. by Da設the,
The floor beams of the building unit is characterized by forming a <br/> dirt floor in a state buried in the concrete. In the construction of the soil, first, a foundation is formed on the ground. At this time, the soil generated by root cutting is piled up in the foundation before the foundation is formed. If the height of the rising portion of the foundation is formed lower than the height of the normal foundation, the last soil level can be lowered. [0007] Then, crushed stone is transported in advance in a place where the floor beam of the building unit installed on the foundation is not located. In this case, in the case of the method of carrying crushed stone after the building unit is installed on the foundation, there is an advantage that the work can be carried out more easily because the crushed stone must be carried over the floor beam of the building unit. Then, after the building unit is installed on the foundation, the crushed stone is leveled, and then concrete is poured from the crushed stone, so that the floor beam of the building unit is buried in the concrete . Form a dirt floor.
Therefore, the floor beams of the building unit do not need to be exposed, and the floor beams do not need to be straddled when entering or exiting the soil. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a method for constructing a dirt floor in a unit building according to the present invention will be described in detail with reference to the drawings. First,
As shown in FIGS. 1A and 1B, the ground 11 is rooted into a rectangular shape in a plane to form a groove 12 for foundation molding. At this time, the root width is made larger and the root is deeper than in the case where the foundation of an ordinary building is formed. Accordingly, a large amount of the root cuttings 13 are generated, but are piled on the ground 11 in the building surrounded by the grooves 12. Crushed stones 14 are spread on the bottom of the groove 12 for foundation molding, and discarded concrete is hit as necessary. Next, as shown in FIGS. 2A and 2B, the foundation 2 is placed on the crushed stone 14 spread on the bottom of the groove 12 for foundation molding.
Form one. For this, first, the footing portion 22 is formed, and then a rising portion 23 is formed by assembling a mold thereon. At this time, the height of the rising portion 23 is formed lower than the height of a normal foundation. In this way, the floor level between soils formed last can be lowered. Next, as shown in FIGS. 3A and 3B, the root cuttings 13 are buried in the gaps between the foundation 21 and the foundation forming grooves 12. In addition, on the ground 11 in the foundation 21,
The embankment 31 is formed using 3. At this time, the root cut 1
If the soil is not suitable for use under soil concrete, use good soil separately. Even if the soil is good, be sure to perform compaction and watertightness. This can prevent uneven settlement of the concrete between the soil and occurrence of cracks. Further, in the embankment 31, a place where a floor beam of a building unit installed on the foundation 21 is located is confirmed in advance, and the place is dug down to a predetermined depth to form a groove 32. In addition, the crushed stones 33 are previously carried in each building unit to a place other than the groove 32, that is, a place where the floor beams of the building units are not located. This way,
When crushed stones are carried in after the building unit is installed on the foundation, the crushed stones must be carried over the floor beams of the building unit, which is advantageous in that the work can be performed more easily. Next, as shown in FIGS. 4A and 4B, a plurality of building units 41 are installed at predetermined positions on the foundation 21. For this purpose, a crane is used to sequentially lift the building units 41 transported from the factory by truck or the like,
After being carried to a predetermined position on the foundation 21, it is installed on the foundation 21. Each building unit 41 has a rectangular parallelepiped frame formed by a plurality of columns 42 arranged at four corners, a ceiling beam (not shown) connecting the upper ends of the columns 42, and a floor beam 44 connecting the lower ends. In this structure, an outer wall, an inner wall, and the like are appropriately attached to the skeleton. After each building unit 41 is installed on the foundation 21, the beam cover 45 is put over the floor beam 44 adjacent to the building unit 41. [0014] Finally, as shown in FIG. 5 (A) (B), after which leveling the crushed stone 33 is carried into each building unit 41 to a uniform thickness, by Da設the dirt floor concrete 51 thereon the floor beams 44 of the building unit 41 to form a dirt floor in embedded tongue state in the concrete 51. Therefore, the floor beams 44 of the building unit 41 do not need to be exposed, and the floor beams do not need to be straddled when entering and exiting the soil. As shown in FIG. 6, each building unit 4
Regarding 1, a flexible styrofoam plate 46 is attached to the upper part of the adjacent floor beam 44 at the factory, and the periphery thereof is covered with a waterproof sheet 47. Thus, the structure is such that the force from the soil is not applied to the floor beam 44. Also,
After leveling the crushed stones 33, before pouring the slab concrete 51 from above, crushed sand is preliminarily filled with crushed sand, and a moisture-proof sheet 52 is laid on the entire surface, and a reinforcing reinforcing bar 53 is arranged inside. By doing so, the strength can be secured. Therefore, according to the construction method of this embodiment, the floor beams 44 of the building unit 41 are buried in the soil.
Therefore, the floor beams of the building unit do not have to be exposed, and the floor beams do not have to be straddled when entering or exiting the soil. Of course, there is no need to remove floor beams at the construction site, and there is no inconvenience when transporting from the factory to the construction site without attaching floor beams in advance. Further, on the embankment 31 in the foundation 21, the location where the floor beam of the building unit is located is confirmed in advance, and the crushed stone 33 is placed in advance in a location where the floor beam 44 of the building unit 41 is not located. The crushed stones 33 can be easily loaded. By the way, if the crushed stone is to be carried in after the building unit is installed on the foundation, the crushed stone must be carried in across the floor beams of the building unit, which is advantageous in that the work can be performed more easily. As described above, according to the method for constructing the dirt in the unit-type building according to the present invention , the dirt is easily formed on the floor side of some building units in the building by a simple working method. be able to.
【図面の簡単な説明】
【図1】 本発明の施工方法における根切り工程を示す
図である。
【図2】 同上施工方法における基礎成形工程を示す図
である。
【図3】 同上施工方法における盛土工程を示す図であ
る。
【図4】 同上施工方法におけるユニット据付工程を示
す図である。
【図5】 同上施工方法におけるコンクリート打設工程
を示す図である。
【図6】 同上施工方法によって形成される隣接する建
物ユニット間の土間構造を示す図である。
【符号の説明】
11…地盤、12…基礎成形用溝、21…基礎、22…
ベース部、23…立上がり部、31…盛土、32…溝、
33…砕石、41…建物ユニット、44…床梁、51…
土間コンクリート。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a view showing a root cutting step in a construction method of the present invention. FIG. 2 is a view showing a foundation forming step in the construction method. FIG. 3 is a view showing an embankment step in the construction method. FIG. 4 is a view showing a unit installation process in the construction method. FIG. 5 is a view showing a concrete placing step in the construction method. FIG. 6 is a view showing a soil structure between adjacent building units formed by the above construction method. [Description of Signs] 11 ... ground, 12 ... groove for foundation molding, 21 ... foundation, 22 ...
Base part, 23 ... rising part, 31 ... embankment, 32 ... groove,
33: crushed stone, 41: building unit, 44: floor beam, 51 ...
Soil concrete.
Claims (1)
てられるユニット式建物において少なくとも一部の建物
ユニットの床側に土間を形成する施工方法であって、 地盤に基礎を形成したのち、 その基礎内において基礎上に据え付けられる建物ユニッ
トの床梁が位置しない場所に砕石を予め搬入しておき、 建物ユニットを基礎上に据え付けたのちに前記砕石をな
らし、 こののち、砕石の上からコンクリートを打設することに
より、建物ユニットの床梁をコンクリート内に埋設した
状態で土間を形成することを特徴とするユニット式建物
における土間の施工方法。(57) at least a portion of the building 11. Claims: 1. A unitary building that is built by a combination of building units
A construction method for forming a earthen floor side of the unit, after forming the foundation ground, in advance carried the crushed stone to the location where the floor beams without the position of the building unit to be mounted on a foundation within the foundation, break the crushed stone into After mounting the building unit on a foundation, Thereafter, to Da設concrete from the top of the crushed stone
More, and the floor beams of the building unit is embedded in the concrete
A method for constructing a soil in a unit-type building , wherein the soil is formed in a state .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP01167293A JP3401282B2 (en) | 1993-01-27 | 1993-01-27 | Construction method of soil between unit type buildings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP01167293A JP3401282B2 (en) | 1993-01-27 | 1993-01-27 | Construction method of soil between unit type buildings |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06220980A JPH06220980A (en) | 1994-08-09 |
JP3401282B2 true JP3401282B2 (en) | 2003-04-28 |
Family
ID=11784483
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP01167293A Expired - Fee Related JP3401282B2 (en) | 1993-01-27 | 1993-01-27 | Construction method of soil between unit type buildings |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3401282B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010127041A (en) * | 2008-11-28 | 2010-06-10 | Taishin Giken Fukuda:Kk | Method for constructing shelter |
-
1993
- 1993-01-27 JP JP01167293A patent/JP3401282B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH06220980A (en) | 1994-08-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4799348A (en) | Method and equipment for making a rigid slab enabling to carry a building | |
CA1298090C (en) | Foundation for wooden buildings and construction method thereof | |
JPH11336099A (en) | Construction method of basement | |
JP3401282B2 (en) | Construction method of soil between unit type buildings | |
JP3173701B2 (en) | Basic structure of building and its construction method | |
JP2927727B2 (en) | Construction method of underground structure | |
JPH09111776A (en) | Basement and construction method thereof | |
JP3090642B2 (en) | Construction method of foundation and foundation for wooden buildings, and structure of foundation and foundation for wooden buildings | |
JP2001059228A (en) | Mat foundation structure for detached house and its constructing method | |
JPS601458B2 (en) | Precast concrete basement construction method | |
JP3065066B1 (en) | Soil floor structure and method of construction | |
JPH11350500A (en) | Foundation structure of building and foundation work method | |
JP2004308134A (en) | Construction method of mat foundation for wooden house | |
JPS621930A (en) | Foundation structure of underground structure | |
JP3223973B2 (en) | Installation method of precast reinforced concrete fabric foundation members | |
KR100386696B1 (en) | Foundation concrete pouring method of building structure | |
JP2874860B2 (en) | Soil floor structure and method of construction | |
JPH11172757A (en) | Building structure | |
JPS6043529A (en) | Mat foundation and its construction | |
JPS5812917Y2 (en) | Foundation formwork support structure | |
JP2992160B2 (en) | Precast foundation structure | |
JP2874862B1 (en) | Soil floor structure and method of construction | |
JPH03228921A (en) | Execution method for concrete foundation work | |
JP2824374B2 (en) | Concrete block for foundation, manufacturing method thereof, and foundation construction method using the same | |
JP2001131988A (en) | Foundation structure of building, and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20020910 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20030204 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080221 Year of fee payment: 5 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080221 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090221 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090221 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100221 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100221 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110221 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110221 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120221 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |