CN115977363B - Operating bench for repairing water-cooled furnace cover of refining furnace - Google Patents

Operating bench for repairing water-cooled furnace cover of refining furnace Download PDF

Info

Publication number
CN115977363B
CN115977363B CN202211618175.XA CN202211618175A CN115977363B CN 115977363 B CN115977363 B CN 115977363B CN 202211618175 A CN202211618175 A CN 202211618175A CN 115977363 B CN115977363 B CN 115977363B
Authority
CN
China
Prior art keywords
construction platform
cover
sleeve
water
shielding cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211618175.XA
Other languages
Chinese (zh)
Other versions
CN115977363A (en
Inventor
李达
陈亮
曾祥勇
赵超鹏
曹金忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN202211618175.XA priority Critical patent/CN115977363B/en
Publication of CN115977363A publication Critical patent/CN115977363A/en
Application granted granted Critical
Publication of CN115977363B publication Critical patent/CN115977363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Vertical, Hearth, Or Arc Furnaces (AREA)
  • Furnace Details (AREA)

Abstract

The invention provides an operation bench for repairing a water-cooled furnace cover of a refining furnace, wherein a bottom plate is connected with a construction platform through a vertically arranged sleeve, and the construction platform is provided with a mounting hole communicated with the sleeve; the sleeves are uniformly arranged at intervals; the lower part of the shielding cover is connected with a stand column in sliding fit with the sleeve, and the stand column penetrates through a mounting hole on the construction platform and is mounted in the sleeve; the upright posts are uniformly arranged at intervals; the sleeve is provided with a first connecting hole, the upright post is provided with a second connecting hole, and a plurality of first connecting holes and second connecting holes are uniformly arranged at intervals along the vertical direction; the sleeve is locked with the upright post through a locking piece; a jacking device is arranged below the shielding cover and drives the shielding cover to move up and down; the construction platform is provided with a window for personnel to pass through, and a cat ladder which is correspondingly arranged with the window is arranged between the bottom plate and the construction platform. The welding repair and cleaning operation of workers on the pipe wall of the cooling water pipe positioned on the inner side of the water-cooling furnace cover is safer.

Description

Operating bench for repairing water-cooled furnace cover of refining furnace
Technical Field
The invention belongs to the technical field of repair auxiliary devices for water-cooled furnace covers of refining furnaces, and particularly relates to an operation bench for repairing a water-cooled furnace cover of a refining furnace.
Background
The LF refining furnace water-cooled furnace cover is a downward opening cover-shaped structure formed by surrounding a circle of cooling water pipes. After long-time use, the water-cooled furnace cover is subjected to intermittent cold and hot alternate stimulation in the production process, fatigue cracks are easy to appear on the pipe wall of the cooling water pipe positioned on the inner side of the water-cooled furnace cover, so that the pipe is cracked and leaked, the production efficiency is seriously affected, and great potential safety hazards exist. Meanwhile, steel slag in the refining furnace is easy to splash and adhere to the pipe wall of a cooling water pipe in the water-cooling furnace cover.
The workers weld repair and clean the cooling water pipe wall positioned on the inner side of the water-cooling furnace cover, and after the temperature of the electrodes is reduced to the safe temperature, the workers set up a crawling ladder and stand on the crawling ladder to weld repair and clean the cooling water pipe wall positioned on the inner side of the water-cooling furnace cover. Or after the electrode which passes through the top wall of the water-cooled furnace cover is lifted off, a worker establishes a crawling ladder and stands on the crawling ladder to repair and clean the pipe wall of the cooling water pipe which is positioned on the inner side of the water-cooled furnace cover. During operation, the large steel slag falling off from the top of the inner wall of the water-cooled furnace cover is easy to crush workers, and has great potential safety hazards. In either the case where the temperature of the electrode is lowered to a safe temperature or the case where the electrode is lifted off, a long time is required, and there is a problem in that the operation efficiency is low.
Disclosure of Invention
The invention aims to solve the technical problem of providing an operation bench for repairing a water-cooled furnace cover of a refining furnace, which ensures that workers are safer when carrying out welding repair and cleaning operation on the pipe wall of a cooling water pipe positioned on the inner side of the water-cooled furnace cover.
The technical scheme adopted for solving the technical problems is as follows: the operation bench for repairing the water-cooled furnace cover of the refining furnace comprises a bottom plate, a construction platform and a shielding cover which are arranged from bottom to top at intervals;
the bottom plate is connected with the construction platform through a vertically arranged sleeve, and the construction platform is provided with a mounting hole communicated with the sleeve; the sleeves are uniformly arranged at intervals;
the lower part of the shielding cover is connected with an upright post which is in sliding fit with the sleeve, and the upright post penetrates through a mounting hole on the construction platform and is mounted in the sleeve; the upright posts are uniformly arranged at intervals;
the sleeve is provided with a first connecting hole, the upright post is provided with a second connecting hole, and a plurality of first connecting holes and second connecting holes are uniformly arranged at intervals along the vertical direction; the sleeve is locked with the upright post through a locking piece;
a jacking device is arranged below the shielding cover and drives the shielding cover to move up and down;
the construction platform is provided with a window for personnel to pass through, and a cat ladder which is arranged corresponding to the window is arranged between the bottom plate and the construction platform.
Further, a through hole for the jacking device to pass through is formed in the construction platform, and the jacking device is connected with the construction platform through a connecting piece.
Further, the jacking device is a hydraulic cylinder.
Further, the connecting piece comprises a U-shaped seat with an upward opening; the U-shaped seat is positioned below the construction platform;
one side arm of the U-shaped seat is connected with the lower surface of the construction platform, and the other side arm is connected with a trunnion on the cylinder body of the hydraulic cylinder.
Further, the shielding cover comprises a shell and a water pipe arranged in the inner cavity of the shell; the water pipe is arranged in a winding way on the horizontal plane; the water inlet and the water outlet of the water pipe extend out of the shell.
Further, the device also comprises an annular guide rail and a rolling trolley;
the annular guide rail is arranged adjacent to the shielding cover and is positioned below the shielding cover; the annular guide rail is connected with the shielding cover through a connecting block; the annular guide rail is arranged along the periphery of the shielding cover;
the rollers of the rolling trolley are in rolling fit with the annular guide rail;
the roller seat of the rolling trolley is connected with a barrel body, and the opening of the barrel body is upward and positioned at the outer side of the shielding cover.
Further, the device also comprises a transportation trolley, and the bottom plate is fixedly arranged on the table top of the transportation trolley.
Further, a first protective guard is arranged on the periphery of the bottom plate, and a second protective guard is arranged on the periphery of the construction platform.
Further, an openable cover plate is arranged at the window.
Further, the periphery of shielding lid is provided with vertical arrangement's annular baffle, annular baffle is located shielding lid's top.
Compared with the prior art, the invention has the beneficial effects that: the invention provides an operation bench for repairing a water-cooled furnace cover of a refining furnace, which ensures that workers are safer when carrying out welding repair and cleaning operation on the pipe wall of a cooling water pipe positioned on the inner side of the water-cooled furnace cover. The steel slag falling off from the top of the inner wall of the water-cooled furnace cover falls on the shielding cover, so that the workers are prevented from being injured by the smashing. The shielding cover also plays a role in heat insulation, workers do not need to enter the field again after the electrodes are cooled, time is saved, efficiency is improved, and safety and reliability are achieved. The steel slag cleaned from the inner side of the water-cooled furnace cover falls into the barrel body.
Drawings
FIG. 1 is a front view of the invention below the water cooled furnace cover of a refining furnace;
FIG. 2 is a perspective view of the present invention;
FIG. 3 is a schematic top view of the construction platform of the present invention;
FIG. 4 is a schematic illustration of the location of a water tube of the present invention;
FIG. 5 is an enlarged view of section A of the present invention;
FIG. 6 is an enlarged view of section B of the present invention;
reference numerals: 1-a bottom plate; 2-a construction platform; 201-mounting holes; 202-window; 203-a through hole; 3-a shielding cover; 301-a water pipe; 302-water inlet; 303-a water outlet; 304-an annular baffle; 4-sleeve; 401-first connection holes; 5-stand columns; 501-a second connection hole; 6-climbing a ladder; 7-jacking device; 8-trunnion; 9-U-shaped seats; 10-a first guard rail; 11-a second guard rail; 12-a transportation trolley; 13-a water-cooling furnace cover; 14-electrodes; 15-an annular guide rail; 16-connecting blocks; 17-a rolling trolley; 18-a barrel body; 19-mounting a tube.
Detailed Description
The invention will be further described with reference to the drawings and examples.
The operation bench for repairing the water-cooled furnace cover of the refining furnace comprises a bottom plate 1, a construction platform 2 and a shielding cover 3 which are arranged from bottom to top at intervals; the base plate 1 is connected with the construction platform 2 through a vertically arranged sleeve 4, and the construction platform 2 is provided with a mounting hole 201 communicated with the sleeve 4; the sleeves 4 are uniformly arranged at intervals; a stand column 5 in sliding fit with the sleeve 4 is connected below the shielding cover 3, and the stand column 5 passes through a mounting hole 201 on the construction platform 2 and is mounted in the sleeve 4; the upright posts 5 are uniformly arranged at intervals; the sleeve 4 is provided with a first connecting hole 401, the upright 5 is provided with a second connecting hole 501, and the first connecting hole 401 and the second connecting hole 501 are uniformly arranged at intervals along the vertical direction; the sleeve 4 is locked with the upright post 5 through a locking piece; a jacking device 7 is arranged below the shielding cover 3, and the jacking device 7 drives the shielding cover 3 to move up and down; a window 202 for personnel to pass through is formed in the construction platform 2, and a ladder stand 6 which is arranged corresponding to the window 202 is arranged between the bottom plate 1 and the construction platform 2.
The plurality of sleeves 4 together play a role in supporting the construction platform 2. The upper end of the upright post 5 is connected with the lower surface of the shielding cover 3, and the upright post 5 passes through the mounting hole 201 to be in sliding fit with the sleeve 4, so as to play a role in guiding the up-and-down movement of the shielding cover 3. The invention is integrally moved below the water-cooled furnace cover 13, and the jacking device 7 drives the shielding cover 3 to move up and down, so that the shielding cover 3 is positioned at a proper height and shields the electrode 14. And then the upright post 5 and the sleeve 4 are locked by a locking piece. The first connecting holes 401 and the second connecting holes 501 are uniformly spaced along the vertical direction, and when the shielding cover 3 is located at different heights, the sleeve 4 and the upright 5 are locked by the locking member. The shielding cover 3 is positioned in the water-cooled furnace cover 13, and a certain gap is formed between the edge of the shielding cover 3 and the inner side of the water-cooled furnace cover 13, wherein the gap is about 100mm. During operation, the distance between the construction platform 2 and the shielding cover 3 and the distance between the bottom plate 1 and the construction platform 2 should be ensured not to influence the standing of workers. The worker can go up to the construction platform 2 via the ladder stand 6 and the window 202. Workers stand on the edge of the construction platform 2 to carry out welding repair and cleaning operation on the inner side of the water-cooled furnace cover 13. The steel slag falling off from the top of the inner wall of the water-cooling furnace cover 13 falls on the shielding cover 3, plays a role in protecting workers, and ensures that the workers are safer when carrying out welding repair and cleaning operation on the pipe wall of the cooling water pipe positioned on the inner side of the water-cooling furnace cover 13.
The locking member may be a latch or bolt.
The connection of the sleeve 4 has various embodiments:
in the first embodiment, the upper end of the sleeve 4 is welded with the construction platform 2, and the lower end is welded with the bottom plate 1.
In the second embodiment, a ring plate is arranged on the periphery of the upper end of the sleeve 4, and the ring plate is welded with the construction platform 2 or connected with the construction platform through bolts; the lower end of the sleeve 4 is connected with an end plate, and the end plate is connected with the bottom plate 1 by welding or by bolts.
The installation of the jacking device 7 has various embodiments:
in the first embodiment, the jacking device 7 is installed on the construction platform 2.
In the second embodiment, the jacking device 7 is installed on the base plate 1, and the construction platform 2 is provided with a through hole 203 through which the jacking device 7 passes.
In the third embodiment, the construction platform 2 is provided with a through hole 203 through which the jacking device 7 passes, and the jacking device 7 is connected with the construction platform 2 through a connecting piece. The connecting piece provides a connecting support for the jacking device 7 and the construction platform 2.
The jacking device 7 is a cylinder or a hydraulic cylinder, a piston rod of the cylinder is connected with the lower surface of the shielding cover 3, or a piston rod of the hydraulic cylinder is connected with the lower surface of the shielding cover 3. Preferably, the piston rod of the cylinder or the piston rod of the hydraulic cylinder is connected to the center of the shielding cover 3.
The connecting piece has multiple structural style, only need guarantee cylinder or pneumatic cylinder's stable installation can. Preferably, the connecting piece comprises a U-shaped seat 9 with an upward opening; the U-shaped seat 9 is positioned below the construction platform 2; one side arm of the U-shaped seat 9 is connected with the lower surface of the construction platform 2, and the other side arm is connected with a trunnion 8 on the cylinder body of the hydraulic cylinder. The trunnion 8 is a structure with a hydraulic cylinder body, and the U-shaped seat 9 plays a role in connecting the construction platform 2 and the trunnion 8. The U-shaped seat 9 can be an integrally formed integral structure, and can also be formed by connecting two L-shaped supports.
Because the electrode 14 is operated at a higher temperature, workers need to wait for a shutdown and then cool the electrode 14 to a safe temperature and enter the field. However, the electrode 14 needs a long time to be cooled, and in order to improve the operation efficiency, it is preferable that the shielding cover 3 includes a housing, and a water pipe 301 installed in an inner cavity of the housing; the water pipe 301 is arranged in a meandering manner on a horizontal plane; the water inlet 302 and the water outlet 303 of the water pipe 301 extend out of the shell. By arranging the water pipe 301 in the shell of the shielding cover 3, the water inlet 302 and the water outlet 303 are both connected with external pipelines, cold water is introduced into the water pipe 301 through the water inlet 302 by the external pipelines and flows out from the water outlet 303 to the other external pipeline, so that the cold water is always introduced into the water pipe 301 during operation. Preferably, both the water inlet 302 and the water outlet 303 are located below the housing. When the shielding cover 3 is close to the electrode 14, the cooling of the shell can be realized, and the workers are prevented from being scalded. The electrode 14 does not need to be cooled, and workers enter the field again, so that the time is saved, the efficiency is improved, and the safety and reliability are realized.
In order to facilitate the collection of the steel slag cleaned from the inner side of the water-cooled furnace cover 13, the device also comprises an annular guide rail 15 and a rolling trolley 17; the annular guide rail 15 is arranged adjacent to the shielding cover 3 and is positioned below the shielding cover 3; the annular guide rail 15 is connected with the shielding cover 3 through a connecting block 16; the annular guide rail 15 is arranged along the outer periphery of the shielding cover 3; the rollers of the rolling trolley 17 are in rolling fit with the annular guide rail 15; the roller seat of the rolling trolley 17 is connected with a barrel 18, and an opening of the barrel 18 is upward and positioned at the outer side of the shielding cover 3. The rolling trolley 17 is of a structure in the prior art, and rollers of the rolling trolley 17 are arranged on roller seats through rotating shafts. The barrel 18 with the upward opening is connected with the roller seat for installation. The roller seat is preferably of a U-shaped structure. The barrel 18 is positioned between the shielding cover 3 and the construction platform 2, and the barrel 18 can move around the periphery of the shielding cover 3 through the cooperation of the rolling trolley 17 and the annular guide rail 15. In actual use, the barrel 18 is positioned below the bottom of the water-cooled furnace cover 13, the opening of the barrel 18 is correspondingly arranged with the inner side of the water-cooled furnace cover 13, and the steel slag cleaned from the inner side of the water-cooled furnace cover 13 falls into the barrel 18. The upper portion of staving 18 lateral wall is connected with the mounting tube 19 that is linked together with the inner chamber of staving 18, with the hose grafting on mounting tube 19, the hose is kept away from the one end of mounting tube 19 and is connected with the dust catcher, clear up the slag in the staving 18 fast through starting the dust catcher.
For convenient movement, it is preferable to further comprise a transportation trolley 12, and the bottom plate 1 is fixedly mounted on the table top of the transportation trolley 12. The transport trolley 12 is preferably a ladle car or a flatbed. The ladle car or the flatbed is the structure in the prior art.
Preferably, a first guard rail 10 is installed on the outer periphery of the base plate 1, and a second guard rail 11 is installed on the outer periphery of the construction platform 2. By providing the first guard rail 10 and the second guard rail 11, work safety is improved.
Preferably, an openable cover plate is installed at the window 202. The cover plate is opened to enable a worker to go up to the construction platform 2 through the window 202. After the worker is put on the construction platform 2, the cover plate is closed, so that the worker is prevented from falling from the window 202, and the operation safety is improved. The installation of apron is prior art, and one end and construction platform 2's upper surface pass through the hinge and link to each other, and the other end overlap joint is on construction platform 2 for the apron.
Preferably, the periphery of the shielding cover 3 is provided with a vertically arranged annular baffle 304, and the annular baffle 304 is located above the shielding cover 3. By providing the annular baffle 304, the steel slag can be prevented from falling from the shielding cover 3. The annular baffle 304 is connected to the housing of the blanking cover 3.
The concrete implementation mode of the invention is that the operation bench for repairing the water-cooled furnace cover of the refining furnace is provided by the invention, so that workers can safely repair and clean the pipe wall of the cooling water pipe positioned at the inner side of the water-cooled furnace cover. The steel slag falling off from the top of the inner wall of the water-cooled furnace cover falls on the shielding cover, so that the workers are prevented from being injured by the smashing. The shielding cover also plays a role in heat insulation, workers do not need to enter the field again after the electrodes are cooled, time is saved, efficiency is improved, and safety and reliability are achieved. The steel slag cleaned from the inner side of the water-cooled furnace cover falls into the barrel body.

Claims (9)

1. Repair operation rack of refining stove water-cooled bell, its characterized in that: comprises a bottom plate (1), a construction platform (2) and a shielding cover (3) which are arranged from bottom to top at intervals;
the base plate (1) is connected with the construction platform (2) through a sleeve (4) which is vertically arranged, and the construction platform (2) is provided with a mounting hole (201) communicated with the sleeve (4); the sleeves (4) are uniformly arranged at intervals;
the lower part of the shielding cover (3) is connected with an upright post (5) which is in sliding fit with the sleeve (4), and the upright post (5) passes through a mounting hole (201) on the construction platform (2) and is mounted in the sleeve (4); the upright posts (5) are uniformly arranged at intervals;
the sleeve (4) is provided with a first connecting hole (401), the upright post (5) is provided with a second connecting hole (501), and the first connecting hole (401) and the second connecting hole (501) are uniformly arranged at intervals along the vertical direction; the sleeve (4) is locked with the upright post (5) through a locking piece;
a jacking device (7) is arranged below the shielding cover (3), and the jacking device (7) drives the shielding cover (3) to move up and down; positioning the shielding cover (3) at a proper height and shielding the electrode (14);
a window (202) for personnel to pass through is formed in the construction platform (2), and a cat ladder (6) which is arranged corresponding to the window (202) is arranged between the bottom plate (1) and the construction platform (2);
the shielding cover (3) comprises a shell and a water pipe (301) arranged in the inner cavity of the shell; -said water pipe (301) being serpentine in a horizontal plane; the water inlet (302) and the water outlet (303) of the water pipe (301) extend out of the shell.
2. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: the construction platform (2) is provided with a through hole (203) for the jacking device (7) to pass through, and the jacking device (7) is connected with the construction platform (2) through a connecting piece.
3. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 2, wherein: the jacking device (7) is a hydraulic cylinder.
4. A work bench for repairing a water cooled furnace cover of a refining furnace as claimed in claim 3, wherein: the connecting piece comprises a U-shaped seat (9) with an upward opening; the U-shaped seat (9) is positioned below the construction platform (2);
one side arm of the U-shaped seat (9) is connected with the lower surface of the construction platform (2), and the other side arm is connected with a trunnion (8) on the cylinder body of the hydraulic cylinder.
5. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: the device also comprises an annular guide rail (15) and a rolling trolley (17);
the annular guide rail (15) is arranged adjacent to the shielding cover (3) and is positioned below the shielding cover (3); the annular guide rail (15) is connected with the shielding cover (3) through a connecting block (16); the annular guide rail (15) is arranged along the periphery of the shielding cover (3);
the rollers of the rolling trolley (17) are in rolling fit with the annular guide rail (15);
the roller seat of the rolling trolley (17) is connected with a barrel body (18), and an opening of the barrel body (18) is upward and positioned at the outer side of the shielding cover (3).
6. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: the device also comprises a transportation trolley (12), and the bottom plate (1) is fixedly arranged on the table top of the transportation trolley (12).
7. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: the first protective guard (10) is installed on the periphery of the bottom plate (1), and the second protective guard (11) is installed on the periphery of the construction platform (2).
8. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: an openable cover plate is arranged at the window (202).
9. The work bench for repairing a water cooled furnace cover of a refining furnace of claim 1, wherein: the periphery of shielding lid (3) is provided with annular baffle (304) of vertical arrangement, annular baffle (304) are located shielding lid (3) top.
CN202211618175.XA 2022-12-15 2022-12-15 Operating bench for repairing water-cooled furnace cover of refining furnace Active CN115977363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211618175.XA CN115977363B (en) 2022-12-15 2022-12-15 Operating bench for repairing water-cooled furnace cover of refining furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211618175.XA CN115977363B (en) 2022-12-15 2022-12-15 Operating bench for repairing water-cooled furnace cover of refining furnace

Publications (2)

Publication Number Publication Date
CN115977363A CN115977363A (en) 2023-04-18
CN115977363B true CN115977363B (en) 2024-04-02

Family

ID=85969246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211618175.XA Active CN115977363B (en) 2022-12-15 2022-12-15 Operating bench for repairing water-cooled furnace cover of refining furnace

Country Status (1)

Country Link
CN (1) CN115977363B (en)

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH417789A (en) * 1961-03-29 1966-07-31 Wargons Ab Reduction furnace with superstructure
US3431691A (en) * 1966-01-17 1969-03-11 Mckee & Co Arthur G Apparatus and method for supporting vessels
US3517954A (en) * 1967-10-23 1970-06-30 Great Lakes Carbon Corp Electrode section-connecting nipple pre-assembly and process of assembling an electrode joint
US4407392A (en) * 1981-08-31 1983-10-04 Western Electric Company, Inc. Safety scaffold for metal melting furnaces
US4662526A (en) * 1982-05-17 1987-05-05 Mannesmann Aktiengesellschaft Hoisting mechanism for the cover of a furnace
JPH03279778A (en) * 1990-03-28 1991-12-10 Kawasaki Steel Corp Furnace bottom electrode replacing device for dc electric furnace
KR200184488Y1 (en) * 2000-01-18 2000-06-01 포철기연주식회사 Jig apparatus for disassembling and assembling bottom electrode assembly of electric furnace
US6539602B1 (en) * 1999-07-05 2003-04-01 Kawasaki Steel Corporation Method of repairing coke oven
CN102094106A (en) * 2011-03-21 2011-06-15 中国十九冶集团有限公司南京分公司 Quick installation method for large four-point suspended type converter
CN208202508U (en) * 2018-05-22 2018-12-07 泉州市欧捷鑫金属制品有限公司 A kind of construction operation platform
CN208830681U (en) * 2018-08-13 2019-05-07 中国水利水电第十四工程局有限公司 A kind of job platform for the construction of vertical shaft penstock
CN210242343U (en) * 2019-06-26 2020-04-03 鄂尔多斯市君正能源化工有限公司 High-reliability furnace door of submerged arc furnace
KR102100383B1 (en) * 2019-12-10 2020-04-13 (주)휴하리 System scaffolding for internal piping inspection
CN112160570A (en) * 2020-09-16 2021-01-01 徐团团 Green building supporting platform convenient to quick construction
CN214463842U (en) * 2020-12-15 2021-10-22 中国水电四局(祥云)工程建设有限公司 Movable assembled aerial work platform
CN113585709A (en) * 2021-09-07 2021-11-02 申锡机械集团有限公司 Barrel structure construction operation platform
CN216196428U (en) * 2021-10-19 2022-04-05 北京市政建设集团有限责任公司 Novel ingate operation construction platform

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9464846B2 (en) * 2013-11-15 2016-10-11 Nucor Corporation Refractory delta cooling system
IN2014MU00274A (en) * 2014-01-25 2015-09-11 Jsw Steel Ltd

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH417789A (en) * 1961-03-29 1966-07-31 Wargons Ab Reduction furnace with superstructure
US3431691A (en) * 1966-01-17 1969-03-11 Mckee & Co Arthur G Apparatus and method for supporting vessels
US3517954A (en) * 1967-10-23 1970-06-30 Great Lakes Carbon Corp Electrode section-connecting nipple pre-assembly and process of assembling an electrode joint
US4407392A (en) * 1981-08-31 1983-10-04 Western Electric Company, Inc. Safety scaffold for metal melting furnaces
US4662526A (en) * 1982-05-17 1987-05-05 Mannesmann Aktiengesellschaft Hoisting mechanism for the cover of a furnace
JPH03279778A (en) * 1990-03-28 1991-12-10 Kawasaki Steel Corp Furnace bottom electrode replacing device for dc electric furnace
US6539602B1 (en) * 1999-07-05 2003-04-01 Kawasaki Steel Corporation Method of repairing coke oven
KR200184488Y1 (en) * 2000-01-18 2000-06-01 포철기연주식회사 Jig apparatus for disassembling and assembling bottom electrode assembly of electric furnace
CN102094106A (en) * 2011-03-21 2011-06-15 中国十九冶集团有限公司南京分公司 Quick installation method for large four-point suspended type converter
CN208202508U (en) * 2018-05-22 2018-12-07 泉州市欧捷鑫金属制品有限公司 A kind of construction operation platform
CN208830681U (en) * 2018-08-13 2019-05-07 中国水利水电第十四工程局有限公司 A kind of job platform for the construction of vertical shaft penstock
CN210242343U (en) * 2019-06-26 2020-04-03 鄂尔多斯市君正能源化工有限公司 High-reliability furnace door of submerged arc furnace
KR102100383B1 (en) * 2019-12-10 2020-04-13 (주)휴하리 System scaffolding for internal piping inspection
CN112160570A (en) * 2020-09-16 2021-01-01 徐团团 Green building supporting platform convenient to quick construction
CN214463842U (en) * 2020-12-15 2021-10-22 中国水电四局(祥云)工程建设有限公司 Movable assembled aerial work platform
CN113585709A (en) * 2021-09-07 2021-11-02 申锡机械集团有限公司 Barrel structure construction operation platform
CN216196428U (en) * 2021-10-19 2022-04-05 北京市政建设集团有限责任公司 Novel ingate operation construction platform

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宝钢炼钢厂LF炉水冷炉盖修复技术攻关;王书剑;;科技展望;20151231(第25期);127 *

Also Published As

Publication number Publication date
CN115977363A (en) 2023-04-18

Similar Documents

Publication Publication Date Title
CN111710474B (en) Cable extrusion molding production line and process
WO2012134036A1 (en) Roof for electric furnace
CN115977363B (en) Operating bench for repairing water-cooled furnace cover of refining furnace
KR101212247B1 (en) Blast furnace bottom dismantlement method and transport device
CN108796159B (en) Modular detachable blast furnace cast house combined dust removal device
EP0611939A1 (en) Device for lifting and moving the roof of a spray cooled furnace
CN201159590Y (en) Collapsible water sealing skirt cover
CA1077266A (en) Enclosure for steel converting apparatus
CN113819769A (en) Flue and boiler
CN213713922U (en) High-melting-efficiency low-loss melting furnace
KR20090016220A (en) Apparatus for preventing breakaway of heat furnace extracting door
CN221870212U (en) Aluminium liquid splashproof supporting seat
CN110434321A (en) A kind of hot-metal bottle heat insulation protective device of hot-metal car
CN217998835U (en) Coke oven tedge upper segment assembly platform
CN220624930U (en) Connection structure between breast board and car frame in circular cooler trolley
US20200132373A1 (en) Drain pump for a spray-cooled metallurgical furnace
CN219710922U (en) Movable smoke hood overhauling bracket for converter
CN216282820U (en) Flue gas isolating device
CN216925178U (en) Environment-friendly smoke hood of anode furnace
CN217230847U (en) Modularization heating platform truck formula tempering furnace
CN205062097U (en) Tap a blast furnace and use sleeve pipe
CN215392453U (en) Scum cleaning operation platform
CN202808868U (en) RH vacuum refined hot-bent pipe
CN220056921U (en) LF stove station double-line feeding device
KR20220087171A (en) Deck and work method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant