US20030230409A1 - Instrumentation assembly for an offshore riser - Google Patents

Instrumentation assembly for an offshore riser Download PDF

Info

Publication number
US20030230409A1
US20030230409A1 US10/459,521 US45952103A US2003230409A1 US 20030230409 A1 US20030230409 A1 US 20030230409A1 US 45952103 A US45952103 A US 45952103A US 2003230409 A1 US2003230409 A1 US 2003230409A1
Authority
US
United States
Prior art keywords
riser
assembly
modules
measuring
processing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
US10/459,521
Other versions
US7080689B2 (en
Inventor
Jean Guesnon
Olivier Vaisberg
Guy Pignard
Pierre Guerin
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IFP Energies Nouvelles IFPEN
Original Assignee
IFP Energies Nouvelles IFPEN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IFP Energies Nouvelles IFPEN filed Critical IFP Energies Nouvelles IFPEN
Assigned to INSTITUT FRANCAIS DU PETROLE reassignment INSTITUT FRANCAIS DU PETROLE ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: GUERIN, PIERRE, PIGNARD, GUY, VAISBERG, OLIVIER, GUESNON, JEAN
Publication of US20030230409A1 publication Critical patent/US20030230409A1/en
Application granted granted Critical
Publication of US7080689B2 publication Critical patent/US7080689B2/en
Adjusted expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/01Risers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/002Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/001Survey of boreholes or wells for underwater installation

Definitions

  • the present invention relates to the development of deep offshore oil reservoirs, i.e. at water depths above 1000 meters, in particular above 2000 m.
  • the production well drilling operations require heavy and therefore costly installations, which involves surveys and techniques specific to the local conditions.
  • Industrialists in the profession currently have a certain number of computer programs allowing complex computations to optimize the installations according to specifications.
  • the problems are such that the computing programs are. currently not totally validated for extreme conditions : water depth, wind, current, etc.
  • the present invention relates to a deep-water drilling installation allowing to control all of the stresses and deformations undergone by the riser considering the oceanographical and operating conditions. What is referred to as control is real-time, pseudo-real time, or not, recording and monitoring of the parameters allowing to analyse the stresses undergone by the riser.
  • the main object of the invention is to acquire a maximum of data on the behaviour of a riser under determined conditions.
  • the displacements, the deformations, the stresses are therefore recorded together with the outside loads and actions.
  • the invention thus relates to an instrumentation assembly intended for an offshore riser operated from a floater.
  • the assembly comprises a central processing unit (PC) connected by conducting cables to:
  • An upper element of the riser can be instrumented to measure (PUP) the tension and the flexion at the top of the riser and connected to said central processing unit.
  • Tensioning means on the riser can comprise detectors for measuring their dynamic operation.
  • the modules can comprise stand-alone means such as memories and batteries so as to be able to work in case of a fault in the link with the central processing unit.
  • An acoustic system can comprise beacons fastened to the same points of the riser as said modules so as to locate it.
  • the assembly can include at least four modules.
  • FIG. 1 diagrammatically shows an offshore drilling installation in its environment
  • FIG. 2 diagrammatically shows all of the detectors according to the invention and the acquisition system.
  • FIG. 1 shows the global architecture of an offshore drilling installation operated from a floater 1 .
  • This type of installation requires a riser 2 consisting of an assembly of elements connected to one another.
  • the riser connects the floater to subsea wellhead 3 .
  • Wellhead 3 consists of a conductor pipe 4 sealed in the sea bottom, elements that support safety preventers 5 , which comprise an upper part LMRP (Lower Marine Riser Package) 6 that can be separated from the lower part by means of a connector.
  • Upper part LMRP remains suspended from the riser in the disconnected mode.
  • the base of the riser can be inclined at an angle ⁇ by means of knuckle type joint 7 .
  • riser 2 The upper part of riser 2 is fastened to floater 1 by a telescopic joint 8 which allows to take up the vertical displacements due to the waves, and by a system of tensioners 9 generally consisting of cables, pulleys and hydropneumatic jacks that maintain the riser under tension and allow its deflected shape to be controlled.
  • tensioners 9 generally consisting of cables, pulleys and hydropneumatic jacks that maintain the riser under tension and allow its deflected shape to be controlled.
  • Arrows 10 represent the current conditions, velocities, amplitudes, directions applied to riser 2 .
  • Arrows 11 represent the wave and swell conditions.
  • Reference number 12 illustrates the displacement of the floater in relation to the vertical 13 of the wellhead.
  • the object of the present invention is to help solve the mechanical problems of the drilling installation, in particular the riser, such as the dynamic behaviour of the riser in the connected and disconnected mode, the consequences of strong currents, in particular vortex-induced vibrations (VIV), and more generally the fatigue strength of the riser.
  • VIV vortex-induced vibrations
  • the riser is controlled both in the mode where it is connected to the wellhead and in the disconnected mode
  • the data provided by the detectors and recorded are compared with the results obtained by the dedicated software DeepDRiser (TM IFP/Principia), or any other similar software,
  • the recorded data relate to: the riser, the lower end of the riser (LMRP), the tensioning system, the telescopic joint, the displacement of the floater, the environment,
  • the data acquisition system is suited to the drilling procedures
  • a long-baseline acoustic system is used to know the position of the end of the riser (LMRP) in the disconnected mode.
  • FIG. 2 diagrammatically shows the acquisition and control network of the drilling installation.
  • a central processing unit PC is connected to a series of detectors to
  • the network can be subdivided into three subsystems:
  • Subsystem 1 it comprises six series of detectors
  • W gives the wave height
  • M/W gives weather information such as the direction and the velocity of the wind, the atmospheric pressure
  • DGPS gives the displacements of the floater according to the six degrees of freedom
  • P gives the position of the floater along two axes x and y.
  • Subsystem 2 it mainly comprises six series of detectors (reference numbers 21 , 22 , 23 , 24 , 25 , 26 ) whose housings are fastened to four riser elements distributed according to circumstances, and two ( 25 and 26 ) are arranged in the vicinity of the end LMRP of the riser and surround joint 7 .
  • the six housings are connected together and to the surface by a cable 27 .
  • Each housing contains three accelerometers allowing dynamic location of a cylinder section (a part of the riser) in space.
  • the housings also contain two inclinometers, or equivalent system, allowing to determine the static deflected shape of the riser. If the cable link is broken, each housing can work under stand-alone conditions by means of memories and batteries.
  • Transmission cable 27 can comprise 4 lines: two for data transmission and two for power supply.
  • Cable 27 is also connected to the detectors PUP fastened to a tubular element (pup-joint) for measurement of the axial load or tension, and of the bending moments along two axes.
  • All of the detectors 28 diagrammatically shown at the top of the riser in FIG. 2 are intended for measurements allowing to control and to operate the tensioning system of the riser, a system consisting of a certain number of identical subsystems.
  • Each tensioning subsystem comprises at least a cable, a system of pulleys that cooperate with a hydraulic jack.
  • the tension is measured at the ends of at least one cable to evaluate the efficiency of the pulleys and the displacement of the jack rod.
  • the hydraulic system is a passive system intended to control the pressure in the jacks, obtained by oleopneumatic accumulators. The gas pressure in these accumulators, whose value is adjusted according to the required tension, is also measured and recorded.
  • the assembly of detectors 28 connected to central processing unit PC by conductors 29 also comprises recording the displacement of the telescopic joint systematically installed at the top of the riser to admit the heave of the floater.
  • This assembly can also comprise measuring the tension on the drilling cable and the weight on the spider on which rests the riser during its descent or in the disconnected mode.
  • Subsystem 2 also comprises assembly DRG which gives the drilling measurements, i.e.: tension at the top of the drill string, density of the drilling fluid, rotating speed of the bit, pressure in the safety lines (KL and CL), depth of the riser end (LMRP), this information being obtained from the measuring system of the drilling installation.
  • assembly DRG which gives the drilling measurements, i.e.: tension at the top of the drill string, density of the drilling fluid, rotating speed of the bit, pressure in the safety lines (KL and CL), depth of the riser end (LMRP), this information being obtained from the measuring system of the drilling installation.
  • the network consists of links by means of conductor cables to a central processing unit PC.
  • This central unit controls:
  • Such a network allows real-time monitoring of the stresses, deformations and positioning of the riser whether during its descent, or disconnected mode, or in the connected mode, i.e. during drilling.
  • Subsystem 3 it consists of an acoustic system diagrammatically represented by detector 30 connected to central unit PC.
  • a certain number of acoustic beacons 31 to 37 fastened at determined points allow to locate them.
  • the beacons fastened to the standard length of the riser ( 31 to 34 ) can serve as a redundant safety for the other system measuring the deflected shape of the riser.
  • Beacons 35 and 36 allow to locate the lower end of the LMRP.
  • the other beacons 37 that lie on the sea bottom are used to locate the floater.

Landscapes

  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Geophysics (AREA)
  • Earth Drilling (AREA)
  • Indicating Or Recording The Presence, Absence, Or Direction Of Movement (AREA)

Abstract

The present invention relates to an instrumentation assembly intended for an offshore riser (2) operated from a floater (1). It comprises a central processing unit (PC) connected by conducting cables (27) to:
a plurality of modules (21-25) fastened to various points of the riser length, the modules comprising measuring means allowing dynamic location of said points in space,
another locating module (26) fastened to the lower end (LMRP) of said riser,
a series of detectors (W, C, M/W) for measuring the environment: wind, wave, current,
an assembly for measuring the position (DGPS, P) of the floater.
The measurements are synchronized with one another, managed and recorded by means of the central processing unit.

Description

    FIELD OF THE INVENTION
  • The present invention relates to the development of deep offshore oil reservoirs, i.e. at water depths above 1000 meters, in particular above 2000 m. To produce such reservoirs, the production well drilling operations require heavy and therefore costly installations, which involves surveys and techniques specific to the local conditions, Industrialists in the profession currently have a certain number of computer programs allowing complex computations to optimize the installations according to specifications. However, at such depths, the problems are such that the computing programs are. currently not totally validated for extreme conditions : water depth, wind, current, etc. [0001]
  • The present invention relates to a deep-water drilling installation allowing to control all of the stresses and deformations undergone by the riser considering the oceanographical and operating conditions. What is referred to as control is real-time, pseudo-real time, or not, recording and monitoring of the parameters allowing to analyse the stresses undergone by the riser. [0002]
  • The main object of the invention is to acquire a maximum of data on the behaviour of a riser under determined conditions. The displacements, the deformations, the stresses are therefore recorded together with the outside loads and actions. [0003]
  • SUMMARY OF THE INVENTION
  • The invention thus relates to an instrumentation assembly intended for an offshore riser operated from a floater. The assembly comprises a central processing unit (PC) connected by conducting cables to: [0004]
  • a plurality of modules fastened to various points of the riser length, said modules comprising measuring means allowing dynamic location of said points in space, [0005]
  • another locating module fastened to the lower end (LMRP) of said riser, [0006]
  • a series of detectors (W, C, M/W) for measuring the environment: wind, wave, current, [0007]
  • an assembly for measuring the position (DGPS, P) of the floater, [0008]
  • said measurements being synchronized with one another, managed and recorded by means of the central processing unit. [0009]
  • An upper element of the riser can be instrumented to measure (PUP) the tension and the flexion at the top of the riser and connected to said central processing unit. [0010]
  • Tensioning means on the riser can comprise detectors for measuring their dynamic operation. [0011]
  • The modules can comprise stand-alone means such as memories and batteries so as to be able to work in case of a fault in the link with the central processing unit. [0012]
  • An acoustic system can comprise beacons fastened to the same points of the riser as said modules so as to locate it. [0013]
  • The assembly can include at least four modules.[0014]
  • BRIEF DESCRIPTION OF THE FIGURES
  • Other features and advantages of the present invention will be clear from reading the description hereafter of a non-limitative embodiment, with reference to the accompanying figures wherein: [0015]
  • FIG. 1 diagrammatically shows an offshore drilling installation in its environment, [0016]
  • FIG. 2 diagrammatically shows all of the detectors according to the invention and the acquisition system.[0017]
  • DETAILED DESCRIPTION
  • FIG. 1 shows the global architecture of an offshore drilling installation operated from a [0018] floater 1. This type of installation requires a riser 2 consisting of an assembly of elements connected to one another. The riser connects the floater to subsea wellhead 3. Wellhead 3 consists of a conductor pipe 4 sealed in the sea bottom, elements that support safety preventers 5, which comprise an upper part LMRP (Lower Marine Riser Package) 6 that can be separated from the lower part by means of a connector. Upper part LMRP remains suspended from the riser in the disconnected mode. In the connected mode, the base of the riser can be inclined at an angle α by means of knuckle type joint 7. The upper part of riser 2 is fastened to floater 1 by a telescopic joint 8 which allows to take up the vertical displacements due to the waves, and by a system of tensioners 9 generally consisting of cables, pulleys and hydropneumatic jacks that maintain the riser under tension and allow its deflected shape to be controlled.
  • [0019] Arrows 10 represent the current conditions, velocities, amplitudes, directions applied to riser 2. Arrows 11 represent the wave and swell conditions. Reference number 12 illustrates the displacement of the floater in relation to the vertical 13 of the wellhead.
  • The object of the present invention is to help solve the mechanical problems of the drilling installation, in particular the riser, such as the dynamic behaviour of the riser in the connected and disconnected mode, the consequences of strong currents, in particular vortex-induced vibrations (VIV), and more generally the fatigue strength of the riser. [0020]
  • The essential characteristics of the present invention can be summed up as follows: [0021]
  • the riser is controlled both in the mode where it is connected to the wellhead and in the disconnected mode, [0022]
  • the data provided by the detectors and recorded are compared with the results obtained by the dedicated software DeepDRiser (™ IFP/Principia), or any other similar software, [0023]
  • the recorded data relate to: the riser, the lower end of the riser (LMRP), the tensioning system, the telescopic joint, the displacement of the floater, the environment, [0024]
  • the data acquisition system is suited to the drilling procedures, [0025]
  • a long-baseline acoustic system is used to know the position of the end of the riser (LMRP) in the disconnected mode. [0026]
  • By means of the system according to the invention, the data allow to study: [0027]
  • the quasi-static deflected shape of the riser subjected to the current, [0028]
  • the dynamic variation of the profile (deflected shape) due to the waves and to the displacements of the floater, [0029]
  • the amplitude and the frequency of the vortex-induced vibrations (VIV), [0030]
  • the hydrodynamic loads, [0031]
  • the behaviour of the tensioners (in the connected mode), [0032]
  • the tension at the riser top, [0033]
  • the dynamic variations of the tension at the top considering the equivalent stiffness of the tensioning system (in the connected mode), [0034]
  • the axial dynamic behaviour of the riser (in the connected and disconnected mode), [0035]
  • the coupling of the tension/flexion modes to assess the risk of dynamic buckling of the upper part of the riser, [0036]
  • the transient behaviour during disconnection of the riser. [0037]
  • FIG. 2 diagrammatically shows the acquisition and control network of the drilling installation. A central processing unit PC is connected to a series of detectors to [0038]
  • supply the detectors with electric power, [0039]
  • record the data, [0040]
  • synchronize the data with one another, [0041]
  • provide a line for continuous control of the detectors. [0042]
  • The network can be subdivided into three subsystems: [0043]
  • Subsystem 1: it comprises six series of detectors [0044]
  • W gives the wave height, [0045]
  • C gives the velocity and the direction of the current, [0046]
  • M/W gives weather information such as the direction and the velocity of the wind, the atmospheric pressure, [0047]
  • DGPS gives the displacements of the floater according to the six degrees of freedom, [0048]
  • P gives the position of the floater along two axes x and y. [0049]
  • The technology of these detectors is known in the profession, they are selected according to the expected conditions and to a determined plan. [0050]
  • Subsystem 2: it mainly comprises six series of detectors ([0051] reference numbers 21, 22, 23, 24, 25, 26) whose housings are fastened to four riser elements distributed according to circumstances, and two (25 and 26) are arranged in the vicinity of the end LMRP of the riser and surround joint 7. The six housings are connected together and to the surface by a cable 27. Each housing contains three accelerometers allowing dynamic location of a cylinder section (a part of the riser) in space. The housings also contain two inclinometers, or equivalent system, allowing to determine the static deflected shape of the riser. If the cable link is broken, each housing can work under stand-alone conditions by means of memories and batteries. In this case, the sampling frequency is reduced. Thus, whether during the descent of the riser or after connection to the wellhead, the deflected shape of the riser can be known and recorded in synchronism with the outside conditions: winds, currents, waves, . . . . Transmission cable 27 can comprise 4 lines: two for data transmission and two for power supply.
  • [0052] Cable 27 is also connected to the detectors PUP fastened to a tubular element (pup-joint) for measurement of the axial load or tension, and of the bending moments along two axes.
  • All of the [0053] detectors 28 diagrammatically shown at the top of the riser in FIG. 2 are intended for measurements allowing to control and to operate the tensioning system of the riser, a system consisting of a certain number of identical subsystems. Each tensioning subsystem comprises at least a cable, a system of pulleys that cooperate with a hydraulic jack. In order to monitor and to control the operation of the tensioning system, the tension is measured at the ends of at least one cable to evaluate the efficiency of the pulleys and the displacement of the jack rod. The hydraulic system is a passive system intended to control the pressure in the jacks, obtained by oleopneumatic accumulators. The gas pressure in these accumulators, whose value is adjusted according to the required tension, is also measured and recorded.
  • The assembly of [0054] detectors 28 connected to central processing unit PC by conductors 29 also comprises recording the displacement of the telescopic joint systematically installed at the top of the riser to admit the heave of the floater.
  • This assembly can also comprise measuring the tension on the drilling cable and the weight on the spider on which rests the riser during its descent or in the disconnected mode. [0055]
  • [0056] Subsystem 2 also comprises assembly DRG which gives the drilling measurements, i.e.: tension at the top of the drill string, density of the drilling fluid, rotating speed of the bit, pressure in the safety lines (KL and CL), depth of the riser end (LMRP), this information being obtained from the measuring system of the drilling installation.
  • The network consists of links by means of conductor cables to a central processing unit PC. This central unit controls: [0057]
  • data transfer organization, [0058]
  • measurement acquisition, [0059]
  • detectors synchronization, [0060]
  • data display, [0061]
  • measurement recording, [0062]
  • modification of the acquisition parameters by an operator, the frequency for example. [0063]
  • Such a network allows real-time monitoring of the stresses, deformations and positioning of the riser whether during its descent, or disconnected mode, or in the connected mode, i.e. during drilling. [0064]
  • Subsystem 3: it consists of an acoustic system diagrammatically represented by [0065] detector 30 connected to central unit PC.
  • A certain number of [0066] acoustic beacons 31 to 37 fastened at determined points allow to locate them. The beacons fastened to the standard length of the riser (31 to 34) can serve as a redundant safety for the other system measuring the deflected shape of the riser. Beacons 35 and 36 allow to locate the lower end of the LMRP. The other beacons 37 that lie on the sea bottom are used to locate the floater.

Claims (6)

1) An instrumentation assembly intended for an offshore riser (2) operated from a floater (1), characterized in that it comprises a central processing unit (PC) connected by conductor cables (27) to
a plurality of modules (21-25) fastened to various points of the riser length, said modules comprising measuring means allowing dynamic location of said points in space,
another locating module (26) fastened to the lower end (LMRP) of said riser,
a series of detectors (W, C, M/W) for measuring the environment: wind, wave, current,
an assembly for measuring the position (DGPS, P) of the floater, said measurements being synchronized with one another, managed and recorded by means of said central processing unit.
2) An assembly as claimed in claim 1, wherein an upper element of said riser is instrumented in order to measure (PUP) the tension and the flexion at the top of the riser, and it is connected to said central processing unit.
3) An assembly as claimed in any one of the previous claims, wherein tensioning means on the riser comprise detectors (28) for measuring the dynamic behaviour thereof.
4) An assembly as claimed in any one of the previous claims, wherein said modules comprise stand-alone means such as memories and batteries so as to be able to work in case of a fault in the link with the central processing unit.
5) An assembly as claimed in any one of the previous claims, wherein an acoustic system (30; 37) comprises beacons (31-35) fastened at the same points of the riser as said modules so as to locate it.
6) An assembly as claimed in any one of the previous claims, wherein it comprises at least four modules.
US10/459,521 2002-06-13 2003-06-12 Instrumentation assembly for an offshore riser Expired - Fee Related US7080689B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR0207245A FR2840951B1 (en) 2002-06-13 2002-06-13 INSTRUMENTATION ASSEMBLY OF AN OFFSHORE DRILLING RISER
FR02/07.245 2002-06-13

Publications (2)

Publication Number Publication Date
US20030230409A1 true US20030230409A1 (en) 2003-12-18
US7080689B2 US7080689B2 (en) 2006-07-25

Family

ID=29595180

Family Applications (1)

Application Number Title Priority Date Filing Date
US10/459,521 Expired - Fee Related US7080689B2 (en) 2002-06-13 2003-06-12 Instrumentation assembly for an offshore riser

Country Status (3)

Country Link
US (1) US7080689B2 (en)
BR (1) BR0302040A (en)
FR (1) FR2840951B1 (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050252685A1 (en) * 2004-01-23 2005-11-17 Baker Hughes Incorporated Floatable drill cuttings bag and method and system for use in cuttings disposal
US20060065401A1 (en) * 2004-09-28 2006-03-30 John Allen System for sensing riser motion
WO2006050488A1 (en) * 2004-11-03 2006-05-11 Shell Internationale Research Maatschappij B.V. Apparatus and method for retroactively installing sensors on marine elements
WO2009109745A1 (en) * 2008-03-05 2009-09-11 Schlumberger Holdings Limited Flexible pipe fatigue monitoring below the bend stiffener of a flexible riser
CN102288376A (en) * 2011-08-02 2011-12-21 上海交通大学 Top-movable vortex-induced vibration rotating device for vertically-arranged vertical pipe under uniform flow and step flow
US8725429B2 (en) 2011-05-27 2014-05-13 Stress Engineering Services, Inc. Fatigue monitoring
WO2014064190A3 (en) * 2012-10-24 2014-08-28 Fmc Kongsberg Subsea As Method of calculation loads on a subsea component.
WO2017048941A1 (en) * 2015-09-15 2017-03-23 Noble Drilling Services Inc. Method for excavating a mud line cellar for subsea well drilling
NO341582B1 (en) * 2015-04-14 2017-12-11 4Subsea As System og metode for å overvåke utmatting ved brønnhodet i undervannsbrønner
WO2018013777A1 (en) * 2016-07-13 2018-01-18 Ensco International Incorporated Riser deflection mitigation
US10767331B2 (en) 2013-12-23 2020-09-08 BP Exploration and Production, Inc. Riser fatigue monitoring
US11063674B2 (en) 2005-06-15 2021-07-13 CSignum Ltd. Communications system
US11075701B2 (en) 2005-06-15 2021-07-27 CSignum Ltd. Communications system
US20230123839A1 (en) * 2018-02-14 2023-04-20 Maersk Drilling A/S Emergency disconnect system
US11750300B2 (en) 2005-06-15 2023-09-05 CSignum Ltd. Mobile device underwater communications system and method
US12072430B2 (en) 2018-08-13 2024-08-27 CSignum Ltd. Underwater navigation
US12136957B2 (en) 2006-02-07 2024-11-05 CSignum Ltd. Mobile device underwater communications system and method

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100465007B1 (en) * 2003-12-06 2005-01-14 강대우 Boring machine in underwater differential global positioning system and boring method using the same
FR2871511B1 (en) * 2004-06-11 2006-07-28 Technip France Sa CONTROL DEVICE FOR FLEXIBLE CONDUIT STIFFENERS
US8074720B2 (en) * 2004-09-28 2011-12-13 Vetco Gray Inc. Riser lifecycle management system, program product, and related methods
US7219739B2 (en) * 2005-03-07 2007-05-22 Halliburton Energy Services, Inc. Heave compensation system for hydraulic workover
US7314087B2 (en) * 2005-03-07 2008-01-01 Halliburton Energy Services, Inc. Heave compensation system for hydraulic workover
US7926579B2 (en) * 2007-06-19 2011-04-19 Schlumberger Technology Corporation Apparatus for subsea intervention
US20090056936A1 (en) * 2007-07-17 2009-03-05 Mccoy Jr Richard W Subsea Structure Load Monitoring and Control System
US9051785B2 (en) 2008-02-11 2015-06-09 Vetco Gray Inc. Oil and gas riser spider with low frequency antenna apparatus and method
US8439109B2 (en) * 2008-05-23 2013-05-14 Schlumberger Technology Corporation System and method for depth measurement and correction during subsea intervention operations
NO333849B1 (en) * 2010-04-28 2013-09-30 Statoil Petroleum As Safety device and method for protecting the well barrier.
WO2013096128A1 (en) 2011-12-22 2013-06-27 Transocean Sedco Forex Ventures Limited Hybrid tensioning riser string
US9080393B2 (en) * 2012-05-31 2015-07-14 Transocean Sedco Forex Ventures Limited Drilling riser retrieval in high current
US20140353036A1 (en) * 2013-05-29 2014-12-04 Vetco Gray Inc. Apparatus and Method for Measuring Inclination in Subsea Running, Setting, and Testing Tools
US9404347B1 (en) * 2015-05-15 2016-08-02 Baker Hughes Incorporated Apparatus and method for connecting a riser from an offshore rig to a subsea structure
GB2542599A (en) * 2015-09-24 2017-03-29 Maersk Drilling As A drilling or work-over rig comprising an operational control and/or state unit and a computer-implemented method of providing operational control
US9593568B1 (en) * 2015-10-09 2017-03-14 General Electric Company System for estimating fatigue damage
US11492893B2 (en) * 2017-05-30 2022-11-08 The Texas A&M University System Apparatus and method for predicting a deformed shape of a structure
BR102018014298B1 (en) 2018-07-13 2021-12-14 Petróleo Brasileiro S.A. - Petrobras SYSTEM AND METHOD OF SUPPORTING THE OPERATION OF SUBSEA INSTALLATIONS FOR 3D RECONSTRUCTION OF FLEXIBLE LINES DURING A DIRECT VERTICAL CONNECTION OPERATION
US11788926B2 (en) * 2018-11-23 2023-10-17 BR2W Solucões Ltda. Method for monitoring axial loads in structures by identifying natural frequencies
EP4075109B1 (en) 2021-04-12 2023-10-25 Ampacimon Sa Method and device for monitoring severity of vibration in overhead power lines
CN113669032B (en) * 2021-07-22 2022-05-10 中国石油大学(北京) Vibration reduction control method, device and system for installation of deepwater drilling riser
CN113607400B (en) * 2021-08-13 2024-03-08 中国石油大学(华东) Linkage test device for deepwater drilling riser and suspension system

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3653635A (en) * 1969-11-17 1972-04-04 Joe Stine Inc Wave motion compensating apparatus for use with floating hoisting systems
US3760875A (en) * 1970-06-29 1973-09-25 Shell Oil Co Floating structure with rotatable templet for connecting guide lines thereto
US4024718A (en) * 1975-12-18 1977-05-24 The Offshore Company Subsea cable apparatus and method of handling same
US4044473A (en) * 1974-02-25 1977-08-30 Hydril Company Tilt detector and system
US4205379A (en) * 1977-05-16 1980-05-27 TRW Inc., Systems & Energy Position determining and dynamic positioning method and system for floating marine well drill platforms and the like
US4317174A (en) * 1980-02-28 1982-02-23 The Offshore Company Riser angle positioning system and process
US4921048A (en) * 1988-09-22 1990-05-01 Otis Engineering Corporation Well production optimizing system
US5704427A (en) * 1995-10-13 1998-01-06 Buck; David A. Portable well service rig
US5978739A (en) * 1997-10-14 1999-11-02 Stockton; Thomas R. Disconnect information and monitoring system for dynamically positioned offshore drilling rigs
US6364021B1 (en) * 2000-07-11 2002-04-02 Halliburton Energy Services, Inc. Well management system and method of operation
US6808021B2 (en) * 2000-08-14 2004-10-26 Schlumberger Technology Corporation Subsea intervention system

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2375431A1 (en) * 1975-06-18 1978-07-21 Petroles Cie Francaise Maintenance of stress in a mud riser - telescopic riser gives hydraulic pressure indication of stress increasing or decreasing force exerted accordingly
US6018501A (en) * 1997-12-10 2000-01-25 Halliburton Energy Services, Inc. Subsea repeater and method for use of the same
GB2372765A (en) * 2001-02-27 2002-09-04 Philip Head Use of coiled tubing and jet drilling to install a casing

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3653635A (en) * 1969-11-17 1972-04-04 Joe Stine Inc Wave motion compensating apparatus for use with floating hoisting systems
US3760875A (en) * 1970-06-29 1973-09-25 Shell Oil Co Floating structure with rotatable templet for connecting guide lines thereto
US4044473A (en) * 1974-02-25 1977-08-30 Hydril Company Tilt detector and system
US4024718A (en) * 1975-12-18 1977-05-24 The Offshore Company Subsea cable apparatus and method of handling same
US4205379A (en) * 1977-05-16 1980-05-27 TRW Inc., Systems & Energy Position determining and dynamic positioning method and system for floating marine well drill platforms and the like
US4317174A (en) * 1980-02-28 1982-02-23 The Offshore Company Riser angle positioning system and process
US4921048A (en) * 1988-09-22 1990-05-01 Otis Engineering Corporation Well production optimizing system
US5704427A (en) * 1995-10-13 1998-01-06 Buck; David A. Portable well service rig
US5978739A (en) * 1997-10-14 1999-11-02 Stockton; Thomas R. Disconnect information and monitoring system for dynamically positioned offshore drilling rigs
US6364021B1 (en) * 2000-07-11 2002-04-02 Halliburton Energy Services, Inc. Well management system and method of operation
US6808021B2 (en) * 2000-08-14 2004-10-26 Schlumberger Technology Corporation Subsea intervention system

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7261164B2 (en) * 2004-01-23 2007-08-28 Baker Hughes Incorporated Floatable drill cuttings bag and method and system for use in cuttings disposal
US20050252685A1 (en) * 2004-01-23 2005-11-17 Baker Hughes Incorporated Floatable drill cuttings bag and method and system for use in cuttings disposal
US20060065401A1 (en) * 2004-09-28 2006-03-30 John Allen System for sensing riser motion
US7328741B2 (en) 2004-09-28 2008-02-12 Vetco Gray Inc. System for sensing riser motion
GB2434863B (en) * 2004-11-03 2010-02-03 Shell Int Research Apparatus and method for retroactively installing sensors on marine elements
WO2006050488A1 (en) * 2004-11-03 2006-05-11 Shell Internationale Research Maatschappij B.V. Apparatus and method for retroactively installing sensors on marine elements
GB2434863A (en) * 2004-11-03 2007-08-08 Shell Int Research Apparatus and method for retroactively installing sensors on marine elements
US7398697B2 (en) 2004-11-03 2008-07-15 Shell Oil Company Apparatus and method for retroactively installing sensors on marine elements
US11075701B2 (en) 2005-06-15 2021-07-27 CSignum Ltd. Communications system
US11750300B2 (en) 2005-06-15 2023-09-05 CSignum Ltd. Mobile device underwater communications system and method
US11063674B2 (en) 2005-06-15 2021-07-13 CSignum Ltd. Communications system
US12136957B2 (en) 2006-02-07 2024-11-05 CSignum Ltd. Mobile device underwater communications system and method
WO2009109745A1 (en) * 2008-03-05 2009-09-11 Schlumberger Holdings Limited Flexible pipe fatigue monitoring below the bend stiffener of a flexible riser
US8725429B2 (en) 2011-05-27 2014-05-13 Stress Engineering Services, Inc. Fatigue monitoring
CN102288376A (en) * 2011-08-02 2011-12-21 上海交通大学 Top-movable vortex-induced vibration rotating device for vertically-arranged vertical pipe under uniform flow and step flow
WO2014064190A3 (en) * 2012-10-24 2014-08-28 Fmc Kongsberg Subsea As Method of calculation loads on a subsea component.
US10767331B2 (en) 2013-12-23 2020-09-08 BP Exploration and Production, Inc. Riser fatigue monitoring
NO341582B1 (en) * 2015-04-14 2017-12-11 4Subsea As System og metode for å overvåke utmatting ved brønnhodet i undervannsbrønner
WO2017048941A1 (en) * 2015-09-15 2017-03-23 Noble Drilling Services Inc. Method for excavating a mud line cellar for subsea well drilling
US10364609B2 (en) 2015-09-15 2019-07-30 Noble Drilling Services Inc. Method for excavating mud line cellar for subsea well drilling
WO2018013777A1 (en) * 2016-07-13 2018-01-18 Ensco International Incorporated Riser deflection mitigation
US20230123839A1 (en) * 2018-02-14 2023-04-20 Maersk Drilling A/S Emergency disconnect system
US11788373B2 (en) * 2018-02-14 2023-10-17 Noble Drilling A/S Emergency disconnect system
US12072430B2 (en) 2018-08-13 2024-08-27 CSignum Ltd. Underwater navigation

Also Published As

Publication number Publication date
FR2840951A1 (en) 2003-12-19
US7080689B2 (en) 2006-07-25
FR2840951B1 (en) 2004-12-24
BR0302040A (en) 2004-09-08

Similar Documents

Publication Publication Date Title
US7080689B2 (en) Instrumentation assembly for an offshore riser
US7328741B2 (en) System for sensing riser motion
EP2886788B1 (en) Riser fatigue monitoring
US20180163532A1 (en) Systems and methods for real-time monitoring of a line
US10378331B2 (en) Monitoring integrity of a riser pipe network
US20140354974A1 (en) Apparatus and Method for Monitoring the Mechanical Properties of Subsea Longitudinal Vertical Components in Offshore Drilling and Production Applications
US20160326861A1 (en) Apparatus and Method for Monitoring the Mechanical Properties of Subsea Longitudinal Vertical Components in Offshore Drilling and Production Applications
WO2002088516A1 (en) Subsea drilling riser disconnect system and method
Myhre et al. Successful real time instrumentation of the conductor and surface casing of an exploration subsea well in the North Sea to measure the actual loads experienced during drilling operations
CN109829233B (en) Fatigue damage assessment method and monitoring and assessment system for fatigue hot spot of underwater wellhead
CN213363837U (en) Optical fiber sensor fixing device for deep-sea mixed transportation vertical pipe
Bompais et al. EMSO-Ligure Nice, a coastal cabled observatory dedicated to the study of slope stability
Karayaka et al. SS: Tahiti on-line monitoring system for steel catenary risers and flowlines
US4612993A (en) Riser position indication apparatus
King et al. The instrumentation of the conductor of a subsea well in the North Sea to measure the installed conditions and behavior under load
CN112178425A (en) Rapid fixing device and laying method for optical fiber sensor for deep-sea mixed transport vertical pipe
US20140354975A1 (en) Apparatus and Method for Measuring Mechanical Properties of Tendons in Tension Leg Platforms
Nilsen et al. Comprehensive instrumentation of two offshore rigs for wellhead fatigue monitoring
Mahoney et al. Flexible production riser system for floating production application in the North Sea
Podskarbi et al. Design consideration of monitoring systems for deepwater steel catenary risers (SCRs)
GB2586948A (en) Riser monitoring using distributed sensing
Maheshwari et al. Riser integrity monitoring techniques and data processing methods
Machado et al. Monitoring program for the first steel catenary riser installed in a moored floating platform in deep water
Edwards et al. Cascade/Chinook Disconnectable FPSO: Free Standing Hybrid Risers Monitoring via Acoustic Control/Communications
Miandro et al. An innovative approach for offshore subsidence monitoring: technology scouting, feasibility studies and realization

Legal Events

Date Code Title Description
AS Assignment

Owner name: INSTITUT FRANCAIS DU PETROLE, FRANCE

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:GUESNON, JEAN;VAISBERG, OLIVIER;PIGNARD, GUY;AND OTHERS;REEL/FRAME:014169/0755;SIGNING DATES FROM 20030424 TO 20030516

FEPP Fee payment procedure

Free format text: PAYOR NUMBER ASSIGNED (ORIGINAL EVENT CODE: ASPN); ENTITY STATUS OF PATENT OWNER: LARGE ENTITY

FPAY Fee payment

Year of fee payment: 4

REMI Maintenance fee reminder mailed
LAPS Lapse for failure to pay maintenance fees
STCH Information on status: patent discontinuation

Free format text: PATENT EXPIRED DUE TO NONPAYMENT OF MAINTENANCE FEES UNDER 37 CFR 1.362

FP Lapsed due to failure to pay maintenance fee

Effective date: 20140725