JPS6138100A - Method of filling construction of secondary lining concrete in shielding construction - Google Patents
Method of filling construction of secondary lining concrete in shielding constructionInfo
- Publication number
- JPS6138100A JPS6138100A JP15990084A JP15990084A JPS6138100A JP S6138100 A JPS6138100 A JP S6138100A JP 15990084 A JP15990084 A JP 15990084A JP 15990084 A JP15990084 A JP 15990084A JP S6138100 A JPS6138100 A JP S6138100A
- Authority
- JP
- Japan
- Prior art keywords
- segment
- construction
- concrete
- secondary lining
- main girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
シールド工事において、2次覆工コンクリートの充填率
は巻厚を管理する上で重要なポイントである。DETAILED DESCRIPTION OF THE INVENTION In shield construction, the filling rate of the secondary lining concrete is an important point in controlling the roll thickness.
特にスチールセグメントの場合は、規定量のコンクリー
トが入りK<<出来形の良否に直接影響するものである
。Particularly in the case of steel segments, a specified amount of concrete enters K<< which directly affects the quality of the finished shape.
セグメントは内部方向に主桁が突出形成されているので
コンクリートを打設すると下部の空気は上部に抜けるが
上部の空気は抜けにくく、特に天端付近では主桁と主桁
の間の空気は桁に邪魔されて横に抜けないためコンクリ
ートに空隙を作る結饗となり、特にスチールセグメント
の場合はセグメントの7ランジが多いため各々のフラン
ジ間の空気はセグメント裏面に残ったま〜コンクリート
が凝固するので危険率が多くなる等の欠点を有している
ものである。The main girders of the segments protrude inward, so when concrete is poured, the air at the bottom escapes to the top, but it is difficult for the air at the top to escape.Especially near the top, the air between the main girders flows through the girders. This is dangerous because the air between the flanges remains on the back side of the segment because there are many 7-flange flanges in the case of steel segments, and the concrete solidifies, which is dangerous. This method has disadvantages such as an increase in the ratio.
本願はこれ等の欠点に鑑みセグメントの天端−トが打設
されて来る側の空気を未だ打設さにていない側圧押し出
し、最終的には天端空隙に開口するドリル削孔よりほと
んど外部に押し出しコンクリートを確実、気密に打設す
ることができるようにしたことを目的としたシールド工
事における2次覆工コンクリートの充填工法に関する発
明である。In view of these drawbacks, the present invention aims to push out the air on the side where the top end of the segment is being cast, and to push out the air on the side where the top end of the segment has not yet been cast. This invention relates to a method for filling secondary lining concrete in shield construction, with the aim of making it possible to reliably and airtightly place extruded concrete.
今、前記目的を達するための実施例を述べれば、1次セ
グメント埋設工事終了後、コンクリートセグメント或は
スチールセグメント(1)の内部方向忙突出形成されて
いる主桁或は7ランジ(2)k対し、セグメン) (1
1の内面に開口端部(3a)が接するよう忙してU字形
パイプ(3)を嵌合固定する。Now, to describe an embodiment for achieving the above-mentioned purpose, after the completion of the primary segment burying work, the main girder or 7 langes (2) k which are formed to protrude inward from the concrete segment or steel segment (1). On the other hand, segment) (1
The U-shaped pipe (3) is fitted and fixed so that the open end (3a) is in contact with the inner surface of the pipe.
U字形パイプ(3)と主桁或はフランジ(2)との固定
に当って、U字形パイプ(3)の中央の空間(3b)K
主桁フランジ(2)を嵌合し、U字形パイプ(3)の開
口端部(3a)はセグメン) (11の内面(1a)に
極く接近して位置させU字形パイプ(3)と主桁フラン
ジ(2)と適宜固定する。When fixing the U-shaped pipe (3) and the main girder or flange (2), the space (3b) K in the center of the U-shaped pipe (3) is
The main girder flange (2) is fitted, and the open end (3a) of the U-shaped pipe (3) is positioned very close to the inner surface (1a) of the segment) (11), and the U-shaped pipe (3) and the main Fix it to the girder flange (2) as appropriate.
U字形パイプ(3)を取り付ける場所としてはシールド
(4)の上半分以上の箇所で特に天端付近に取り付ける
。The U-shaped pipe (3) should be installed above the upper half of the shield (4), especially near the top.
これはシールド(4)の下半分及び側面付近に形成され
る空隙の空気はコンクリートの打設により容易忙上方に
押し出され残ることがないが、天端付近では主桁或は7
ランジ(2)等により横移動を阻止されて空隙にそのま
〜残るためである。This is because the air in the void formed near the lower half and sides of the shield (4) is easily pushed upwards by concrete pouring and does not remain, but near the top of the shield (4) the air in the void formed near the main girder or 7
This is because the lateral movement is prevented by the lunge (2) and the like and it remains in the gap.
本願は前記のように準備した後、コンクリートを下部よ
り打設していくと型枠内の空隙の空気はコンクリ−)
(51K押され横方向或は上部方向に押し出され、コン
クリート(5)はセグメントと型枠間に充填されていく
。In this application, after preparing as described above, when concrete is poured from the bottom, the air in the voids in the formwork is removed from the concrete.)
(The concrete (5) is pushed out horizontally or upwardly by 51K, and the space between the segment and the formwork is filled with concrete (5).
しかし上部に行くに従って主桁7ランジ(2)が壁面と
なる空1!i (61の空気はコンクリート(5)によ
り成る程度は圧縮されて体積を縮めるが一定以上は縮ま
らないのでコンクリ−) (5>が打設されない状態と
なる。However, as you go to the top, the main girder 7 lunge (2) becomes a wall surface! i (The air in 61 is compressed by concrete (5) and its volume is reduced, but it does not shrink beyond a certain level, so it is concrete) (5> is not placed).
そこで本願は前記したように主桁フランジ(2)の両側
忙わたるようにU字形パイプ(3)を設けたこと釦より
、空隙の空気はコンクリート(5)が打設されて来る側
より他側にU字形パイプ(3)の孔な通じて矢印囚のよ
うに排出され、このようにして順次主桁フランジ(2)
をくぐるようKしてコンクリート(5)の打設されてい
ないセグメン) (11の内面に移り、最終的にはU字
形パイプ(3)により抜けた空気は順次セグメントを伝
わって排出され内部に空気を残すことなく打設できるも
のである。Therefore, as mentioned above, in this application, the U-shaped pipe (3) is provided so that both sides of the main girder flange (2) are connected. It is discharged through the hole of the U-shaped pipe (3) as shown by the arrow, and in this way it is sequentially discharged from the main girder flange (2).
(The air moves to the inner surface of 11 and finally escapes through the U-shaped pipe (3), passing through the segments and exhausting the air inside.) It can be poured without leaving any residue.
実施例
2次覆工開始後、53スパン経過した時点でU字形パイ
プ便用忙よる充填率の向上と天端の空隙調査を行った。Example: After 53 spans had passed after the start of secondary lining, the filling rate of the U-shaped pipe was improved and the voids at the top were investigated.
と
Uo = 4.713> U (2α)=3.。90と
なり有意水準(危険率)1%でU字形パイプを使用した
方が充填率が向上した。and Uo = 4.713> U (2α) = 3. . 90, and at a significance level (risk rate) of 1%, the filling rate was improved by using the U-shaped pipe.
以上の結果から、天端空隙が備単位から線単位と1オー
ダ少なくなり打ち込み充填率も約2%上昇した。これは
天端の空気を排除する事により達成されたものである。From the above results, the gap at the top was reduced by one order from the unit to the line, and the implant filling rate increased by about 2%. This was achieved by eliminating the air at the top.
本願は叙上のようにシールド工事におケルセグメント構
設後、セグメントの天端部の長手方と
向圧設けた天端部近傍の主桁に開口部がセグメント内面
に接近させ且つ彎曲部中央に主桁を嵌合させてU字形パ
イプを適宜数取付けた後、セグメントと内型枠間にコン
クリートを打設して成ることを特徴とするので良く所期
の目的を達することができるものである。As described above, after constructing the Kel segment in the shield work, the opening in the main girder near the top end is provided with counter pressure in the longitudinal direction of the top end of the segment, and the opening approaches the inner surface of the segment and the center of the curved part. The main girder is fitted to the main girder, an appropriate number of U-shaped pipes are installed, and then concrete is poured between the segments and the inner formwork, so it is possible to achieve the desired purpose. be.
第1図はシールドの断面図、第2図は第1図のB部の拡
大断面図、第3図は第2図のC−C断面図である。FIG. 1 is a sectional view of the shield, FIG. 2 is an enlarged sectional view of section B in FIG. 1, and FIG. 3 is a sectional view taken along line CC in FIG.
Claims (1)
ントの天端部の長手方向に設けた天端部近傍の主桁に開
口部をセグメント内面に接近させ且つ彎曲部中央に主桁
を嵌合させてU字形パイプを適宜数取付けた後、セグメ
ントと内型枠間にコンクリートを打設して成ることを特
徴とするシールド工事における2次覆工コンクリートの
充填工法。(1) After constructing the segment during shield construction, the opening of the main girder near the top end of the segment is placed in the longitudinal direction, and the opening approaches the inner surface of the segment, and the main girder is fitted into the center of the curved part. A secondary lining concrete filling method in shield construction, characterized by installing an appropriate number of U-shaped pipes and then pouring concrete between the segments and the inner formwork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15990084A JPS6138100A (en) | 1984-07-30 | 1984-07-30 | Method of filling construction of secondary lining concrete in shielding construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15990084A JPS6138100A (en) | 1984-07-30 | 1984-07-30 | Method of filling construction of secondary lining concrete in shielding construction |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6138100A true JPS6138100A (en) | 1986-02-24 |
Family
ID=15703623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15990084A Pending JPS6138100A (en) | 1984-07-30 | 1984-07-30 | Method of filling construction of secondary lining concrete in shielding construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6138100A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5112001A (en) * | 1989-09-30 | 1992-05-12 | Teijin Seiki Co., Ltd. | Yarn winding method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5021773A (en) * | 1973-06-25 | 1975-03-07 | ||
JPS5673799A (en) * | 1979-11-22 | 1981-06-18 | Nippon Steel Corp | Method of covering tunnel |
-
1984
- 1984-07-30 JP JP15990084A patent/JPS6138100A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5021773A (en) * | 1973-06-25 | 1975-03-07 | ||
JPS5673799A (en) * | 1979-11-22 | 1981-06-18 | Nippon Steel Corp | Method of covering tunnel |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5112001A (en) * | 1989-09-30 | 1992-05-12 | Teijin Seiki Co., Ltd. | Yarn winding method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4042229A (en) | Tundish with weirs | |
CH547931A (en) | SUPPORT STRUCTURE OF THE PANELS OF A FORMWORK FOR THE CASTING OF CONCRETE. | |
JPS6156393B2 (en) | ||
JPS6138100A (en) | Method of filling construction of secondary lining concrete in shielding construction | |
GB2135918B (en) | Pouring tube for casting steel | |
JPS6254959B2 (en) | ||
CN110205943A (en) | The construction method of prefabricated freely-supported small box girder end floor beam | |
BE889575A (en) | PROCESS FOR THE MANUFACTURE OF STEEL CONCRETE REINFORCEMENTS WITH IMPROVED PROPERTIES. | |
JPS6335998A (en) | Tunnel lining method | |
CN219638470U (en) | Precast concrete plugging device | |
JPS6127538B2 (en) | ||
CN218405887U (en) | Partition wall connection structure for steel construction building | |
CN216641446U (en) | Post-cast plate seam leak protection structure | |
FR2466289B1 (en) | LINGOTIERE FOR HORIZONTAL CONTINUOUS CASTING OF METALS, ESPECIALLY FOR STEEL CASTING | |
JPS52132504A (en) | Method of pouring mortar forming antiicorrosive cover of steel pipe piles | |
JPS6142458A (en) | Casting method using tundish | |
JPS6351212B2 (en) | ||
JPS58138864A (en) | Reinforcement of small beam | |
JPS6335997A (en) | Tunnel lining method | |
JPS587099A (en) | Method of placing construction of secondary mudcap | |
JPH041832B2 (en) | ||
FR2415697A1 (en) | Permanent precast concrete shutter for floor slab - is cast onto bottom boom lattice work joist and has T=section to enable use without propping | |
SU796467A1 (en) | Method of compacting the external walls of artificial rock body | |
JPH0439545B2 (en) | ||
SE8002820L (en) | DEVICE FOR CONTINUOUS CASTING OF STEEL |