JPH0579049A - Constructing method for beam and slab in underground body construction work - Google Patents
Constructing method for beam and slab in underground body construction workInfo
- Publication number
- JPH0579049A JPH0579049A JP3241250A JP24125091A JPH0579049A JP H0579049 A JPH0579049 A JP H0579049A JP 3241250 A JP3241250 A JP 3241250A JP 24125091 A JP24125091 A JP 24125091A JP H0579049 A JPH0579049 A JP H0579049A
- Authority
- JP
- Japan
- Prior art keywords
- slab
- formwork
- constructing
- underground
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は地下躯体工事における
梁、スラブの構築工法、詳しくは地下構築物の逆打工法
における地下階の梁、スラブの構築工法に係るものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a beam and a slab in an underground skeleton construction, and more particularly to a method for constructing a beam and a slab in a basement floor in a reverse construction method for an underground structure.
【0002】[0002]
【従来の技術】従来、地下構造物の逆打工法における地
下階の梁、スラブの施工に際しては、建物周囲の外壁に
沿って山留aを施工したのち、構築物を支持する仮支
柱、または構真柱bを埋設して地下階を支持し、同地下
階のスラブc、梁dを構築するもので、逆打階の梁、ス
ラブ下の適宜深さまで掘削し、同掘削レベルに捨てコン
クリートを打設して当階の柱型、梁型、スラブを形成す
るための合金型枠とパイプ、緊結金物等により型枠を組
立て、捨てコンクリートを前記型枠下部をサポートのよ
うな支保工によって支持し、鉄筋を組立てたのちコンク
リートを打設し、打設コンクリートが所要の強度を発現
したのち、前記型枠を解体して次の下階に繰り返し工事
を進めていく。(図9参照) 基礎部eも同様に所定の深さまで、掘削したのち、捨て
コンクリートを打設して梁、スラブの合板型枠を組立
て、鉄筋を組立てたのち、コンクリートを打設し、同打
設コンクリートが所定の強度を発現したのち、前記型枠
を解体する。図中fは杭、gはトツプスラブである。2. Description of the Related Art Conventionally, when constructing a beam or slab on the basement floor in the reverse construction method for an underground structure, after constructing a mountain retaining a along the outer wall around the building, a temporary pillar or a structure for supporting the structure is constructed. By embedding the true pillar b and supporting the basement, and constructing the slab c and the beam d on the same basement, excavation to the appropriate depth below the beam and slab on the opposite floor, and discarding concrete to the same excavation level. Assemble the formwork by casting it to form pillars, beams, alloy formwork and pipes to form slabs, pipes, binding materials, etc., and support discarded concrete by supporting work such as the lower part of the formwork. Then, after assembling the reinforcing bars, the concrete is poured, and after the cast concrete exhibits the required strength, the formwork is dismantled and the construction is repeated on the next lower floor. (Refer to FIG. 9) Similarly, the foundation part e is also excavated to a predetermined depth, then casts discarded concrete to assemble plywood formwork for beams and slabs, assembles reinforcing bars, and then casts concrete. After the cast concrete exhibits a predetermined strength, the formwork is disassembled. In the figure, f is a pile and g is a top slab.
【0003】前記工法の他、従来図10に示す如きグラ
ンドフオーム工法が行なわれている。この工法は、地下
所定階の梁型、スラブ下まで掘削して、同掘削面におけ
る梁型部gにはビニルシートhを敷き、他のスラブi下
には掘削面に敷きモルタルkを平滑に敷き均らして、梁
型部gのみ型枠を組立てる工法である。In addition to the above-mentioned construction method, a ground-form construction method as shown in FIG. 10 has been conventionally used. In this construction method, a beam type on a predetermined basement floor is excavated up to the bottom of the slab, a vinyl sheet h is laid on the beam type part g on the same excavation surface, and a mortar k is laid on the excavation surface under the other slab i. This is a construction method in which the molds are laid out evenly and only the beam mold part g is assembled.
【0004】[0004]
【発明が解決しようとする課題】前記従来工法によれ
ば、型枠の組立に型枠用合板、端太パイプ、フオームタ
イ等の各種型枠資材及び型枠組立資材を大量に必要と
し、資材管理、資材の損耗等でコストが嵩み、スラブは
サポートで支保する支保工作業が必要となり、これら型
枠の組立、解体作業は多大の労力を要し、専門職の型枠
工で行なうため作業員の確保が至難である。According to the above-mentioned conventional method, a large amount of various formwork materials such as formwork plywood, thick pipes, form ties, and formwork assembly materials are required for assembly of formwork, and material management is required. However, the cost increases due to the wear of materials, etc., and the support work for supporting the slab is required, and the work of assembling and disassembling these forms requires a great deal of work, and is performed by a professional formworker. It is very difficult to secure a member.
【0005】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は専門職の作
業員を要せず、且つ大量の型枠資材支保工を要せず、省
力化が図られ、工費が節減される地下躯体工事における
梁、スラブの構築工法を提供する点にある。The present invention has been proposed in view of the above-mentioned problems of the prior art, and the object of the present invention is that it does not require a professional worker and a large amount of formwork material support work. The purpose is to provide a construction method for beams and slabs in underground framing work that saves labor and saves construction costs.
【0006】[0006]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る地下躯体工事における梁、スラブの構
築工法によれば、地上部より地下下方に向って順次地下
躯体を構築する逆打工法において、構築階の最大の梁成
を有する梁よりやや下部まで掘削し、同掘削部底面に敷
き砂を平滑に敷き均し、同敷き砂上に均一に下地板を敷
設して同下地板上に型枠ユニツトによって梁及びスラブ
型枠を組立て、同各型枠に鉄筋を組立ててコンクリート
を打設し、同打設コンクリートが所定の強度を発現した
のち、次の下層を掘削するとともに、前記型枠を解体し
て地下躯体を構築するものである。In order to achieve the above object, according to the method of constructing a beam and a slab in an underground skeleton construction work according to the present invention, a reverse skeleton is constructed by sequentially constructing an underground skeleton from an above-ground portion toward a lower underground. In the driving method, excavation is carried out to a little lower than the beam having the largest beam composition on the construction floor, the sand is spread evenly on the bottom of the excavated part, and the base plate is laid evenly on the spread sand. Assemble the beam and slab formwork with the formwork unit on the top, assemble the rebar in each of the formwork and place concrete, and after the placed concrete develops a predetermined strength, excavate the next lower layer, The formwork is disassembled to construct an underground structure.
【0007】[0007]
【作用】本発明によれば前記したように、逆打工法にお
いて構築階における最大の梁成を有する梁よりやや下部
まで掘削し、同掘削部底面に平滑に敷き均らした敷き砂
上に均一に地下板を敷設して、掘削地盤自体を梁型スラ
ブの支持盤として利用して前記下地板上に梁及びスラブ
型枠を組立て、支保工を不要ならしめるとともに、同型
枠を型枠ユニツトによって構成することによって、型枠
用合板、型枠組立用資材を不要ならしめるものである。According to the present invention, as described above, in the reverse striking method, excavation is carried out to a little lower than the beam having the largest beam formation in the construction floor, and the sand is evenly spread evenly on the bottom surface of the excavated part and evenly distributed. By laying an underground plate and using the excavated ground itself as a support plate for the beam slab to assemble the beam and slab form on the base plate to eliminate the need for supporting work and to construct the form with a form unit. By doing so, the plywood for the formwork and the material for assembling the formwork are made unnecessary.
【0008】[0008]
【実施例】以下本発明を図示の実施例について説明す
る。図1に示す如く逆打工法において構築階における最
大の梁成を有する梁位置よりやや下まで水平に掘削し、
同掘削面1に敷き砂2を平滑に敷きならし、同敷き砂2
上に均一に発泡樹脂より構成された図3に示す下地板3
を敷設し、同下地板3上に大梁型枠4及びスラブ型枠5
を組立てる。The present invention will be described below with reference to the illustrated embodiments. As shown in Fig. 1, in the reverse construction method, horizontal excavation is carried out to a little below the beam position with the largest beam formation on the construction floor,
Spread the sand 2 evenly on the excavated surface 1 and spread the sand 2
The base plate 3 shown in FIG.
Laying down, and girder form 4 and slab form 5 on the base plate 3
Assemble
【0009】大梁型枠4は相対する一双の発泡樹脂より
構成されたL型板4aより構成され、(図4参照)スラ
ブ型枠5は対向面に係止凹窩6が列設された発泡樹脂よ
り構成された上下一双の水平板5aと、同各水平板5a
の凹窩6に亘って嵌装された発泡樹脂製の束材5bより
構成されている。(図5及び図6参照) なお小梁型枠4′は前記L型板4aより小型の一双のL
型板4′aの下方と下地板3との間に、図7に示す発泡
樹脂製の補助ユニツト材7を介装して構成される。The girder mold 4 is composed of an L-shaped plate 4a made of a pair of opposing resin foams (see FIG. 4), and the slab mold 5 is foamed in which locking recesses 6 are formed in rows on the opposite surfaces. A pair of upper and lower horizontal plates 5a made of resin, and each horizontal plate 5a.
It is composed of a bundle material 5b made of foamed resin, which is fitted over the recesses 6 of FIG. (See FIGS. 5 and 6) The beam form 4'is a pair of Ls smaller than the L-shaped plate 4a.
Between the lower side of the template 4'a and the base plate 3, an auxiliary unit material 7 made of foamed resin shown in FIG. 7 is interposed.
【0010】次いで前記大梁型枠4、小梁型枠4′、及
びスラブ型枠5に夫々梁鉄筋8,8′、スラブ鉄筋9を
組立ててコンクリートを打設し、同打設コンクリートが
所定強度を発現するのをまって下層を掘削し、前記各型
枠を脱型し、大梁、小梁及びスラブを構築する。図2は
本発明の他の実施例を示し、図8に示す如き一定のサイ
ズに成形された発泡樹脂ブロツク10を梁、スラブの形
状に積上げて型枠とし、地下躯体を構成した場合を示
す。Next, beam reinforcements 8 and 8'and slab reinforcements 9 are respectively assembled to the large beam formwork 4, the small beam formwork 4'and the slab formwork 5 and concrete is poured into them, and the cast concrete has a predetermined strength. After that, the lower layer is excavated, the molds are demolded, and girders, girders, and slabs are constructed. FIG. 2 shows another embodiment of the present invention, showing a case where a foamed resin block 10 molded into a certain size as shown in FIG. 8 is stacked in the shape of a beam or a slab to form a formwork to form an underground structure. .
【0011】図中、前記実施例と均等部分には同一符号
が付されている。In the figure, the same parts as those in the above embodiment are designated by the same reference numerals.
【0012】[0012]
【発明の効果】本発明によれば前記したように型枠をユ
ニツト化することによって、従来のように梁型の加工を
要せず、簡単に型枠が組立てられる。また本発明によれ
ば掘削地盤を梁型、スラブの支持盤とすることによって
支保工が不要となり、型枠合板、端太パイプ、フオーム
タイ等の各種の資材を使用することなくコンクリート
梁、スラブが施工できるので、資材の管理、損耗の問題
がなくなる。As described above, according to the present invention, by unitizing the mold as described above, it is possible to easily assemble the mold without the need for beam-shaped machining as in the conventional case. Further, according to the present invention, since the excavated ground is a beam type, a supporting plate for the slab does not require support work, and concrete beams and slabs can be used without using various materials such as formwork plywood, thick pipes and foam ties. Since it can be installed, there is no problem of material management and wear.
【0013】請求項2の発明は、梁型枠ユニツトを相対
する1双のL型板より構成し、スラブ型枠ユニツトを上
下一双の水平板と束材とより構成したことによって、型
枠の組立、解体が専門職によることなく簡単に行なわ
れ、省力化と工費の節減が図られる。請求項3の発明は
前記型枠ユニツトを発泡樹脂製としたことによって軽量
で耐食性を有し、型枠の組立、分解がより簡単に行なわ
れ、使用済みの型枠ユニツトは回収されて再使用に供せ
られ、経済性が向上される。According to the second aspect of the present invention, the beam form unit is composed of one pair of L-shaped plates facing each other, and the slab form unit is composed of one pair of upper and lower horizontal plates and a bundle member. Assembling and disassembling can be performed easily without the need for a professional, saving labor and reducing construction costs. According to the invention of claim 3, since the mold unit is made of foamed resin, it is lightweight and has corrosion resistance, the mold can be assembled and disassembled more easily, and the used mold unit can be recovered and reused. It is provided to the public and the economic efficiency is improved.
【図面の簡単な説明】[Brief description of drawings]
【図1】本発明に係る地下躯体工事における梁、スラブ
の構築工法の一実施例の実施状況を示す縦断面図であ
る。FIG. 1 is a vertical cross-sectional view showing an implementation state of an embodiment of a construction method for a beam and a slab in an underground skeleton construction work according to the present invention.
【図2】本発明の他の実施例の実施状況を示す縦断面図
である。FIG. 2 is a vertical cross-sectional view showing an implementation situation of another embodiment of the present invention.
【図3】下地板の斜視図である。FIG. 3 is a perspective view of a base plate.
【図4】梁型枠ユニツトの斜視図である。FIG. 4 is a perspective view of a beam form unit.
【図5】スラブ型枠ユニツトにおける水平板の斜視図で
ある。FIG. 5 is a perspective view of a horizontal plate in the slab form unit.
【図6】スラブ型枠ユニツトにおける束材の斜視図であ
る。FIG. 6 is a perspective view of a bundle material in the slab form unit.
【図7】補助ユニツトの斜視図である。FIG. 7 is a perspective view of an auxiliary unit.
【図8】発泡樹脂ブロツクの斜視図である。FIG. 8 is a perspective view of a foamed resin block.
【図9】従来工法の1例を示す縦断面図である。FIG. 9 is a vertical sectional view showing an example of a conventional method.
【図10】従来工法の他の例を示す縦断面図である。FIG. 10 is a vertical cross-sectional view showing another example of the conventional method.
1 掘削面 2 敷き砂 3 下地板 4 大梁型枠 4a L型板 4′ 小梁型枠 4′a L型板 5 スラブ型枠 5a 水平板 5b 束材 6 係止凹窩 7 補助ユニツト 8,8′ 梁鉄筋 9 スラブ鉄筋 1 excavated surface 2 spread sand 3 base plate 4 girder formwork 4a L-shape plate 4'small beam formwork 4'a L-shape plate 5 slab formwork 5a horizontal plate 5b bundle 6 locking recess 7 auxiliary unit 8, 8 ′ Beam reinforcement 9 Slab reinforcement
Claims (3)
体を構築する逆打工法において、構築階の最大の梁成を
有する梁よりやや下部まで掘削し、同掘削部底面に敷き
砂を平滑に敷き均し、同敷き砂上に均一に下地板を敷設
して同下地板上に型枠ユニツトによって梁及びスラブ型
枠を組立て、同各型枠に鉄筋を組立ててコンクリートを
打設し、同打設コンクリートが所定の強度を発現したの
ち、次の下層を掘削するとともに、前記型枠を解体して
地下躯体を構築することを特徴とする地下躯体工事にお
ける梁、スラブ構築工法。1. In the reverse driving method for constructing an underground skeleton sequentially from the above-ground part to the lower part of the underground, excavation is carried out to a part lower than the beam having the largest beam composition of the construction floor, and the sand spread on the bottom of the excavated part is smoothed. And lay the base plate evenly on the same sand, assemble the beams and slab formwork on the base plate with the formwork unit, assemble the reinforcing bars in each formwork, and place concrete. A method for constructing a beam or slab in an underground skeleton construction, which comprises constructing an underground skeleton by disassembling the formwork and constructing an underground skeleton while excavating the next lower layer after the cast concrete exhibits a predetermined strength.
より構成され、スラブ型枠ユニツトは上下一双の水平板
と、同各水平板を連結する束材とによって構成された請
求項1記載の地下躯体工事における梁、スラブの構築工
法。2. The beam form unit is composed of a pair of L-shaped plates facing each other, and the slab form unit is composed of a pair of upper and lower horizontal plates and a bundle member connecting the horizontal plates. Construction method of beams and slabs in the underground structure work described.
形された請求項2記載の地下躯体工事における梁、スラ
ブの構築工法。3. The method for constructing a beam or slab in an underground skeleton construction according to claim 2, wherein the form unit is formed of foamed resin.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3241250A JP2769936B2 (en) | 1991-09-20 | 1991-09-20 | Construction method of beams and slabs in underground skeleton construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3241250A JP2769936B2 (en) | 1991-09-20 | 1991-09-20 | Construction method of beams and slabs in underground skeleton construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0579049A true JPH0579049A (en) | 1993-03-30 |
JP2769936B2 JP2769936B2 (en) | 1998-06-25 |
Family
ID=17071444
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3241250A Expired - Fee Related JP2769936B2 (en) | 1991-09-20 | 1991-09-20 | Construction method of beams and slabs in underground skeleton construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2769936B2 (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0748848A (en) * | 1993-08-10 | 1995-02-21 | Kajima Corp | Construction method for underground skeleton by inverted construction method |
JPH07127080A (en) * | 1993-11-04 | 1995-05-16 | Takenaka Komuten Co Ltd | Beam and floor constructing method in inversely placing constructing method |
JPH07127081A (en) * | 1993-11-05 | 1995-05-16 | Takenaka Komuten Co Ltd | Beam and floor constructing method in inversely placing constructing method |
JPH07189396A (en) * | 1993-12-27 | 1995-07-28 | Kumagai Gumi Co Ltd | Floor slab construction method |
JPH07293003A (en) * | 1994-04-22 | 1995-11-07 | Dow Kakoh Kk | Construction method for slab form |
JPH08158384A (en) * | 1994-12-01 | 1996-06-18 | Takenaka Komuten Co Ltd | Timbering of floor form, etc. |
JPH08165661A (en) * | 1994-12-12 | 1996-06-25 | Takenaka Komuten Co Ltd | Construction method of underground structure |
WO2008123298A1 (en) | 2007-03-26 | 2008-10-16 | Hirofumi Matsui | Infusion preparation for cancer patient |
JP2017206882A (en) * | 2016-05-19 | 2017-11-24 | 鹿島建設株式会社 | Method of constructing underground structure |
CN110029810A (en) * | 2019-05-15 | 2019-07-19 | 中铁建设集团有限公司 | It is a kind of to have enough to meet the need template system for the construction of contrary sequence method horizontal member |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04281920A (en) * | 1991-03-11 | 1992-10-07 | Taisei Corp | Construction beam |
-
1991
- 1991-09-20 JP JP3241250A patent/JP2769936B2/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04281920A (en) * | 1991-03-11 | 1992-10-07 | Taisei Corp | Construction beam |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0748848A (en) * | 1993-08-10 | 1995-02-21 | Kajima Corp | Construction method for underground skeleton by inverted construction method |
JPH07127080A (en) * | 1993-11-04 | 1995-05-16 | Takenaka Komuten Co Ltd | Beam and floor constructing method in inversely placing constructing method |
JPH07127081A (en) * | 1993-11-05 | 1995-05-16 | Takenaka Komuten Co Ltd | Beam and floor constructing method in inversely placing constructing method |
JPH07189396A (en) * | 1993-12-27 | 1995-07-28 | Kumagai Gumi Co Ltd | Floor slab construction method |
JPH07293003A (en) * | 1994-04-22 | 1995-11-07 | Dow Kakoh Kk | Construction method for slab form |
JPH08158384A (en) * | 1994-12-01 | 1996-06-18 | Takenaka Komuten Co Ltd | Timbering of floor form, etc. |
JPH08165661A (en) * | 1994-12-12 | 1996-06-25 | Takenaka Komuten Co Ltd | Construction method of underground structure |
WO2008123298A1 (en) | 2007-03-26 | 2008-10-16 | Hirofumi Matsui | Infusion preparation for cancer patient |
JP2017206882A (en) * | 2016-05-19 | 2017-11-24 | 鹿島建設株式会社 | Method of constructing underground structure |
CN110029810A (en) * | 2019-05-15 | 2019-07-19 | 中铁建设集团有限公司 | It is a kind of to have enough to meet the need template system for the construction of contrary sequence method horizontal member |
Also Published As
Publication number | Publication date |
---|---|
JP2769936B2 (en) | 1998-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH0579049A (en) | Constructing method for beam and slab in underground body construction work | |
JPS609178B2 (en) | How to install garden or boundary wall panels | |
JP7112635B1 (en) | U-shaped throwaway formwork for rising foundations of buildings | |
JP2641182B2 (en) | Slope stabilization method and slope expansion method | |
JPH08177059A (en) | Footing block, and integrated method for constructing continuous footing employing footing block | |
JPH06264453A (en) | Precast concrete-made permanent form for foundation, and foundation practice using its form | |
JPH07138972A (en) | Construction method for underground skeleton | |
JPH10299003A (en) | Foundation work using precast concrete member | |
JPS6123092Y2 (en) | ||
JP3713117B2 (en) | How to build the foundation | |
JPH11323958A (en) | Execution method of building and concrete product used therefor | |
JP2757032B2 (en) | Construction method of underground building with pillars with capital by reverse hitting method | |
JPH1121860A (en) | Construction method for wall-form concrete structure | |
JPH0711630A (en) | Method of underground continuous wall used for precast prestressed concrete slab wall | |
CN1309219A (en) | Construction method for assembling shutterings of multi-storey building at same time and pouring cement grout once | |
JP2000064300A (en) | Continuous footing execution method | |
JP3108898B2 (en) | Construction method of underground structure by reverse construction method | |
JPS62253821A (en) | Construction of concrete floor slab | |
JPS5858503B2 (en) | Construction method of reinforced concrete composite wall | |
JPH07127081A (en) | Beam and floor constructing method in inversely placing constructing method | |
JP3058503B2 (en) | Natural stone precast plate and its construction method | |
JPH08269979A (en) | Single-side precast concrete underground beam and its constituent member | |
JPS60341Y2 (en) | stacked block foundation frame | |
JPH07113220B2 (en) | Beam construction method | |
CN115652803A (en) | Precast beam diaphragm plate on-site connection construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080417 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090417 Year of fee payment: 11 |
|
LAPS | Cancellation because of no payment of annual fees |