JP6267547B2 - Jig for production of concrete filled steel segment - Google Patents

Jig for production of concrete filled steel segment Download PDF

Info

Publication number
JP6267547B2
JP6267547B2 JP2014044754A JP2014044754A JP6267547B2 JP 6267547 B2 JP6267547 B2 JP 6267547B2 JP 2014044754 A JP2014044754 A JP 2014044754A JP 2014044754 A JP2014044754 A JP 2014044754A JP 6267547 B2 JP6267547 B2 JP 6267547B2
Authority
JP
Japan
Prior art keywords
plate
concrete
frame
jig
partition plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014044754A
Other languages
Japanese (ja)
Other versions
JP2015168986A (en
Inventor
中村 和憲
和憲 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Metal Products and Engineering Inc
Original Assignee
JFE Metal Products and Engineering Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Metal Products and Engineering Inc filed Critical JFE Metal Products and Engineering Inc
Priority to JP2014044754A priority Critical patent/JP6267547B2/en
Publication of JP2015168986A publication Critical patent/JP2015168986A/en
Application granted granted Critical
Publication of JP6267547B2 publication Critical patent/JP6267547B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

この発明は、コンクリート中詰鋼製セグメント製造用治具、特に、セグメントを周方向にリング状に連結する際に使用される継手板用ボルトの締結作業用空間を形成するためのコンクリート中詰鋼製セグメント製造用治具に関するものである。   The present invention relates to a jig for manufacturing a segment of concrete-filled steel, and in particular, concrete-filled steel for forming a fastening space for a joint plate bolt used when connecting the segments in a ring shape in the circumferential direction. The present invention relates to a segment manufacturing jig.

トンネル構築法の一つにシールド工法がある。シールド工法とは、立坑内に設置した掘進機を一定長さ掘進させる毎に、その後部で、例えば、円弧状のコンクリート中詰鋼製セグメント(既存の鋼製セグメントの鋼製枠(鋼殻)内にコンクリートを予め工場で中詰めさせたセグメントであるが、設計思想として、鋼材とコンクリートを強度的に相互補完しあった合成効果を有する、いわゆる、「合成セグメント」も含まれる。)を周方向にリング状に組み立ててセグメントリングを構築し、これを順次、延長させて円筒形の覆工を形成してシールドトンネルを構築する工法である。   One of the tunnel construction methods is the shield method. With the shield method, every time the excavator installed in the vertical shaft is excavated for a certain length, the rear part, for example, an arc-shaped concrete filled steel segment (a steel frame (steel shell) of an existing steel segment) This is a segment in which concrete is packed in the factory in advance, but the design concept also includes a so-called “synthetic segment” that has a composite effect in which steel and concrete are mutually complemented in strength. This is a construction method in which a segment ring is constructed by assembling in a ring shape in the direction, and this is sequentially extended to form a cylindrical lining to construct a shield tunnel.

コンクリート中詰鋼製セグメントは、強度が高く、しかも、内周面には、コンクリートの余盛部が形成されているので、シールド工法の際に行う必要がある二次覆工、すなわち、セグメントリングの内周面をコンクリートで被覆して仕上げる工事を省略することができるといった利点を有している。   The concrete-filled steel segment is high in strength and has a concrete overfill on the inner peripheral surface, so the secondary lining that needs to be performed during the shield method, that is, the segment ring The construction of covering the inner peripheral surface of the concrete with concrete and finishing it can be omitted.

コンクリート中詰鋼製セグメントを、図面を参照しながら説明する。   The concrete-filled steel segment will be described with reference to the drawings.

図4は、コンクリート中詰鋼製セグメントを示す概略斜視図、図5は、従来法によりコンクリート中詰鋼製セグメントを製造する場合の鋼製枠を示す概略斜視図、図6は、側枠を示す背面図、図7は、中子位置における主桁への側枠の取り付け構造を示す縦断面図、図8は、発泡スチロール製ブロックを示す斜視図である。   4 is a schematic perspective view showing a concrete-filled steel segment, FIG. 5 is a schematic perspective view showing a steel frame when a concrete-filled steel segment is manufactured by a conventional method, and FIG. FIG. 7 is a longitudinal sectional view showing a structure for attaching the side frame to the main girder at the core position, and FIG. 8 is a perspective view showing a polystyrene foam block.

図4に示すように、コンクリート中詰鋼製セグメントは、鋼製枠1と鋼製枠1内に打設されたコンクリート2とから構成されている。   As shown in FIG. 4, the concrete-filled steel segment is composed of a steel frame 1 and concrete 2 placed in the steel frame 1.

鋼製枠1は、補強材3(通常は、「縦リブ」と呼ばれている。:図5参照)により連結された一対の円弧状の主桁4と、主桁4の両端部間に溶接された一対の継手板5と、主桁4の外周面に溶接されたスキンプレート6とからなっている。   The steel frame 1 is formed between a pair of arc-shaped main girders 4 connected by a reinforcing material 3 (usually called “vertical ribs”: see FIG. 5) and both ends of the main girders 4. It consists of a pair of welded joint plates 5 and a skin plate 6 welded to the outer peripheral surface of the main girder 4.

主桁4には、セグメントリングを軸方向に連結する主桁用ボルト(図示せず)のボルト孔7が形成され、継手板5には、セグメント同士を周方向にリング状に連結する継手板用ボルト(図示せず)のボルト孔8が形成されている。   The main girder 4 is formed with bolt holes 7 for main girder bolts (not shown) for connecting the segment rings in the axial direction, and the joint plate 5 is a joint plate for connecting the segments in a ring shape in the circumferential direction. Bolt holes 8 for use with bolts (not shown) are formed.

図4に示すように、コンクリート2において、ボルト孔7に対応する箇所には、前記主桁用ボルトの締結作業用空間となる凹陥部9(通常は、「ボルトボックス」と呼ばれている。)が形成され、ボルト孔8に対応する位置には、前記継手板用ボルトの締結作業用空間となる凹陥部10が形成されている。   As shown in FIG. 4, in the concrete 2, in a portion corresponding to the bolt hole 7, a recessed portion 9 (usually referred to as “bolt box”) serving as a space for fastening the main girder bolt. ) Is formed, and a recessed portion 10 is formed at a position corresponding to the bolt hole 8 as a space for fastening the joint plate bolt.

コンクリート2には、上述した二次覆工用の余盛部11が形成されている(図4参照)。   The concrete 2 is formed with the above-described secondary embedding portion 11 for secondary lining (see FIG. 4).

コンクリート中詰鋼製セグメントを製造するには、先ず、図5に示すような鋼製枠1を製作し、鋼製枠1内に凹陥部9を形成するための中子12(図7参照)と、凹陥部10を形成するための中子(図示せず)とを設置し、主桁4の外面に側枠13をボルト孔7を利用してボルト14により取り付け(図7参照)、側枠13の両端部間に端部枠15を取り付け(図5においては、側枠13の一方の端部間の端部枠15のみが記載されている。)、鋼製枠1内にコンクリートを打設し、そして、コンクリート硬化後、側枠13および端部枠15を取り外していた。   In order to manufacture a concrete-filled steel segment, first, a steel frame 1 as shown in FIG. 5 is manufactured, and a core 12 for forming a recessed portion 9 in the steel frame 1 (see FIG. 7). And a core (not shown) for forming the recessed portion 10 is installed, and the side frame 13 is attached to the outer surface of the main girder 4 with bolts 14 using the bolt holes 7 (see FIG. 7). An end frame 15 is attached between both ends of the frame 13 (in FIG. 5, only the end frame 15 between one end of the side frame 13 is shown), and concrete is put in the steel frame 1. After placing and concrete hardening, the side frame 13 and the end frame 15 were removed.

図6に示すように、側枠13の内面には、余盛部11を形成するための余盛枠16が側枠13に沿って取り付けられている。余盛枠16の板厚は、図7に示すように、主桁4の板厚より薄く形成されているので、余盛枠16の下面は、主桁4の内周面の外側に係合する。主桁4の内周面の外側を、図5、図7において、(a)で示す。   As shown in FIG. 6, a surplus frame 16 for forming the surplus portion 11 is attached to the inner surface of the side frame 13 along the side frame 13. As shown in FIG. 7, the thickness of the extra-frame 16 is formed thinner than the thickness of the main girder 4, so that the lower surface of the extra-frame 16 is engaged with the outside of the inner peripheral surface of the main girder 4. To do. The outside of the inner peripheral surface of the main girder 4 is indicated by (a) in FIGS.

コンクリート中詰鋼製セグメントは、上述したように製造されているが、以下のような問題があった。   The concrete-filled steel segment is manufactured as described above, but has the following problems.

シールドトンネルの曲線部に対応するために、幅が狭いコンクリート中詰鋼製セグメントを製造する必要性があった。即ち、曲線部の曲率により近似させる必要があるからである。図4中、セグメントの幅をW、セグメントの高さをHで示す。例えば、幅が30cmのコンクリート中詰鋼製セグメントを上記方法により製造する場合には、幅が狭すぎて、継手板用ボルトの締結作業を可能にする凹陥部10を形成するための中子の設置が行えない。   In order to accommodate the curved part of the shield tunnel, it was necessary to produce a narrow concrete filled steel segment. That is, it is necessary to approximate the curvature of the curved portion. In FIG. 4, the width of the segment is indicated by W and the height of the segment is indicated by H. For example, when a concrete-filled steel segment having a width of 30 cm is manufactured by the above-described method, the core is too narrow to form a recess 10 that allows a joint plate bolt to be fastened. Installation cannot be performed.

このために、従来は、図5に示すように、鋼製枠1の一方の継手板5a側の主桁4間を仕切板17により仕切り、一方の継手板5aと仕切板17との間の空間に、図8に示すような、余盛高さを有する発泡スチロール製ブロック18を嵌め込んで、コンクリートを打設していた。   Therefore, conventionally, as shown in FIG. 5, the main girder 4 on the side of one joint plate 5 a of the steel frame 1 is partitioned by a partition plate 17, and between the one joint plate 5 a and the partition plate 17. As shown in FIG. 8, a foamed polystyrene block 18 having a surplus height as shown in FIG.

しかし、以下のような問題があった。   However, there were the following problems.

(a)ブロック18の一部は、主桁4の内周面(板厚部)の内側に載せる必要があるので、ブロック18の上部両側には、段部18aが形成されている。主桁4の内周面の内側を、図5、図7において、(b)で示す。しかし、ブロック18は、発泡スチロール製であるために、段部18a部分が欠損し易く、この結果、ブロック18の反復使用が困難である。   (A) Since a part of the block 18 needs to be placed inside the inner peripheral surface (thickness portion) of the main beam 4, step portions 18 a are formed on both upper sides of the block 18. The inner side of the inner peripheral surface of the main girder 4 is indicated by (b) in FIGS. However, since the block 18 is made of polystyrene foam, the stepped portion 18a is easily lost, and as a result, it is difficult to repeatedly use the block 18.

(b)仕切板17の取り付け位置は、コンクリート中詰鋼製セグメント毎に若干、異なる。この結果、コンクリート中詰鋼製セグメントによっては、ブロック18と仕切板17との間に隙間が生じる場合がある。この問題を解決するには、コンクリート中詰鋼製セグメント毎にブロック18を用意する必要があるので、コストがかかる。   (B) The attachment position of the partition plate 17 is slightly different for each concrete-filled steel segment. As a result, a gap may be generated between the block 18 and the partition plate 17 depending on the concrete-filled steel segment. In order to solve this problem, it is necessary to prepare the block 18 for each concrete-filled steel segment, which is expensive.

従って、この発明の目的は、コンクリート中詰鋼製セグメント毎に仕切板の取り付け位置が変わっても、これに容易に対処することができる、セグメントを周方向にリング状に連結する際に使用される継手板用ボルトの締結作業用空間を形成するためのコンクリート中詰鋼製セグメント製造用治具を提供することにある。   Accordingly, an object of the present invention is used when connecting segments in a ring shape in the circumferential direction, which can easily cope with the change in the mounting position of the partition plate for each of the concrete-filled steel segments. Another object of the present invention is to provide a concrete-filled steel segment manufacturing jig for forming a space for fastening bolts for joint plates.

この発明は、上記目的を達成するためになされたものであって、下記を特徴とする。   The present invention has been made to achieve the above object, and is characterized by the following.

請求項1に記載の発明は、鋼製枠と前記鋼製枠内に打設されたコンクリートとから構成され、前記鋼製枠は、一対の主桁と、前記主桁の両端部間に溶接された一対の継手板と、前記主桁の外周面に溶接されたスキンプレートと、前記主桁の外側に着脱可能に取り付けられる側枠と、一方の前記継手板側の前記主桁間に溶接された仕切板とを備え、前記側枠の内面には、前記側枠に沿って余盛枠が取り付けられ、前記余盛枠の下面は、前記主桁の内周面の外側に当接するコンクリート中詰鋼製セグメントを製造する際の、継手板用ボルトの締結作業用空間を形成するための治具において、前記仕切板に当てがわれるせき板と、前記せき板を進退させて、前記一方の継手板と前記せき板との間隔を調整する間隔調整機構とを備え、前記せき板の上部は、前記余盛枠の高さと同一高さを有すると共に、前記余盛枠間の間隔と同じ長さを有し、前記せき板の下部は、前記主桁間の間隔と同じ長さを有し、前記せき板の上部の両端下面は、前記主桁の内周面の内側に当接することに特徴を有するものである。   The invention according to claim 1 is composed of a steel frame and concrete cast in the steel frame, and the steel frame is welded between a pair of main girders and both ends of the main girders. A pair of joint plates, a skin plate welded to the outer peripheral surface of the main girder, a side frame removably attached to the outer side of the main girder, and a weld between the main girder on one of the joint plates And a partition frame is attached to the inner surface of the side frame along the side frame, and the lower surface of the surplus frame is in contact with the outside of the inner peripheral surface of the main girder In the jig for forming the space for fastening the joint plate bolts when producing the middle-packed steel segment, the slat plate applied to the partition plate and the slat plate are advanced and retracted, A gap adjusting mechanism for adjusting a gap between the joint plate and the baffle plate, Has the same height as the height of the extra-frames and has the same length as the interval between the extra-frames, and the lower part of the bottom plate has the same length as the interval between the main girders. The lower surfaces of both ends of the upper portion of the dam plate are in contact with the inside of the inner peripheral surface of the main girder.

請求項2に記載の発明は、請求項1に記載の発明において、前記間隔調整機構は、前記せき板の前記一方の継手板側の面に固定されたねじ棒と、前記ねじ棒と螺合し、前記一方の継手板の内面に当接するナットとからなり、前記ナットを回すことによって、前記せき板を前記仕切板に密着させることに特徴を有するものである。   According to a second aspect of the present invention, in the first aspect of the invention, the distance adjusting mechanism includes a screw rod fixed to a surface of the first coupling plate side of the dam plate, and a screw engagement with the screw rod. And a nut abutting against the inner surface of the one joint plate, wherein the base plate is brought into close contact with the partition plate by turning the nut.

請求項3に記載の発明は、請求項1に記載の発明において、前記間隔調整機構は、前記せき板の前記一方の継手板側の面に固定された外管と、前記外管内にコイルばねを介して挿入された、前記一方の継手板の内面に当接する内管とからなり、前記コイルばねの弾性力によって、前記せき板を前記仕切板に密着させることに特徴を有するものである。   According to a third aspect of the present invention, in the first aspect of the present invention, the distance adjusting mechanism includes an outer tube fixed to the surface of the one coupling plate side of the dam plate, and a coil spring in the outer tube. And the inner pipe abutting against the inner surface of the one joint plate, and characterized in that the weir plate is brought into close contact with the partition plate by the elastic force of the coil spring.

この発明によれば、主桁間に溶接された仕切板に当てがわれるせき板を進退可能に構成することによって、セグメント毎に仕切板の取り付け位置が変わっても、これに容易に対処することができるコンクリート中詰鋼製セグメント製造用治具を提供することができる。   According to the present invention, it is possible to easily cope with the change of the attachment position of the partition plate for each segment by configuring the slat plate applied to the partition plate welded between the main girders so as to be able to advance and retreat. It is possible to provide a jig for manufacturing a concrete-filled steel segment that can be used.

この発明の治具が設置された鋼製枠を示す概略斜視図である。It is a schematic perspective view which shows the steel frame in which the jig | tool of this invention was installed. この発明の治具が設置された鋼製枠を示す平面図である。It is a top view which shows the steel frame in which the jig | tool of this invention was installed. この発明の治具が設置された鋼製枠を示す正面図である。It is a front view which shows the steel frame in which the jig | tool of this invention was installed. コンクリート中詰鋼製セグメントを示す概略斜視図である。It is a schematic perspective view which shows the segment made from concrete filling steel. 従来法によりコンクリート中詰鋼製セグメントを製造する場合の鋼製枠を示す概略斜視図である。It is a schematic perspective view which shows the steel frame in the case of manufacturing a concrete filling steel segment by the conventional method. 側枠を示す背面図である。It is a rear view which shows a side frame. 中子位置における主桁への側枠の取り付け構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the attachment structure of the side frame to the main girder in a core position. 発泡スチロール製ブロックを示す斜視図である。It is a perspective view which shows the block made from a polystyrene foam. 他の間隔調整機構を示す概略斜視図である。It is a schematic perspective view which shows another space | interval adjustment mechanism.

この発明のコンクリート中詰鋼製セグメント用治具の一実施態様を、図面を参照しながら説明する。   An embodiment of a jig for a concrete-filled steel segment according to the present invention will be described with reference to the drawings.

図1は、この発明の治具が設置された鋼製枠を示す概略斜視図、図2は、この発明の治具が設置された鋼製枠を示す平面図、図3は、この発明の治具が設置された鋼製枠を示す正面図である。   FIG. 1 is a schematic perspective view showing a steel frame in which the jig of the present invention is installed, FIG. 2 is a plan view showing the steel frame in which the jig of the present invention is installed, and FIG. It is a front view which shows the steel frame in which the jig | tool was installed.

図1から図3に示すように、この発明の治具(説明の便宜上、以下「治具A」と称す。)は、コンクリート中詰鋼製セグメントを製造する際の、継手板用ボルトの締結作業用空間(S)を形成するためのものである。   As shown in FIGS. 1 to 3, the jig of the present invention (hereinafter referred to as “jig A” for convenience of explanation) is used to fasten joint plate bolts when producing concrete-filled steel segments. This is for forming a working space (S).

コンクリート中詰鋼製セグメントは、上述した通りであるので、簡単に説明する。   Since the concrete-filled steel segment is as described above, it will be briefly described.

コンクリート中詰鋼製セグメントは、鋼製枠1と鋼製枠1内に打設されたコンクリート(図4参照)とから構成されている。鋼製枠1は、一対の主桁4と、主桁4の両端部間に溶接された一対の継手板5と、主桁4の外周面に溶接されたスキンプレート6と、主桁4の外側に着脱可能に取り付けられる側枠13と、一方の継手板5a側の主桁4間に溶接された仕切板17とを備えている。側枠13の内面には、側枠13に沿って余盛枠16が取り付けられ、余盛枠16の下面は、主桁4の内周面の外側に当接するものから構成されている。   The concrete-filled steel segment is composed of a steel frame 1 and concrete (see FIG. 4) placed in the steel frame 1. The steel frame 1 includes a pair of main girders 4, a pair of joint plates 5 welded between both ends of the main girders 4, a skin plate 6 welded to the outer peripheral surface of the main girders 4, and the main girders 4. A side frame 13 detachably attached to the outside and a partition plate 17 welded between the main beams 4 on the side of one joint plate 5a are provided. The extra frame 16 is attached to the inner surface of the side frame 13 along the side frame 13, and the lower surface of the extra frame 16 is configured to be in contact with the outer side of the inner peripheral surface of the main girder 4.

この他、図5におけると同一番号は、同一物を示す。   In addition, the same numbers as those in FIG.

この発明の治具Aは、仕切板17に当てがわれるせき板19と、せき板19を進退させて、一方の継手板5aとせき板19との間隔を調整する間隔調整機構20とからなっている。   The jig A of the present invention includes a slat plate 19 applied to the partition plate 17 and a distance adjusting mechanism 20 that moves the slat plate 19 forward and backward to adjust the distance between one joint plate 5 a and the slat plate 19. ing.

せき板19の上部は、余盛枠16の高さと同一高さを有すると共に、余盛枠16,16間の間隔と同じ長さを有する。せき板19の下部は、主桁4,4間の間隔と同じ長さを有し、せき板19の上部の両端下面は、主桁4の内周面の内側(b)に当接する。せき板19の上部の両端下面を、図1において、(c)で示す。   The upper portion of the weir plate 19 has the same height as the extra frame 16 and the same length as the interval between the extra frames 16 and 16. The lower portion of the weir plate 19 has the same length as the distance between the main girders 4 and 4, and the lower surfaces of both ends of the upper portion of the weir plate 19 abut on the inner side (b) of the inner peripheral surface of the main girder 4. The lower surfaces at both ends of the upper portion of the weir plate 19 are shown in FIG.

間隔調整機構20は、せき板19の一方の継手板5a側の面に固定されたねじ棒21と、ねじ棒21と螺合し、一方の継手板5aの内面に当接するナット22とからなっている。ナット22を回転させることによって、ねじ棒21が進退し、これによって、せき板19も進退する。この結果、セグメント毎に仕切板17の取り付け位置が変わっても、常に、一台の間隔調整機構20によって、継手板用ボルトの締結作業用空間(S)を形成することが可能となる。   The interval adjusting mechanism 20 includes a screw rod 21 fixed to the surface of the joint plate 19 on the one joint plate 5a side, and a nut 22 that is screwed with the screw rod 21 and contacts the inner surface of the one joint plate 5a. ing. By rotating the nut 22, the screw rod 21 advances and retreats, so that the dam plate 19 also advances and retreats. As a result, even if the attachment position of the partition plate 17 changes for each segment, the space for fastening operation (S) of the joint plate bolt can always be formed by the single interval adjusting mechanism 20.

この発明の治具Aを使用してコンクリート中詰鋼製セグメントを製造するには、図1に示すように、この発明の治具Aを一方の継手板5aと仕切板17との間に設置し、ナット22を手等で回転させて、せき板19を仕切板17に密着させる。   In order to produce a concrete-filled steel segment using the jig A of the present invention, the jig A of the present invention is installed between one joint plate 5a and the partition plate 17, as shown in FIG. Then, the nut 22 is rotated by hand or the like, and the weir plate 19 is brought into close contact with the partition plate 17.

このようにして、この発明の治具Aを設置したら、せき板19と端部枠15との間の鋼製枠1内にコンクリートを打設する。そして、コンクリート硬化後、この発明の治具A、側枠13および端部枠15を取り外す。   Thus, when the jig A of the present invention is installed, concrete is placed in the steel frame 1 between the dam plate 19 and the end frame 15. And after concrete hardening, the jig | tool A of this invention, the side frame 13, and the edge part frame 15 are removed.

一方の継手板5aと仕切板17との間に形成された空間(S)内には、シールドトンネル施工時において、セグメントリングを組立てた後(ボルト締め後)、コンクリートを打設する。   In the space (S) formed between one joint plate 5a and the partition plate 17, after assembling the segment ring (after bolting) at the time of shield tunnel construction, concrete is placed.

以上、説明したように、この発明によれば、従来の発泡スチロール製ブロック18のように欠損の恐れがないので、反復使用が可能である。   As described above, according to the present invention, unlike the conventional polystyrene foam block 18, there is no fear of a defect, so that it can be used repeatedly.

また、この発明によれば、せき板19を自在に移動することができるので、セグメント毎に仕切板17の取り付け位置が変わっても、これに容易に対処することができる。
その結果、コンクリート中詰鋼製セグメントの製造能率が向上し、その品質も安定する。
Moreover, according to this invention, since the dam 19 can be moved freely, even if the attachment position of the partition plate 17 changes for every segment, this can be coped with easily.
As a result, the production efficiency of the concrete-filled steel segment is improved and the quality is stabilized.

なお、間隔調整機構20は、ねじ棒とナットによる構造以外のものでも良い。例えば、図9に示すように、せき板19に固定した外管23と、外管23内にコイルばね24を介して挿入された内管25とからなり、コイルばね24の弾性力によって、せき板19を仕切板17に密着させる構造であっても良い。   In addition, the space | interval adjustment mechanism 20 may be other than the structure by a screw rod and a nut. For example, as shown in FIG. 9, the outer tube 23 is fixed to the dam plate 19, and the inner tube 25 is inserted into the outer tube 23 via a coil spring 24. A structure in which the plate 19 is in close contact with the partition plate 17 may be employed.

内管25は、必ずしも中空の管体でなくても良く、いわゆる中実の柱体でも機能上使用できる。また、その材質は鋼製でなくても良く、アルミニウム等の金属製、若しくは硬質プラスチック製等でも良い。   The inner tube 25 does not necessarily have to be a hollow tube body, and a so-called solid column body can be used functionally. Further, the material does not have to be made of steel, but may be made of metal such as aluminum or hard plastic.

さらに、コイルばね24の弾性力を増すため、図示をしないが、間隔調整機構20を複数並列にせき板19に設けても良い。   Further, in order to increase the elastic force of the coil spring 24, although not shown, a plurality of interval adjusting mechanisms 20 may be provided on the dam plate 19 in parallel.

A:この発明の治具
1:鋼製枠
2:コンクリート
3:補強材(縦リブ)
4:主桁
5:継手板
5a:一方の継手板
6:スキンプレート
7:ボルト孔
8:ボルト孔
9:凹陥部(ボルトボックス)
10:凹陥部
11:余盛部
12:中子
13:側枠
14:ボルト
15:端部枠
16:余盛枠
17:仕切板
18:ブロック
19:せき板
20:間隔調整機構
21:ねじ棒
22:ナット
23:外管
24:コイルばね
25:内管
A: Jig of the present invention 1: Steel frame 2: Concrete 3: Reinforcement material (vertical rib)
4: Main girder 5: Joint plate 5a: One joint plate 6: Skin plate 7: Bolt hole 8: Bolt hole 9: Recessed part (bolt box)
10: recessed part 11: extra part 12: core 13: side frame 14: bolt 15: end part frame 16: extra part frame 17: partition plate 18: block 19: baffle plate 20: interval adjusting mechanism 21: screw rod 22: Nut 23: Outer tube 24: Coil spring 25: Inner tube

Claims (3)

鋼製枠と前記鋼製枠内に打設されたコンクリートとから構成され、前記鋼製枠は、一対の主桁と、前記主桁の両端部間に溶接された一対の継手板と、前記主桁の外周面に溶接されたスキンプレートと、前記主桁の外側に着脱可能に取り付けられる側枠と、一方の前記継手板側の前記主桁間に溶接された仕切板とを備え、前記側枠の内面には、前記側枠に沿って余盛枠が取り付けられ、前記余盛枠の下面は、前記主桁の内周面の外側に当接するコンクリート中詰鋼製セグメントを製造する際の、継手板用ボルトの締結作業用空間を形成するための治具において、
前記仕切板に当てがわれるせき板と、前記せき板を進退させて、前記一方の継手板と前記せき板との間隔を調整する間隔調整機構とを備え、前記せき板の上部は、前記余盛枠の高さと同一高さを有すると共に、前記余盛枠間の間隔と同じ長さを有し、前記せき板の下部は、前記主桁間の間隔と同じ長さを有し、前記せき板の上部の両端下面は、前記主桁の内周面の内側に当接することを特徴とするコンクリート中詰鋼製セグメント製造用治具。
It is composed of a steel frame and concrete cast in the steel frame, and the steel frame includes a pair of main girders, a pair of joint plates welded between both ends of the main girders, and A skin plate welded to the outer peripheral surface of the main girder, a side frame detachably attached to the outside of the main girder, and a partition plate welded between the main girder on one of the joint plates, A surplus frame is attached to the inner surface of the side frame along the side frame, and the lower surface of the surplus frame is used when manufacturing a concrete-filled steel segment that abuts the outside of the inner peripheral surface of the main girder. In a jig for forming a space for fastening work of a bolt for a joint plate,
A partition plate applied to the partition plate, and a spacing adjusting mechanism that adjusts a spacing between the one joint plate and the projection plate by moving the partition plate forward and backward. The height is the same as the height of the filling frame, and has the same length as the interval between the extra-frames, and the lower portion of the slat has the same length as the interval between the main girders, A jig for producing a concrete-filled steel segment, characterized in that the lower surfaces of both ends of the upper part of the plate are in contact with the inside of the inner peripheral surface of the main girder.
前記間隔調整機構は、前記せき板の前記一方の継手板側の面に固定されたねじ棒と、前記ねじ棒と螺合し、前記一方の継手板の内面に当接するナットとからなり、前記ナットを回すことによって、前記せき板を前記仕切板に密着させることを特徴とする、請求項1に記載のコンクリート中詰鋼製セグメント製造用治具。   The spacing adjustment mechanism includes a screw rod fixed to the surface of the one coupling plate side of the dam plate, and a nut that is screwed with the screw rod and contacts the inner surface of the one coupling plate, 2. The jig for producing a concrete-filled steel segment according to claim 1, wherein the partition plate is brought into close contact with the partition plate by turning a nut. 3. 前記間隔調整機構は、前記せき板の前記一方の継手板側の面に固定された外管と、前記外管内にコイルばねを介して挿入された、前記一方の継手板の内面に当接する内管とからなり、前記コイルばねの弾性力によって、前記せき板を前記仕切板に密着させることを特徴とする、請求項1に記載のコンクリート中詰鋼製セグメント製造用治具。   The spacing adjusting mechanism includes an outer tube fixed to the surface of the one coupling plate side of the dam plate, and an inner surface that contacts the inner surface of the one coupling plate inserted into the outer tube via a coil spring. 2. The jig for manufacturing a concrete-filled steel segment according to claim 1, wherein the jig is made of a tube, and the partition plate is brought into close contact with the partition plate by an elastic force of the coil spring.
JP2014044754A 2014-03-07 2014-03-07 Jig for production of concrete filled steel segment Active JP6267547B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014044754A JP6267547B2 (en) 2014-03-07 2014-03-07 Jig for production of concrete filled steel segment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014044754A JP6267547B2 (en) 2014-03-07 2014-03-07 Jig for production of concrete filled steel segment

Publications (2)

Publication Number Publication Date
JP2015168986A JP2015168986A (en) 2015-09-28
JP6267547B2 true JP6267547B2 (en) 2018-01-24

Family

ID=54201982

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014044754A Active JP6267547B2 (en) 2014-03-07 2014-03-07 Jig for production of concrete filled steel segment

Country Status (1)

Country Link
JP (1) JP6267547B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6997353B1 (en) 2021-08-26 2022-01-17 Khファシリテック株式会社 Manufacturing method of steel segment

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1381292A (en) * 1971-01-11 1975-01-22 Cooper E F Tunnelling
JP2753687B2 (en) * 1995-01-27 1998-05-20 ジオスター株式会社 End form correction device for segment formwork
JP3383253B2 (en) * 2000-01-17 2003-03-04 テクノス株式会社 Forming device for synthetic segment and method for manufacturing synthetic segment
JP3406280B2 (en) * 2000-07-03 2003-05-12 テクノス株式会社 Manufacturing method of synthetic segment

Also Published As

Publication number Publication date
JP2015168986A (en) 2015-09-28

Similar Documents

Publication Publication Date Title
JP2007284989A (en) Tunnel interior building method
JP6379045B2 (en) Structure of beam-bottom formwork support bracket and PCa beam joint and its construction method
CN105780972A (en) Building quake-proof outer wall hanging plate
JP6267547B2 (en) Jig for production of concrete filled steel segment
JP2017031584A (en) Steel bar support and installation method of steel bar for invert concrete
JP6715092B2 (en) Construction method of underground structure
JP2009083407A (en) Production process of composite segment
JP2006159581A (en) Combined segment and its manufacturing method
JP6348540B2 (en) Deck receiving jig
JP6605943B2 (en) Tunnel internal structure and construction method thereof
JP2013204298A (en) Method for reinforcing inner lining of tunnel
JP5832561B2 (en) Steel structure and seismic retrofitting method
JP6902747B2 (en) Reinforced concrete column-beam joint structure and its construction method
KR101779023B1 (en) Method for assembling block in curved part of a ship
CN106089249A (en) A kind of Quick-detachable adjustable lining cutting plug punching block and installation and application
JP6402001B2 (en) Invert block and invert block fixing method
JP2002309706A (en) Stud of composite girder or the like
JP2007023715A (en) Installation method of precast concrete member
JP2017008693A (en) Structure repair method
JP6735121B2 (en) Connection structure of insert and PCT plate
JP2016142088A (en) Tunnel lining concrete mold support structure
JP6049486B2 (en) Support structure for connecting strut and beam
JP2005297497A (en) Manufacturing method for concrete product
JP6874051B2 (en) Groove construction method
JP6266472B2 (en) Drilling method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170113

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20171124

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20171128

R150 Certificate of patent or registration of utility model

Ref document number: 6267547

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250