JP4057338B2 - Method and apparatus for renewing a ballast roadbed - Google Patents
Method and apparatus for renewing a ballast roadbed Download PDFInfo
- Publication number
- JP4057338B2 JP4057338B2 JP2002125864A JP2002125864A JP4057338B2 JP 4057338 B2 JP4057338 B2 JP 4057338B2 JP 2002125864 A JP2002125864 A JP 2002125864A JP 2002125864 A JP2002125864 A JP 2002125864A JP 4057338 B2 JP4057338 B2 JP 4057338B2
- Authority
- JP
- Japan
- Prior art keywords
- bulk material
- container
- ballast
- crane
- excavator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B27/00—Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
- E01B27/06—Renewing or cleaning the ballast in situ, with or without concurrent work on the track
- E01B27/10—Renewing or cleaning the ballast in situ, with or without concurrent work on the track without taking-up track
- E01B27/105—Renewing or cleaning the ballast in situ, with or without concurrent work on the track without taking-up track the track having been lifted
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、軌道のバラスト道床を修復するための方法であって、汚れたバルク材料を掘削チェーンで掘り返して運び去り、更新間隔を形成し、これと並行してバラスト道床を修復するための新たなバルク材料を軌道上およびバラスト道床を修復するための装置に排出する。
【0002】
【従来の技術】
米国特許第4,465,414号から、バラストを清掃中に蓄積する廃物をコンテナ内に保管し、ガントリークレーンを用いて廃物装填車上に搬送する方法が知られている。
【0003】
【発明が解決しようとする課題】
本発明の目的は、効率的なバラスト道床修復を行うことができる特殊なタイプの方法を提供することである。
【0004】
【課題を解決するための手段・作用・効果】
本発明により、この目的は、主請求項の特徴部分に記載した特徴により、冒頭に記載した類の方法を用いて達成される。
【0005】
この方法は、構造費用が比較的少なくて済み、材料を非常に効率的に交換することができ、コンテナを搬送するために装備されたガントリークレーンを最初に作動させる時に、新たなバルク材料、つまりバラストまたは砂利が更新間隔に運び込まれ、その後、ガントリークレーンは帰路で、処分すべきバルク材料を運び去ることができる。さらに、最小限に適応させるだけで、多くの既存の装填ワゴンを有利な方法で使用することが可能である。
【0006】
本発明は、また、請求項3の特徴に係るバラスト道床を修復するための装置にさらに関する。この種の解決方法により、構造費用を最小限に削減することができ、その結果、かなりのバルク材料保管容量が必要であるにも関わらず、特別に設計された保管ワゴンを使用する必要はなくなる。充填開口部により、コンベヤベルトに関する全体の費用を著しく減少させることができる。
【0007】
本発明のその他の利点および特徴は、従属請求項および図面から明白になる。
【0008】
本発明について、図示の実施態様に関して以下にさらに詳細に説明する。
【0009】
【発明の実施の形態】
軌道3のバラスト道床2を修復するための図1および図2に示す装置1は、掘削チェーン4を有する掘削車5と、装填プラットフォーム7を備える任意の数の装填ワゴン6とから成る。全体の機械ユニットは、軌道上台車8により軌道3上で移動可能であり、動力駆動装置9を装備されている。
【0010】
掘削車5は、軌道上台車8上の両端で移動可能な機械フレーム10と、軌道上昇装置11とを備える。バラストがない更新間隔13は、装置1の動作方向(矢印12)に関して掘削チェーン4の真後ろに位置し、掘削チェーンは、エンドレスチェーンとして軌道3の周囲に案内される。掘削チェーン4は、回転可能であり、駆動装置40、41により垂直方向および横断方向に調節可能である。装置の前端には、制御装置15を備える運転台または操作台14が位置する。
【0011】
掘削車5の後端には、充填コンテナ17のために充填ステーション16が設けられている。充填ステーション16は、装置の長手方向に延在し、クレーンレール18間に配置され、駆動装置42を備える下部コンベヤベルト19と、コンベヤ装置20とから構成される。コンベヤ装置20は、掘削チェーン4の排出端部21の下側に配置された受容端部22と、充填ステーション16上に配置された排出端部23とを有する。
【0012】
動力駆動装置25を有するガントリークレーン24は、コンテナ17を搬送するために設けられ、フランジ付きローラ26によりクレーンレール18上で移動可能である。コンテナ17から中身を放出するため、ガントリークレーン24は、装置の長手方向に垂直に延在する軸28周囲で水平に回転可能な傾斜機構27を備える。
【0013】
クレーンのレール18(図4参照)により形成されるレール平面29と掘削チェーン4の上端30との間に垂直に延在する距離aは、入口フレーム高さbより短くなるように設計されている。入口フレーム高さbは、レール平面29、および2個の入り口支持部31を互いに接続する横断ビーム32により境界を画定される。運転台の高さcも、入口フレーム高さbより短い。
【0014】
特に図3で分かるように、機械フレーム10は、バラスト34が通過するための充填開口部33を備え、充填ホッパー35と、フレーム開口部36と、機械フレーム10の下側に位置するコンベヤベルト37とから成る。コンベヤベルト37は、フレーム開口部36の下側に配置された受容端部38と、掘削チェーン4と軌道上昇装置11との間に位置する排出端部39とを有する。
【0015】
装置1および装填ワゴン6から成る機械ユニットの動作モードについて、以下にさらに詳細に説明する。
【0016】
掘削チェーン4が掘り返した汚れたバルク材料すなわちバラスト34は、コンベヤ装置20により、下部コンベヤベルト19上に配置されたコンテナ17内に充填され、新たなバラスト34が充填されたコンテナ17は、ガントリークレーン24により充填開口部33に搬送され、コンベヤベルト37上に排出される。バラスト34は、コンベヤベルト37から最終的に更新間隔13に送られる。次に、ガントリークレーン24は充填ステーション16まで駆動され、空になったコンテナ17が下部コンベヤベルト19(破線参照)上に配置される。その後、その間に汚れたバラスト34を充填されたコンテナ17がガントリークレーン24により持ち上げられて、装填ワゴン6の自由空間上に配置される。駆動装置42が作動することにより、空のコンテナ17は下部コンベヤベルト19により受容端部23の下側に移動する。その後の順序では、再び新たな作動サイクルが開始し、新たなバラスト34を充填されたコンテナ17が充填開口部33に搬送され、これと並行して空のコンテナに充填される。
【0017】
別法による実施態様では、たとえば、新たなバラストではなく砂利を搬送して地層保護層を形成することができる。同様に、装填ワゴン6は、特殊な機械設備改善作業を行わずに、装置1の右側端部に都合の良い方法で結合することができる。また、砂利を左側から充填開口部33に搬送し、これと並行して新たなバラストを右側から更新間隔13に供給しても良い。
【0018】
図5に示す装置1の場合、第2コンベヤベルト37を備えた第2つまり前方充填ホッパー43は、コンテナ17内に保管された砂利を空にするために設けられる。コンテナ17は、装置の前端に結合された装填ワゴン6上に配置される。第2ガントリークレーン24は、砂利を充填されたコンテナ17を搬送するために設けられる。装置の後端に結合された装填ワゴン6は、新たなバラストを充填されたコンテナ17を搬送するために設けられる。これらコンテナ17は、砂利が放出されるのと並行して、後部充填ホッパー35を介して更新間隔13内に新たなバルク材料を放出する。この装置1を使用すると、バラスト道床の更新と並行して地層保護層44を形成することができ、地層保護層44は、整地/固め装置45により整地され、固められる。
【図面の簡単な説明】
【図1】 バラスト道床修復装置の側面図を示す。
【図2】 バラスト道床修復装置の側面図を示す。
【図3】 装置の略上面図を示す。
【図4】 装置の略断面図を示す。
【図5】 装置のその他の変形の略側面図を示す。
【符号の説明】
1 装置
2 バラスト道床
3 軌道
4 掘削チェーン
5 掘削車
6 装填ワゴン
7 装填プラットフォーム
8 軌道上台車
10 機械フレーム
11 軌道上昇装置
13 更新間隔
15 制御装置
14 運転台
16 充填ステーション
17 コンテナ
18 クレーンレール
19 コンベヤベルト
20 コンベヤ装置
21 排出端部
22 受容端部
23 排出端部
24 ガントリークレーン
25 動力駆動装置
26 フランジ付きローラ
27 傾斜機構
28 軸
29 レール平面
30 上端
31 入り口支持部
32 横断ビーム
34 バラスト
35 充填ホッパー
36 フレーム開口部
37 コンベヤベルト
38 受容端部
39 排出端部
40 駆動装置
41 駆動装置[0001]
BACKGROUND OF THE INVENTION
The present invention is a method for repairing a ballast roadbed in an orbit, which is a new method for repairing a ballast roadbed in parallel with this by excavating and carrying away dirty bulk material with a drilling chain. The bulk material is discharged into an orbital and ballast track repair device.
[0002]
[Prior art]
From U.S. Pat. No. 4,465,414, a method is known in which waste that accumulates during ballast cleaning is stored in a container and transported onto a waste loaded vehicle using a gantry crane.
[0003]
[Problems to be solved by the invention]
It is an object of the present invention to provide a special type of method that can perform an efficient ballast track restoration.
[0004]
[Means / Actions / Effects to Solve Problems]
According to the invention, this object is achieved with the features described in the characterizing part of the main claim using a method of the kind described at the outset.
[0005]
This method requires relatively low construction costs, allows material to be exchanged very efficiently, and when the gantry crane equipped to transport the container is first operated, a new bulk material, i.e. Ballast or gravel is brought into the renewal interval, after which the gantry crane can carry away bulk material to be disposed of on the return path. Furthermore, many existing loading wagons can be used in an advantageous manner with minimal adaptation.
[0006]
The invention also relates to a device for repairing a ballast bed according to the features of
[0007]
Other advantages and features of the invention will become apparent from the dependent claims and the drawings.
[0008]
The invention is described in more detail below with respect to the illustrated embodiments.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
The
[0010]
The
[0011]
A
[0012]
A
[0013]
The distance a extending vertically between the
[0014]
As can be seen in particular in FIG. 3, the
[0015]
The mode of operation of the machine unit comprising the
[0016]
The dirty bulk material or
[0017]
In an alternative embodiment, for example, gravel can be conveyed instead of new ballast to form a geological protective layer. Similarly, the loading wagon 6 can be coupled in a convenient manner to the right end of the
[0018]
In the case of the
[Brief description of the drawings]
FIG. 1 shows a side view of a ballast roadbed repair device.
FIG. 2 shows a side view of the ballast roadbed repair device.
FIG. 3 shows a schematic top view of the device.
FIG. 4 shows a schematic cross-sectional view of the device.
FIG. 5 shows a schematic side view of another variant of the device.
[Explanation of symbols]
DESCRIPTION OF
Claims (7)
装填ワゴン(6)上に設けられ新たなバルク材料(34)が充填されたコンテナ(17)が更新間隔(13)に搬送され、新たなバルク材料が放出されて前記バラスト道床(2)を修復し、その後、空になった前記コンテナ(17)は、前記掘削チェーン(4)が掘り返した汚れたバルク材料(34)で充填され、装填ワゴン(6)上に配置されて新たな作業サイクルを開始し、新たなバルク材料(34)が充填されたコンテナが再び前記更新間隔(13)に搬送されることを特徴とする方法。Dirt bulk material (34) is dug back and carried away by the drilling chain (4), thereby forming an update interval (13), in parallel, a new bulk material (34) for repairing the ballast roadbed A method of repairing a ballast bed (2) of an orbit (3) such that
The container (17) provided on the loading wagon (6) and filled with the new bulk material (34) is transported at the renewal interval (13), and the new bulk material is released to restore the ballast roadbed (2). The emptied container (17) is then filled with dirty bulk material (34) dug by the drilling chain (4) and placed on the loading wagon (6) for a new work cycle. A method which starts and a container filled with new bulk material (34) is transported again in the update interval (13).
バラストを掘り返すための掘削チェーン(4)を有する掘削車(5)と、コンテナ(17)が装填された複数の装填ワゴン(6)と、クレーンレール(18)上で前記装填ワゴン(6)に沿って移動可能でありコンテナ(17)を搬送するためのガントリークレーン(24)とを有し、
前記掘削車(5)は、前記ガントリークレーン(24)を移動させるためのクレーンレール(18)と、コンテナ(17)から前記軌道(3)上に放出されることができるバルク材料(34)が通過するための充填開口部(33)とを備えることを特徴とする装置。 An apparatus (1) for repairing a ballast bed (2) of a track (3),
An excavator (5) having an excavation chain (4) for digging ballast, a plurality of loading wagons (6) loaded with containers (17), and the loading wagon (6) on a crane rail (18). A gantry crane (24) movable along the container (17),
The excavator (5) has a crane rail (18) for moving the gantry crane (24) and a bulk material (34) that can be discharged from a container (17) onto the track (3). and wherein the Rukoto with fill opening for passing the (33).
該充填ステーション(16)は、前記装置の長手方向に延在すると共に前記クレーンレール(18)間に配置された下部コンベヤベルト(19)と、コンベヤ装置(20)の前記コンベヤベルト(19)上に配置された排出端部(23)とを有し、
前記コンベヤ装置(20)の受容端部(22)が前記掘削チェーン(4)の排出端部(21)の下側に配置されていることを特徴とする、請求項2〜4のいずれかに記載の装置。Said excavator (5) comprises a filling station (16) for filling containers;
The filling station (16) extends in the longitudinal direction of the device and is arranged between the crane rail (18) and on the conveyor belt (19) of the conveyor device (20). And a discharge end (23) disposed in the
Wherein the receiving end of the conveyor device (20) (22) is disposed under the discharge end of the excavation chain (4) (21), in any one of claims 2-4 The device described.
前記横断ビームが、前記装置の横方向に互いに離間配置された入口支持部(31)を接続するために設けられ、フランジ付きローラ(26)を有することを特徴とする、請求項2〜5のいずれかに記載の装置。 On the one hand, the distance (a) extending vertically between the rail plane (29) formed by the crane rail (18) and on the other hand the upper end (30) of the excavation chain (4) is the rail plane. Configured to be shorter than the vertical entrance frame height (b) between (29) and the transverse beam (32) of the gantry crane (24),
It said transverse beam is provided for connecting the inlet support portion which are spaced from each other in the lateral direction of the device (31), characterized Rukoto that having a flanged roller (26), claims 2 to The apparatus according to any one of 5.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AT343/2001 | 2001-05-03 | ||
AT0034301U AT4763U3 (en) | 2001-05-03 | 2001-05-03 | METHOD FOR RENEWING A GRAVEL BED AND MACHINE |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002363902A JP2002363902A (en) | 2002-12-18 |
JP4057338B2 true JP4057338B2 (en) | 2008-03-05 |
Family
ID=3488066
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002125864A Expired - Fee Related JP4057338B2 (en) | 2001-05-03 | 2002-04-26 | Method and apparatus for renewing a ballast roadbed |
Country Status (6)
Country | Link |
---|---|
EP (1) | EP1254987B1 (en) |
JP (1) | JP4057338B2 (en) |
CN (1) | CN1206407C (en) |
AT (2) | AT4763U3 (en) |
DE (1) | DE50203174D1 (en) |
ES (1) | ES2242842T3 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT6487U3 (en) * | 2003-07-15 | 2004-10-25 | Plasser Bahnbaumasch Franz | ROOM CHAIN FOR THE TRANSPORT OF SCOTS OF A BEDDING |
AT507789B1 (en) * | 2009-06-17 | 2010-08-15 | Plasser Bahnbaumasch Franz | METHOD FOR COMMISSIONING A MACHINE |
DE102012220877A1 (en) * | 2012-11-15 | 2014-05-15 | K & K Maschinenentwicklungs Gmbh & Co. Kg | System for the track-bound transport of objects |
AT14465U1 (en) * | 2014-07-14 | 2015-11-15 | Plasser & Theurer Export Von Bahnbaumaschinen Gmbh | Cleaning vehicle for cleaning ballast of a track |
DE202021106741U1 (en) * | 2021-12-10 | 2022-05-16 | Hans Hermann Bergmann | Rail-bound platform truck with conveyor belt and loading area |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT336670B (en) * | 1973-01-12 | 1977-05-25 | Plasser Bahnbaumasch Franz | MOBILE SILO CARRIAGE, RAILWAY CARRIAGE AND DGL. WITH A LOADING OR MATERIAL SUPPLY DEVICE |
AT351584B (en) * | 1976-05-31 | 1979-08-10 | Plasser Bahnbaumasch Franz | ZUGSVERBAND FOR ACCEPTING, DISPOSING AND TRANSPORTING BULK CARGO |
AT379176B (en) * | 1981-12-22 | 1985-11-25 | Plasser Bahnbaumasch Franz | DRIVABLE PLANT AND METHOD FOR CONTINUOUSLY PROGRESSIVE RENOVATION OF THE RAILWAYS |
AT373833B (en) * | 1982-01-15 | 1984-02-27 | Plasser Bahnbaumasch Franz | TRACKABLE PLANT FOR THE TRANSPORT OF SCHUETTGUT |
NL8800467A (en) * | 1988-02-24 | 1989-09-18 | Railbouw Bv | BALLAST DRAIN SYSTEM. |
-
2001
- 2001-05-03 AT AT0034301U patent/AT4763U3/en not_active IP Right Cessation
-
2002
- 2002-04-03 ES ES02450074T patent/ES2242842T3/en not_active Expired - Lifetime
- 2002-04-03 AT AT02450074T patent/ATE296379T1/en active
- 2002-04-03 DE DE50203174T patent/DE50203174D1/en not_active Expired - Lifetime
- 2002-04-03 EP EP02450074A patent/EP1254987B1/en not_active Expired - Lifetime
- 2002-04-26 JP JP2002125864A patent/JP4057338B2/en not_active Expired - Fee Related
- 2002-04-29 CN CNB021188203A patent/CN1206407C/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
EP1254987A3 (en) | 2003-10-08 |
EP1254987A2 (en) | 2002-11-06 |
CN1384244A (en) | 2002-12-11 |
AT4763U2 (en) | 2001-11-26 |
EP1254987B1 (en) | 2005-05-25 |
DE50203174D1 (en) | 2005-06-30 |
AT4763U3 (en) | 2002-03-25 |
ES2242842T3 (en) | 2005-11-16 |
CN1206407C (en) | 2005-06-15 |
ATE296379T1 (en) | 2005-06-15 |
JP2002363902A (en) | 2002-12-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2825336B2 (en) | Work machines for picking up and spreading ballast for roadbeds | |
JPS58110701A (en) | Moving machine for repairing road bed of railroad | |
CA2102007C (en) | A loading wagon for the transport of bulk material | |
US3827585A (en) | Method and apparatus for loading bagged mail from a loading dock into a highway vehicle | |
CA2093089C (en) | Installation for continuously rehabilitating a ballast bed of a track | |
HU183516B (en) | Movable apparatus and method for rehabilitating track founding | |
NL1003464C2 (en) | Storage wagon for storing bulk goods. | |
JPH0756122B2 (en) | Self-propelled track changer | |
US4004524A (en) | Method of renewal of a railroad track and train therefor | |
RU2229550C2 (en) | Rail track reconstruction machine | |
US3779404A (en) | Apparatus for loading mail bags into a highway vehicle | |
US3167193A (en) | Loading car with conveyor | |
GB2261455A (en) | An arrangement for creating a railway track formation protection layer | |
JP3793263B2 (en) | Reducing method and equipment for ballast under floor of railroad | |
GB1559258A (en) | Travellin machine arrangements | |
JP3267787B2 (en) | Ballast updating machine | |
EP1836081B1 (en) | Tanks for railway trucks to transport crushed stones, gravel and other materials, particularly for railroad ballast restoring machines | |
JP4057338B2 (en) | Method and apparatus for renewing a ballast roadbed | |
ES2304669T3 (en) | PROCEDURE FOR TRACKING A VIA. | |
JP2853911B2 (en) | Railcar for gravel leveling | |
JP5222282B2 (en) | Storage car | |
PL201968B1 (en) | Railway track renovating machine | |
US4357129A (en) | Self-propelled ballast dispensing machine | |
JPH09111703A (en) | Ballast bed execution machine for truck | |
SU1505446A3 (en) | Mobile gravel-cleaning machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050406 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070619 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070912 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071113 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071213 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4057338 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101221 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101221 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111221 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111221 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121221 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131221 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |