JP2001115468A - Execution method of concrete structure - Google Patents
Execution method of concrete structureInfo
- Publication number
- JP2001115468A JP2001115468A JP33478399A JP33478399A JP2001115468A JP 2001115468 A JP2001115468 A JP 2001115468A JP 33478399 A JP33478399 A JP 33478399A JP 33478399 A JP33478399 A JP 33478399A JP 2001115468 A JP2001115468 A JP 2001115468A
- Authority
- JP
- Japan
- Prior art keywords
- block
- concrete
- frame
- shaped steel
- blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Retaining Walls (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、擁壁やビルの躯体
などの各種コンクリート構造物の施工方法に関し、特に
略同一形状のブロックで構築した枠体の内側にコンクリ
ートを打設して、コンクリート構造物を施工する方法に
関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing various types of concrete structures such as retaining walls and building frames, and more particularly to a method of casting concrete inside a frame constructed of blocks having substantially the same shape. The present invention relates to a method for constructing a structure.
【0002】[0002]
【従来の技術】従来の、擁壁などのコンクリート構造物
の施工方法としては、 ブロックを積み上げて形成した枠体の内側にコンクリ
ートを流し込む石積み工法 例えば板製または鋼鉄製のの型枠を組み立てて形成し
た枠体の内側にコンクリートを流し込む型枠工法 などがある。2. Description of the Related Art Conventionally, as a construction method of a concrete structure such as a retaining wall, a masonry method in which concrete is poured into a frame formed by stacking blocks, for example, a form made of a plate or steel is assembled. There is a formwork method in which concrete is poured inside the formed frame.
【0003】石積み工法は、基本的に人手に依る枠体構
築法であって、使用可能なブロックもその形状が20c
m×30cmで重量が20〜25kgのものに限定され
るため、施工期間の短縮化を図ることが難しい。機材を
用いて型枠を組み立てる型枠工法ではこのようなことは
ないが機材の組立てに時間を要する。The masonry method is basically a method of constructing a frame by hand, and usable blocks have a shape of 20c.
Since it is limited to those having a size of mx 30 cm and a weight of 20 to 25 kg, it is difficult to shorten the construction period. This is not the case with the formwork method of assembling a formwork using equipment, but it takes time to assemble the equipment.
【0004】各工法ではコンクリートの側圧による枠体
の破壊を防ぐため、 ・石積み工法の場合、ブロック1段分の20〜30cm
の高さごとにコンクリートを打設し、 ・型枠工法の場合、1〜1.5mの高さごとに数次に分
けてコンクリートを打設している。直壁施工(型枠工
法)のときは4〜5mを限度にコンクリートを打設す
る。In each method, in order to prevent the destruction of the frame due to the lateral pressure of the concrete: In the case of the masonry method, 20 to 30 cm for one block
Concrete is cast at every height. ・ In the case of the formwork method, concrete is cast at several levels every 1 to 1.5 m. In the case of straight wall construction (formwork method), concrete is poured within a limit of 4 to 5 m.
【0005】なお、の石の積み上げ作業時の足場とし
ては最後に打設したコンクリートの(硬化後の)上面を
用い、の型枠の組み立て時には地面側からパイプなど
による足場を新たに設置している。[0005] As a scaffold for the work of stacking stones, the upper surface of concrete (hardened) cast last is used, and when assembling the formwork, a scaffold such as a pipe is newly installed from the ground side. I have.
【0006】石積み工法の場合の枠体形成に用いた石は
施工終了後もそのまま残ってコンクリート構造物の外表
面を構成するが、型枠工法の場合の型枠および足場は施
工終了後に解体される。[0006] In the case of the masonry method, the stone used for forming the frame remains as it is after the completion of the construction and forms the outer surface of the concrete structure. In the case of the formwork method, the formwork and the scaffold are dismantled after the completion of the construction. You.
【0007】[0007]
【発明が解決しようとする課題】このような石積み工法
の場合、ブロックの形状や重さも限定され、その工程も
職人(石工)さんの構築作業が中心となるため、工期の
短縮化が難しく経済性の点で効率的ではないという問題
点があった。このことは高齢化社会に進んでいくほど顕
著化する。In the case of such a masonry construction method, the shape and weight of the blocks are limited, and the construction process is mainly performed by a craftsman (mason). There was a problem that it was not efficient in terms of sex. This becomes more prominent as we move into an aging society.
【0008】型枠工法の場合、型枠職人による枠体の構
築や、コンクリート施工終了後の足場および型枠の解体
・片付けが必要となるため、作業が煩雑化し、作業全体
の効率性を十分に確保できないという問題点があった。In the case of the formwork method, it is necessary to construct a frame by a formwork craftsman and to disassemble and clear the scaffold and the formwork after the completion of concrete work, which complicates the work and sufficiently improves the efficiency of the entire work. There was a problem that it could not be secured.
【0009】そこで、本発明では、機材の使用により枠
体を構築していく複数のブロック単位を保持部材に固定
し、さらにはこの保持部材自体や、当該固定用の結合部
材の一部をコンクリートの打設空間に設けることによ
り、施工期間の短縮化に加えて枠体の一体化,安定化や
面一化を図ることを目的とする。Therefore, in the present invention, a plurality of block units for constructing a frame by using equipment are fixed to a holding member, and furthermore, the holding member itself and a part of the fixing connecting member are fixed to concrete. The purpose of the present invention is to provide an integrated space, stabilization and leveling of the frame in addition to shortening the construction period by providing the space in the casting space.
【0010】また、コンクリート構造物の完成時に当該
ブロックをその一部とすることにより、施工後の枠体撤
去作業を不要にすることを目的とする。Another object of the present invention is to eliminate the need for removing the frame after the construction by making the block a part of the concrete structure when the structure is completed.
【0011】[0011]
【課題を解決するための手段】本発明はこれらの課題を
次のようにして解決する。 (1)略同一形状のブロックで構築した枠体の内側にコ
ンクリートを打設して、コンクリート構造物を施工する
に際し、前記枠体構築時の前記ブロックをその複数から
なる単位で保持部材に固定する。 (2)上記(1)において、前記ブロックを前記コンク
リート構造物の一部として残したままとする。 (3)上記(1),(2)において、前記保持部材をコ
ンクリートの打設空間に設ける。 (4)上記(1),(2),(3)において、前記ブロ
ックとしてその一部に孔部を形成したものを使用し、前
記打設作業に先だち、前記ブロックを前記保持部材に固
定するための結合部材を当該孔部に通してその一部がコ
ンクリートの打設空間に入り込んだ状態にする。The present invention solves these problems as follows. (1) When concrete is poured into the inside of a frame constructed of blocks having substantially the same shape and a concrete structure is constructed, the blocks at the time of constructing the frame are fixed to a holding member in units of a plurality of frames. I do. (2) In the above (1), the block is left as a part of the concrete structure. (3) In the above (1) and (2), the holding member is provided in a concrete casting space. (4) In the above (1), (2), and (3), a block having a hole formed in a part thereof is used, and the block is fixed to the holding member before the casting operation. A connecting member is passed through the hole so that a part of the connecting member enters the concrete casting space.
【0012】本発明によれば、上記(1)のように、略
同一形状のブロックを保持部材に固定して枠体を順次構
築することにより、枠体の一体化,安定化や枠体表面全
体の面一化を図っている。なお、ブロックを保持部材に
固定するための手段は任意であり、後述のボルト・ナッ
ト機構の外、各種の連結部材,接着手法(溶接など)を
用いてもよい。According to the present invention, as described in the above (1), the frames are successively constructed by fixing the blocks having substantially the same shape to the holding member, thereby integrating and stabilizing the frames and improving the surface of the frames. It is aiming for the same level as a whole. The means for fixing the block to the holding member is arbitrary, and various connecting members and bonding methods (such as welding) may be used in addition to the bolt / nut mechanism described later.
【0013】また、上記(2)のように、枠体構築用の
ブロックをコンクリート構造物の完成時にその一部とす
ることにより、施工後の枠体撤去作業を不要にしてい
る。Further, as described in (2) above, the frame construction block is part of the concrete structure at the time of completion of the concrete structure, thereby making it unnecessary to remove the frame after construction.
【0014】また、上記(3)のように、ブロック固定
対象の保持部材をコンクリート打設空間に設けて最終的
に当該保持部材をコンクリートで固めることにより、コ
ンクリート構造物完成時の枠体全体を安定なものにして
いる。Further, as described in (3) above, the holding member to be fixed to the block is provided in the concrete casting space, and the holding member is finally hardened with concrete, so that the entire frame at the time of the completion of the concrete structure is completed. It is stable.
【0015】また、上記(4)のように、ブロックを保
持部材に固定するためのツールである結合部材をコンク
リート打設空間に設けて最終的に当該結合部材をコンク
リートで固めることにより、コンクリート構造物完成時
の枠体全体をいっそう安定なものにしている。Further, as described in (4) above, a connecting member, which is a tool for fixing the block to the holding member, is provided in the concrete casting space, and the connecting member is finally hardened with concrete. The whole frame at the time of product completion is more stable.
【0016】[0016]
【発明の実施の形態】図1乃至図6を参照して本発明の
実施の形態を説明する。これらの図において、1は枠体
構築用のブロック(図6参照),1aはブロック中央に
形成したボルト挿入用の(小径)孔部、1bは当該孔部
から表面側に続く大径凹部,1cは(小径)孔部1aと
大径凹部1bとの間の段部,1dはブロック1の上面側
位置決め部,1eはブロック1の下面側位置決め部,2
は地面部分(基礎)に設置した縦方向のC形鋼,2aは
支持部,2bは基部,2cはボルト貫通用の孔部,3は
地面の掘削部分にコンクリートで形成した基礎,3aは
一段目のブロックを案内して定置するための段部,5は
引抜き板,6は割り栗,7はボルト(結合部材),7a
および7bはネジ部,8および8′はブロック1を固定
するための横方向のC形鋼(保持部材),8aおよび8
a′はボルト貫通用の孔部,8bおよび8b′はC形鋼
8,8′の鍔部に設けた連結棒貫通用の孔部,9はネジ
部7aに対するキャップ,9aはキャップ9の内側ネジ
部,10はC形鋼2に連結した縦方向のC形鋼,10a
はボルト貫通用の孔部,11は連結板,12は上下方向
の隣同士に位置するC形鋼8やC形鋼8′を所定間隔で
保持するための連結棒(ボルト),12aはネジ部,を
それぞれ示している。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described with reference to FIGS. In these figures, 1 is a block for constructing a frame (see FIG. 6), 1a is a (small diameter) hole for bolt insertion formed in the center of the block, 1b is a large diameter recess extending from the hole to the surface side, 1c is a step between the (small-diameter) hole 1a and the large-diameter recess 1b, 1d is an upper-side positioning portion of the block 1, 1e is a lower-side positioning portion of the block 1, 2
Is a vertical C-shaped steel installed on the ground portion (foundation), 2a is a support portion, 2b is a base portion, 2c is a hole for bolt penetration, 3 is a concrete excavated portion of the ground, and 3a is a single step. Step for guiding and positioning the eye block, 5 is a pull-out plate, 6 is a split chestnut, 7 is a bolt (coupling member), 7a
And 7b are threaded portions, 8 and 8 'are lateral C-shaped steel members (retaining members) for fixing the block 1, 8a and 8
a 'is a hole for bolt penetration; 8b and 8b' are holes for connecting rods provided in flanges of C-shaped steel members 8 and 8 '; 9 is a cap for screw portion 7a; The threaded portion 10 is a longitudinal C-shaped steel connected to the C-shaped steel 2, 10a
Is a hole for bolt penetration, 11 is a connecting plate, 12 is a connecting rod (bolt) for holding the C-shaped steel 8 or C-shaped steel 8 'located at a predetermined interval adjacent to each other in the vertical direction, and 12a is a screw. , Respectively.
【0017】図1は、法面を対象としたもたれ擁壁を施
工するときの説明図である。施工時の一回のコンクリー
ト打設の高さは例えばブロック1の上下方向2個分に相
当の約200cmであり、基礎3に固定されたC形鋼2
の支持部2aの長さは約220cmである。FIG. 1 is an explanatory view when a leaning retaining wall intended for a slope is constructed. The height of one concrete casting at the time of construction is, for example, about 200 cm corresponding to two blocks 1 in the vertical direction, and the C-shaped steel 2 fixed to the foundation 3
Has a length of about 220 cm.
【0018】図2は、図1のもたれ擁壁の施工手順を示
す説明図であり、その内容は次のようになっている。 (S1)縦方向のC形鋼2の基部2bを埋め込んだ態様
で基礎3を形成する。 (s2)枠体構築用のブロック1を基礎3(または下段
ブロック)に載置する。ブロック1は段部3aに案内さ
れている。 (S3)ブロック1の孔部1aおよび横方向のC形鋼8
の孔部8aにボルト7を挿入してからそのC形鋼2の側
にナットを取り付ける。 (S4)ボルト7のナット取付側端部を縦方向のC形鋼
2の孔部2cに挿入する。 (S5)ボルト7の一方のネジ部7aにキャップ9およ
び上記ナットを螺合させて横方向のC形鋼8にブロック
1を固定するとともに、他方のネジ部7bに上記ナット
などを螺合させて縦方向のC形鋼2にボルト7を固定す
る。FIG. 2 is an explanatory view showing the procedure for constructing the leaning retaining wall of FIG. 1, and the contents are as follows. (S1) The foundation 3 is formed in a mode in which the base 2b of the longitudinal C-shaped steel 2 is embedded. (S2) The block 1 for constructing the frame is placed on the foundation 3 (or the lower block). Block 1 is guided to step 3a. (S3) Hole 1a of block 1 and lateral C-shaped steel 8
After the bolt 7 is inserted into the hole 8a, a nut is attached to the C-shaped steel 2 side. (S4) Insert the nut mounting end of the bolt 7 into the hole 2c of the C-shaped steel 2 in the vertical direction. (S5) The cap 9 and the nut are screwed into one screw portion 7a of the bolt 7 to fix the block 1 to the lateral C-shaped steel member 8, and the nut or the like is screwed into the other screw portion 7b. The bolt 7 is fixed to the C-shaped steel 2 in the vertical direction.
【0019】ここで、キャップ9およびナットとネジ部
7aとの上記螺合に基づく締付け作用によって、段単位
のブロック1はそれぞれ横方向のC形鋼8に確実に固定
され、当該ブロック全体の面一性も確保される。Here, the block 1 of each step is securely fixed to the lateral C-shaped steel 8 by the tightening action based on the above-mentioned screwing of the cap 9 and the nut with the screw portion 7a. Oneness is secured.
【0020】続いてステップ(s2)以降の作業を繰り
返すことにより、基礎3に続く上下2段のブロック1か
らなる一次枠体を構築する。なお、上下2段のブロック
同士は下段ブロックの上面側位置決め部1dと上段ブロ
ックの下面側位置決め部1eとによって確実に位置決め
される。Subsequently, by repeating the operation of step (s2) and subsequent steps, a primary frame consisting of upper and lower blocks 1 following the base 3 is constructed. The upper and lower blocks are reliably positioned by the upper-side positioning portion 1d of the lower block and the lower-side positioning portion 1e of the upper block.
【0020】この一次枠体を構築してから次の作業に移
行する。 (s6)縦方向のC形鋼2の裏側(法面側)に引抜き板
5を設置して、それと法面との間に割り栗6を入れる。 (s7)引抜き板5と一次枠体との間に一次コンクリー
トを打設する。 (s8)コンクリートがある程度硬化してから引抜き板
5を上方に引き抜く。After the construction of the primary frame, the operation proceeds to the next operation. (S6) The drawing plate 5 is installed on the back side (slope side) of the C-shaped steel 2 in the longitudinal direction, and the split chestnut 6 is inserted between the drawing plate 5 and the slope. (S7) Primary concrete is cast between the drawing plate 5 and the primary frame. (S8) After the concrete has hardened to some extent, the drawing plate 5 is pulled upward.
【0021】このようにして基礎3に続くブロック2段
分の擁壁を形成した後、縦方向のC形鋼2とこれに連結
されるC形鋼10との端部同士を連結板11で挟み込
み、当該連結板をボルトとナットで固定してから、次の
ブロック2段分の擁壁施工へと移行する。After forming the retaining wall for the two blocks following the foundation 3 in this manner, the ends of the longitudinal C-shaped steel 2 and the C-shaped steel 10 connected thereto are connected by the connecting plate 11. After sandwiching and fixing the connecting plate with bolts and nuts, the process moves to the next two steps of retaining wall construction.
【0022】すなわち、C形鋼10の連結後に当該C形
鋼を対象とした上述の(s1)乃至(s6)および(s
7)乃至(s9)の作業を新たに実行して、計ブロック
4段分の擁壁を施工する。That is, after the connection of the C-shaped steel 10, the above-mentioned (s1) to (s6) and (s
7) through (s9) are newly executed, and a retaining wall for a total of four steps is constructed.
【0023】なお、3段目および4段目のブロックを構
築するときの足場には、その下側ブロック2段分の打設
コンクリートの上面部分などを用いる。As the scaffold for constructing the third and fourth blocks, the upper surface of cast concrete for the two lower blocks is used.
【0024】同様の作業を繰り返すことにより、予定し
たブロック段数分のもたれ擁壁を施工している。By repeating the same operation, a leaning retaining wall for a predetermined number of blocks is constructed.
【0025】図3および図4は、対向状態のブロック枠
体間にコンクリートを打設して擁壁を施工するときの説
明図であり、図3は直擁壁を示し、図4は堤体式の重力
擁壁を示している。施工時の一回のコンクリート打設の
高さは図1のもたれ擁壁の場合と同様である。FIGS. 3 and 4 are explanatory views when a concrete retaining wall is constructed by casting concrete between block frames facing each other, FIG. 3 shows a straight retaining wall, and FIG. Shows a gravity retaining wall. The height of one concrete casting during construction is the same as that of the leaning retaining wall in FIG.
【0026】図1のもたれ擁壁との主な相違点は、 ・縦方向のC形鋼2およびこれに連結されるC形鋼1
0,引抜き板5,割り栗6,連結板11などを使用しな
いこと ・ブロック枠体を対向する形で設置したこと ・各段の複数ブロックを固定する横方向のC形鋼8,
8′をブロック表面側に設けたこと(図3の直擁壁の場
合) ・同じブロック枠体の隣同士のC形鋼8,8′を固定す
るための連結棒12を設けたこと などである。The main differences from the leaning retaining wall of FIG. 1 are as follows: a longitudinal C-shaped steel 2 and a C-shaped steel 1 connected thereto;
0, draw-out plate 5, split chestnut 6, connecting plate 11, etc. not to be used ・ The block frame is installed facing each other ・ The horizontal C-shaped steel 8, which fixes a plurality of blocks in each step
8 ′ is provided on the block surface side (in the case of a straight retaining wall in FIG. 3). ・ A connecting rod 12 for fixing the adjacent C-shaped steel members 8, 8 ′ of the same block frame is provided. is there.
【0027】図5は、図3および図4の擁壁の施工手順
を示す説明図であり、その内容は次のようになってい
る。 (s11)地面の掘削部分にコンクリートを打設して基
礎3を形成する。 (s12)枠体構築用のブロック1をそれぞれ対向させ
る形で基礎3(または下段ブロック)に載置する。ブロ
ック1は段部3aに案内されている。 (S13)横方向のC形鋼8の孔部8aおよび対向状態
の一方のブロック1の孔部1aにボルト7を挿入してか
らそのコンクリート打設側にナットを取り付ける。 (S14)ボルト7のナット取付側端部を対向状態の他
方のブロック1の孔部1aおよびC形鋼8′の孔部8
a′に挿入する。 (S15)ボルト7の端部側の各ネジ部7a,7bにキ
ャップ9および上記ナットを螺合させて横方向のC形鋼
8,8′にブロック1をそれぞれ固定する。FIG. 5 is an explanatory view showing the procedure for constructing the retaining wall of FIGS. 3 and 4, and the contents are as follows. (S11) The concrete 3 is cast on the excavated portion of the ground to form the foundation 3. (S12) The blocks 1 for constructing the frame are placed on the foundation 3 (or the lower block) so as to face each other. Block 1 is guided to step 3a. (S13) The bolt 7 is inserted into the hole 8a of the C-shaped steel 8 in the lateral direction and the hole 1a of one of the blocks 1 facing each other, and then a nut is attached to the concrete casting side. (S14) The hole 1a of the other block 1 and the hole 8 of the C-section steel 8 'with the nut mounting end of the bolt 7 facing the other.
a '. (S15) The cap 9 and the nut are screwed into the threaded portions 7a, 7b on the end side of the bolt 7, and the block 1 is fixed to the lateral C-shaped steels 8, 8 '.
【0028】次に、最下段ブロックを対象に上記ステッ
プ(s12)乃至(s15)の作業を新たに実行して基
礎3に続く上下2段のブロック1からなる一次枠体を構
築し、その中に一次コンクリートを打設する。Next, the operations of steps (s12) to (s15) are newly performed on the lowermost block to construct a primary frame composed of upper and lower two-level blocks 1 following the foundation 3, and the primary frame is constructed therein. Pour primary concrete into
【0029】以上の作業を繰り返すことにより、予定段
数分のコンクリート擁壁を施工している。上下に隣同士
のC形鋼8やC形鋼8′の間には連結棒12を必要に応
じて設け、この連結棒とナットとで当該C形鋼同士を固
定している。By repeating the above operation, concrete retaining walls for the predetermined number of steps are constructed. A connecting rod 12 is provided as needed between the vertically adjacent C-shaped steel members 8 and 8 ', and the connecting rods and nuts fix the C-shaped steel members together.
【0030】図3の施工時は足場を組み、擁壁完成後に
はキャップ9をボルト7から外して(それまでブロック
1を段単位で保持していた)C形鋼8,8′を取り外
す。なお、図4の施工時の足場としては打設コンクリー
トの上面部分などを用いる。At the time of the construction shown in FIG. 3, the scaffold is assembled, and after the retaining wall is completed, the cap 9 is removed from the bolt 7 (the C-shaped steels 8, 8 ', which had been holding the blocks 1 in steps until then), are removed. In addition, as a scaffold at the time of construction of FIG. 4, an upper surface portion of cast concrete is used.
【0031】図4の重力擁壁ではその対向ブロックの間
隔が2m以上になることもある。このような場合など、
対向するブロック同士をボルト7で連結する代わりに、
図1のときと同じように、当該ブロックのそれぞれに対
応した縦方向のC形鋼2を個々に設け、これとブロック
とをボルト7で連結してもよい。In the gravity retaining wall shown in FIG. 4, the distance between the opposing blocks may be 2 m or more. In such cases,
Instead of connecting the opposing blocks with bolts 7,
As in the case of FIG. 1, a vertical C-shaped steel 2 corresponding to each of the blocks may be individually provided, and this may be connected to the block by bolts 7.
【0032】上述の各施工に際して、ボルト7は、 ・ブロック1をC形鋼8,8′に固定する機能 ・基礎3に固定された縦方向のC形鋼2とブロック1と
の間隔や、対向するブロック同士の間隔を保持する機能 を併せ持っている。In each of the above-mentioned constructions, the bolt 7 has the following functions: a function of fixing the block 1 to the C-shaped steel members 8 and 8 '; a distance between the vertical C-shaped steel member 2 fixed to the foundation 3 and the block 1; It also has the function of maintaining the space between opposing blocks.
【0033】C形鋼2,8,8′,10の各孔部をあら
かじめ工場で形成するか、施工時に現場で形成するかは
任意である。It is optional whether the holes of the C-shaped steels 2, 8, 8 ', and 10 are formed in advance in a factory or on site during construction.
【0034】これら各孔部の個数も任意であり、図示に
ように多数の孔部を形成しておけばブロック1,ボルト
7,連結棒12などとC形鋼の孔部との位置合わせ作業
を簡単に行なうことができる。また、図1や図4のよう
に、C形鋼2,8,8′,10をコンクリートの打設空
間に設ける施工形式の場合には、打設されたコンクリー
トが未使用の各孔部からも入り込んでいき、C形鋼の周
辺にも十分なコンクリートが供給される。The number of these holes is also arbitrary, and if a large number of holes are formed as shown in the figure, the work of aligning the blocks 1, bolts 7, connecting rods 12 and the like with the holes of the C-section steel can be performed. Can be easily performed. In the case of the construction type in which the C-section steels 2, 8, 8 'and 10 are provided in the concrete casting space as shown in FIGS. 1 and 4, the cast concrete is removed from each unused hole. And enough concrete is supplied around the C-shaped steel.
【0035】上述の各施工において、 ・C形鋼2,8,8′,10の代わりにL形鋼やH形鋼
を用いる、 ・C形鋼2,10をブロック3段分以上の長さにする、 ようにしてもよい。In each of the above constructions, an L-beam or an H-beam is used in place of the C-beams 2, 8, 8 'and 10. May be used.
【0036】図6は、各種形態からなる枠体構築用のブ
ロックを示す説明図であり、 (a)は表裏面とも平面にした方形状ブロック (b)は裏面の対向する縁部分を凸状にした方形状ブロ
ック (c)は表裏面とも平面にした三角形状ブロック をそれぞれ示している。なお、ブロック自体の形状は任
意であり、他の多角形状や円状のものでもよい。FIGS. 6A and 6B are explanatory views showing frames for constructing a frame body in various forms. FIG. 6A is a square block having both front and rear surfaces flat, and FIG. The rectangular block (c) shown here is a triangular block in which both the front and back surfaces are flat. The shape of the block itself is arbitrary, and may be another polygonal shape or circular shape.
【0037】上述のように、1は枠体構築用のブロッ
ク,1aはブロック中央に形成したボルト挿入用の(小
径)孔部,1bは当該孔部から表面側に続く大径孔部,
1cは(小径)孔部1aと大径凹部1bとの間の段部,
1dはブロック1の上面側位置決め部,1eはブロック
1の下面側位置決め部をそれぞれ示している。As described above, 1 is a block for constructing a frame, 1a is a (small diameter) hole for bolt insertion formed in the center of the block, 1b is a large diameter hole extending from the hole to the surface side,
1c is a step between the (small diameter) hole 1a and the large diameter recess 1b,
Reference numeral 1d denotes an upper surface side positioning portion of the block 1, and 1e denotes a lower surface side positioning portion of the block 1.
【0038】図1や図3,図4の施工例(一回のコンク
リート打設の高さ:約200cm)で用いる枠体構築用
のブロック1は、概略、 ・高さ(H)が1000mm ・幅(W)が1000mm ・厚さ(T)が100〜150mm ・重さが100〜200kg である。The frame construction block 1 used in the construction examples shown in FIGS. 1, 3 and 4 (the height of a single concrete casting: about 200 cm) is roughly as follows: Height (H) is 1000 mm The width (W) is 1000 mm, the thickness (T) is 100 to 150 mm, and the weight is 100 to 200 kg.
【0039】孔部1aや大径凹部1bはブロック1の製
造時にあらかじめ設けてもよいし、施工現場で設けるよ
うにしてもよい。孔部1aや大径凹部1bの設定位置や
個数も任意である。また、ブロック1にラス金網を埋め
込んで当該ブロックの強度を上げてもよい。The hole 1a and the large-diameter concave portion 1b may be provided in advance at the time of manufacturing the block 1, or may be provided at a construction site. The set positions and the number of the holes 1a and the large-diameter concave portions 1b are also arbitrary. Further, a lath wire mesh may be embedded in the block 1 to increase the strength of the block.
【0040】上述の各種擁壁の完成後もブロック1の大
径凹部1bに残ったままのボルト7のネジ部を、ブロッ
ク枠体の外表面側で用いる足場や梯子などの取り付け用
基部として用いることもできる。The threaded portion of the bolt 7 remaining in the large-diameter recess 1b of the block 1 even after completion of the above-mentioned various retaining walls is used as a mounting base for a scaffold or a ladder used on the outer surface side of the block frame. You can also.
【0041】[0041]
【発明の効果】このように、本発明は、略同一形状のブ
ロックを保持部材に固定して枠体を順次構築するので、
枠体の一体化,安定化や枠体表面全体の面一化を図るこ
とができる。As described above, according to the present invention, the frames are successively constructed by fixing the blocks having substantially the same shape to the holding member.
It is possible to integrate and stabilize the frame, and to level the entire surface of the frame.
【0042】また、枠体構築用のブロックをコンクリー
ト構造物の完成時にその一部としているので、施工後の
枠体撤去作業が不要となり、作業期間の短縮化を図るこ
とができる。Further, since the block for constructing the frame is used as a part of the concrete structure at the time of completion of the concrete structure, the work of removing the frame after construction is not required, and the working period can be shortened.
【0043】また、ブロック固定対象の保持部材をコン
クリート打設空間に設け、最終的に当該保持部材をコン
クリートで固めているので、コンクリート構造物完成時
の枠体全体を安定なものにすることができる。Further, since the holding member to be fixed to the block is provided in the concrete casting space and the holding member is finally hardened with concrete, the whole frame at the time of completion of the concrete structure can be stabilized. it can.
【0044】また、ブロックを保持部材に固定するため
のツールである結合部材をコンクリート打設空間に設
け、最終的に当該結合部材をコンクリートで固めている
ので、コンクリート構造物完成時の枠体全体をより安定
なものにすることができる。Further, since a connecting member, which is a tool for fixing the block to the holding member, is provided in the concrete casting space, and the connecting member is finally hardened with concrete, the entire frame body when the concrete structure is completed is completed. Can be made more stable.
【図1】本発明の、法面を対象としたもたれ擁壁を施工
するときの説明図である。FIG. 1 is an explanatory view when a leaning retaining wall for a slope is constructed according to the present invention.
【図2】本発明の、図1のもたれ擁壁の施工手順を示す
説明図である。FIG. 2 is an explanatory view showing a construction procedure of the leaning retaining wall of FIG. 1 according to the present invention.
【図3】本発明の、直擁壁を施工するときの説明図であ
る。FIG. 3 is an explanatory view when a straight retaining wall is constructed according to the present invention.
【図4】本発明の、堤体式の重力擁壁を施工するときの
説明図である。FIG. 4 is an explanatory view when a levee type gravity retaining wall is constructed according to the present invention.
【図5】本発明の、図3および図4の擁壁の施工手順を
示す説明図である。FIG. 5 is an explanatory view showing a procedure for constructing the retaining wall of FIGS. 3 and 4 according to the present invention.
【図6】本発明の、各種形態からなる枠体構築用のブロ
ックを示す説明図である。FIG. 6 is an explanatory diagram showing frames for constructing a frame body in various forms according to the present invention.
1:枠体構築用のブロック 1a:ブロック中央に形成したボルト挿入用の(小径)
孔部 1b:当該孔部から表面側に続く大径凹部 1c:(小径)孔部1aと大径凹部1bとの間の段部 1d:ブロック1の上面側位置決め部 1e:ブロック1の下面側位置決め部 2:地面部分(基礎)に設置した縦方向のC形鋼 2a:支持部 2b:基部 2c:ボルト貫通用の孔部 3:地面の掘削部分にコンクリートで形成した基礎, 3a:ブロックを案内して定置するための段部, 5:引抜き板 6:割り栗 7:ボルト(結合部材) 7a,7b:ネジ部 8,8′:ブロック1を固定するための横方向のC形鋼
(保持部材) 8a,8a′:ボルト貫通用の孔部 8b,8b′:鍔部に設けた連結棒貫通用の孔部 9:ネジ部7a,7bに対するキャップ 9a:キャップの内側ネジ部 10:C形鋼2に連結した縦方向のC形鋼 10a:ボルト貫通用の孔部 11:連結板 12:上下方向の隣同士に位置するC形鋼8やC形鋼
8′を所定間隔で保持するための連結棒(ボルト) 12a:ネジ部1: Block for frame construction 1a: For bolt insertion (small diameter) formed in the center of the block
Hole 1b: Large-diameter concave portion continuing from the hole to the front surface side 1c: (Small-diameter) step portion between hole 1a and large-diameter concave portion 1b 1d: Upper surface side positioning portion of block 1 1e: Lower surface side of block 1 Positioning part 2: Vertical C-shaped steel installed on the ground part (foundation) 2a: Support part 2b: Base part 2c: Hole for bolt penetration 3: Base made of concrete in excavated part of ground, 3a: Block Step for guiding and setting, 5: Pull-out plate 6: Split chestnut 7: Bolt (coupling member) 7a, 7b: Screw portion 8, 8 ': Lateral C-shaped steel for fixing block 1 ( 8a, 8a ': Hole for bolt penetration 8b, 8b': Hole for connection rod penetration provided in flange 9: Cap for screw portion 7a, 7b 9a: Inner screw portion of cap 10: C Longitudinal C-section steel 10a connected to section 2 Through a hole portion 11: connection plate 12: the vertical direction of the connecting rod to hold the C-shaped steel 8 and C-shaped steel 8 'at predetermined intervals, located next to each other (volts) 12a: screw portion
Claims (4)
内側にコンクリートを打設して、コンクリート構造物を
施工する方法であって、 前記枠体を構築する際の前記ブロックをその複数からな
る単位で保持部材に固定する、ことを特徴とするコンク
リート構造物の施工方法。1. A method of constructing a concrete structure by casting concrete inside a frame constructed of blocks of substantially the same shape, wherein the block is constructed from a plurality of blocks when constructing the frame. A method for constructing a concrete structure, wherein the method is fixed to a holding member in units of:
部として残したままとする、ことを特徴とする請求項1
記載のコンクリート構造物の施工方法。2. The method according to claim 1, wherein said block is left as a part of a concrete structure.
The construction method of the concrete structure described.
に設けた、ことを特徴とする請求項1または2記載のコ
ンクリート構造物の施工方法。3. The method according to claim 1, wherein the holding member is provided in a concrete casting space.
形成したものを使用し、 前記打設作業に先だち、前記ブロックを前記保持部材に
固定するための結合部材を当該孔部に通してその一部が
コンクリートの打設空間に入り込んだ状態にする、こと
を特徴とする請求項1乃至3記載のコンクリート構造物
の施工方法。4. A block having a hole formed in a part thereof, and a connecting member for fixing the block to the holding member is passed through the hole prior to the placing operation. The method according to claim 1, wherein a part of the concrete structure is put into a concrete placing space.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33478399A JP2001115468A (en) | 1999-10-19 | 1999-10-19 | Execution method of concrete structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33478399A JP2001115468A (en) | 1999-10-19 | 1999-10-19 | Execution method of concrete structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2001115468A true JP2001115468A (en) | 2001-04-24 |
Family
ID=18281195
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33478399A Pending JP2001115468A (en) | 1999-10-19 | 1999-10-19 | Execution method of concrete structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2001115468A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100412160B1 (en) * | 1999-04-24 | 2003-12-31 | 주식회사 기하 동문 건축사사무소 | Structure of steel aggregate for concrete building |
JP2005030011A (en) * | 2003-07-09 | 2005-02-03 | Oohishi:Kk | Concrete wall |
CN106638676A (en) * | 2017-02-10 | 2017-05-10 | 合肥学院 | Gravity type retaining wall structure formed by waste tires and construction method thereof |
CN106759471A (en) * | 2017-02-10 | 2017-05-31 | 合肥学院 | Arched retaining wall structure formed by waste tires and construction method thereof |
KR20180137951A (en) * | 2017-06-20 | 2018-12-28 | 한국도로공사 | Method for constructing a retaining wall using lightweight flowable fills |
-
1999
- 1999-10-19 JP JP33478399A patent/JP2001115468A/en active Pending
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100412160B1 (en) * | 1999-04-24 | 2003-12-31 | 주식회사 기하 동문 건축사사무소 | Structure of steel aggregate for concrete building |
JP2005030011A (en) * | 2003-07-09 | 2005-02-03 | Oohishi:Kk | Concrete wall |
JP4676683B2 (en) * | 2003-07-09 | 2011-04-27 | 株式会社大菱 | Concrete wall |
CN106638676A (en) * | 2017-02-10 | 2017-05-10 | 合肥学院 | Gravity type retaining wall structure formed by waste tires and construction method thereof |
CN106759471A (en) * | 2017-02-10 | 2017-05-31 | 合肥学院 | Arched retaining wall structure formed by waste tires and construction method thereof |
KR20180137951A (en) * | 2017-06-20 | 2018-12-28 | 한국도로공사 | Method for constructing a retaining wall using lightweight flowable fills |
KR102003843B1 (en) * | 2017-06-20 | 2019-07-25 | 한국도로공사 | Method for constructing a retaining wall using lightweight flowable fills |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2360710C (en) | Temporary bracing system for insulated wall form and method | |
EP1945879A2 (en) | Bolt-a-blok - a system for unitized, post-tensioned masonry structures | |
JP2001115468A (en) | Execution method of concrete structure | |
EP1561874A1 (en) | Connecting device and node for buildings with prefabricated elements | |
JP3763575B2 (en) | Underground beam construction frame and underground beam construction method using the same | |
JP2003336213A (en) | Concrete receiving beam and method for building girder by using it | |
KR102398605B1 (en) | Construction method of seismic retrofit system using pc panel | |
KR101288831B1 (en) | Remodeling construction method using micropile and truss in a surrounding structure and the places that it is adjacent to | |
JP2009257006A (en) | Ground anchor construction method | |
EP1126091A2 (en) | Mounting support and process using such a support for mounting a prefabricated element on a building part | |
KR100626326B1 (en) | concrete structure | |
JP3408629B2 (en) | Precast concrete foundation structure | |
JP4385127B2 (en) | Slope protection retaining wall construction method and retaining wall building unit | |
JPS61233131A (en) | Foundation structure of pole | |
KR102682632B1 (en) | Permanant form panel for buliding foundation work | |
JP2889840B2 (en) | Construction method of underground outer peripheral wall | |
KR102678291B1 (en) | Steel lintel for U block and U block lintel beam combined with U block and construction method thereof | |
KR102709947B1 (en) | Dry bonding system for A-type pillars and girders that do not require additional concrete pouring, and dry bonding method using the same | |
KR102720024B1 (en) | Form bar having inclined plate | |
JP2009275475A (en) | Post erection method by anchor bolt, and anchor bolt bender | |
JP3744922B2 (en) | PC foundation beam member and its connection structure | |
JP3025638B2 (en) | Formwork equipment for fabric foundation | |
KR100897342B1 (en) | Floor extension method using hybrid structure | |
KR200362827Y1 (en) | concrete structure | |
JP2008261153A (en) | Reinforcing method of concrete skeleton |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040601 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050405 |