CN208533543U - Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance - Google Patents

Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance Download PDF

Info

Publication number
CN208533543U
CN208533543U CN201821125826.0U CN201821125826U CN208533543U CN 208533543 U CN208533543 U CN 208533543U CN 201821125826 U CN201821125826 U CN 201821125826U CN 208533543 U CN208533543 U CN 208533543U
Authority
CN
China
Prior art keywords
foundation pit
smw
grouting pipe
supporting construction
waterproof performance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821125826.0U
Other languages
Chinese (zh)
Inventor
谢伟东
李兆平
夏春亮
刘川
王兴全
袁军
丁彬
柴文东
李建华
李鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201821125826.0U priority Critical patent/CN208533543U/en
Application granted granted Critical
Publication of CN208533543U publication Critical patent/CN208533543U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a kind of structure and foundation pit SMW supporting construction for improving foundation pit side-wall waterproof performance, wherein, the foundation pit SMW building enclosure includes: structure side wall (1) in sequentially connected foundation pit, waterproof roll layer (5), sand finish layer (3) and foundation pit SMW supporting construction (2);The foundation pit SMW supporting construction (2) includes: multiple SMW pile bodies (22), the Grouting Pipe (23) being arranged in each SMW pile body (22);Multiple extravasating holes (231) are set on the Grouting Pipe (23);Filled with cement slurry in the Grouting Pipe (23) and in the cavity between Grouting Pipe (23) and foundation pit SMW pile body (22).The utility model can be improved the waterproof effect of structure side wall in foundation pit, solve the technical problem for the cement soil pile water-stagnating effect difference left after the fashioned iron in foundation pit SMW supporting construction is extracted.

Description

Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance
Technical field
The utility model relates to technical field of building construction, more particularly, to a kind of knot for improving foundation pit side-wall waterproof performance Structure and foundation pit SMW supporting construction.
Background technique
SMW (Soil Mixing Wall, fashioned iron cement mixing method) supporting construction 2 is to utilize special multi-shaft stirring just The ground drilling cutting soil body, forms SMW foundation pit, while cement grout is injected the soil body in drill bit end, after being thoroughly mixed, Structure side wall 1 takes overlapping lapping construction between each construction cell along foundation pit, again will before soil cement mixture is not tied firmly Fashioned iron 21 is inserted into pile body, and being formed has some strength and rigidity supporting construction, i.e. SMW supporting construction.The SMW supporting construction is made For the earth-retaining and water sealing structure of underground excavation foundation pit, there is sealing and supporting double action.
Due to the simple structure of SMW supporting construction 2, speed of application is fast, can substantially shorten the construction period, and main inside foundation pit Fashioned iron can be extracted and be recycled after the completion of body structure construction, be therefore widely used in underground construction engineering.
However, cement earth pile after support construction after the completion extracts fashioned iron inside foundation pit, as water-stop curtain Gap can be generated in vivo, these gaps will become water space and penetrating passage, and cement soil pile is easily caused locally to occur Infiltration, influences the waterproof effect of structure side wall 1 in foundation pit.
In addition, leading to the waterproof roll being laid on the inside of structure side wall 1 in fashioned iron 21 and foundation pit since fashioned iron 21 is inserted into error Between cement protective soil layer became uneven, easily damage waterproof roll in 21 withdrawal process of fashioned iron, influence waterproof effect and Structure durability.
Therefore, there is an urgent need to the relevant technologies at present to solve following two technical problems:
First, the cement soil pile water-stagnating effect that the fashioned iron in foundation pit SMW supporting construction is left after extracting is poor;
Second, being easy to cause the destruction for the waterproof roll being laid on the inside of structure side wall 1 in foundation pit during extracting fashioned iron.
Utility model content
The purpose of this utility model be presently, there are aiming at the problem that, provide it is a kind of improve foundation pit side-wall waterproof performance knot Structure and foundation pit SMW supporting construction, can effectively improve the waterproof effect of structure side wall in foundation pit, so as to solve foundation pit Influence after fashioned iron is extracted in SMW to cement soil pile waterproof performance in foundation pit.
The purpose of this utility model is achieved through the following technical solutions:
The purpose of the utility model is to provide a kind of structures for improving foundation pit side-wall waterproof performance comprising:
Structure side wall, waterproof roll layer, sand finish layer and foundation pit SMW supporting construction in sequentially connected foundation pit;
The foundation pit SMW supporting construction includes: multiple SMW pile bodies, is arranged in each SMW intracorporal Grouting Pipe;It is described Multiple extravasating holes are set in Grouting Pipe;Filled with cement slurry in the Grouting Pipe and in the cavity between Grouting Pipe and SMW pile body.
It is highly preferred that be additionally provided between the waterproof roll layer and the sand finish layer low ratio foamed polyethylene board every Absciss layer.
It is highly preferred that being wrapped in rubber ring outside the Grouting Pipe.
It is highly preferred that inner side slot of the burial place of the Grouting Pipe close to every fashioned iron of foundation pit SMW supporting construction.
The utility model also provides a kind of foundation pit SMW supporting construction for improving waterproof performance comprising:
Multiple SMW pile bodies are arranged in each SMW intracorporal Grouting Pipe;Multiple extravasating holes are set in the Grouting Pipe;Institute It states in Grouting Pipe and in the cavity between Grouting Pipe and foundation pit SMW pile body filled with cement slurry.
It is highly preferred that being wrapped in rubber ring outside the Grouting Pipe.
It is highly preferred that inner side slot of the burial place of the Grouting Pipe close to every fashioned iron of foundation pit SMW supporting construction.
The utility model has the following technical effect that it can be seen from above-mentioned the technical solution of the utility model
The utility model leaves the technology in the gap of cement soil pile by burying Grouting Pipe after filling section steel extraction, mention The waterproof effect of structure side wall in high foundation pit, to solve the water left after the fashioned iron in foundation pit SMW supporting construction is extracted The technical problem of soil pile body water-stagnating effect difference.
The utility model between SMW supporting construction pile body and side wall waterproof roll by adding one layer of low ratio foamed polyethylene The technology of benzene plate separation layer avoids and the waterproof roll that structure side wall is laid in foundation pit is easy to cause to destroy during extracting fashioned iron The drawbacks of, to further can be improved the waterproof effect of structure side wall in foundation pit.
Detailed description of the invention
Fig. 1 is the application schematic diagram of SMW building enclosure in the prior art;
Fig. 2 is the floor plan for the structure that the utility model improves foundation pit side-wall waterproof performance;
Fig. 3 is the A-A view of Fig. 2;
Fig. 4 is the B partial enlargement diagram in Fig. 3;
Fig. 5 is the structural schematic diagram of the Grouting Pipe in the utility model;
Fig. 6 is the implementation flow chart of the utility model;
Fig. 7 be the utility model in into Grouting Pipe during slip casting slurries filling mechanism schematic diagram.
In attached drawing:
It is structure side wall 1 in foundation pit, foundation pit SMW supporting construction 2, sand finish layer 3, low ratio foamed polyethylene board separation layer 4, anti- Water coiled material layer 5;Fashioned iron 21, SMW pile body 22, Grouting Pipe 23, rubber ring 24;Extravasating hole 231.
Specific embodiment
In order to make those skilled in the art more fully understand the technical solution of the application, below with reference to attached drawing 2 to attached Shown in Fig. 5, the utility model is described in further details.
Embodiment one:
The utility model provides a kind of structure for improving foundation pit side-wall waterproof performance, and structure is as shown in Fig. 2 ,-Fig. 5.It can It successively include: structure side wall 1 in foundation pit, waterproof roll layer 5, the poly- second of low ratio foamed in foundation pit SMW building enclosure to find out Alkene plate separation layer 4, sand finish layer 3, foundation pit SMW supporting construction 2;Wherein foundation pit SMW supporting construction 2 includes: multiple SMW pile bodies 22, multiple Grouting Pipes 23 are provided in each SMW pile body 22, Grouting Pipe 23 is equipped with extravasating hole 231, wraps up outside Grouting Pipe 23 There is a rubber ring 24, cement slurry is full of in Grouting Pipe 23 and in the cavity between Grouting Pipe 23 and SMW pile body 22.
The position of Grouting Pipe 23 still as shown in Fig. 2, in the inner side slot of fashioned iron 21 be arranged two Grouting Pipes 23, with Fashioned iron is inserted into pit slot soil cement simultaneously, and the upper end of the Grouting Pipe 23 and foundation pit interior main body structure roof maintain an equal level, and lower end is deep into The following set depth in Foundation Pit bottom, the set depth can be 1m.
The structure of Grouting Pipe 23 is as shown in figure 5, the Grouting Pipe 23 can use steel pipe, such as the hot finished steel pipe of φ 42mm, note It starches and is arranged on pipe by multiple extravasating holes 231, such as the extravasating hole 231 of φ 8mm.The extravasating hole 231 can be in quincuncial arrangement, can also To be arranged in other shapes, such as it is staggered in arrangement, the pitch-row between the two neighboring extravasating hole 231 of 23 axis direction of Grouting Pipe is many In setting spacing threshold, such as 1m.Cement grout enters Grouting Pipe 23 in pit slot to prevent in insertion process, the Grouting Pipe 23 Outside is enclosed with rubber ring 24.
A kind of structure of above-mentioned improvement foundation pit side-wall waterproof performance, can implement to complete, process by the following method As shown in fig. 6, including the following steps:
Step S10, after completing SMW excavation of foundation pit, in the inside slot position of the every fashioned iron close to foundation pit SMW supporting construction More Grouting Pipes 23 of place's setting are set, are inserted into foundation pit soil cement simultaneously with fashioned iron 21;It is arranged on the tube wall of the Grouting Pipe 23 multiple Extravasating hole 231, the outside of Grouting Pipe 23 are enclosed with rubber ring 24.
Step S20 constructs to foundation pit SMW supporting construction 2, and in the construction process first to 22 side of foundation pit SMW pile body Wall applies sand finish, and low ratio foamed polyethylene board separation layer 4 is then laid on the basis of the sand finish layer 3 of formation, is re-layed Waterproof roll layer 5, finally in waterproof roll layer 5 and foundation pit between structure side wall 1 joints cement soil.
To prevent fashioned iron from extracting the destruction to waterproof roll, before, first using the mortar of 5cm to foundation pit SMW supporting knot Plastering processing is carried out outside the pile body side wall of structure 2, forms the sand finish layer 3 of surfacing;Then it is poly- to re-lay one layer of low ratio foamed The thickness of vinyl plate separation layer 4, the low ratio foamed polyethylene board separation layer 4 is not less than 1cm;Then waterproof is laid on separation layer again Coiled material forms waterproof roll layer 5, finally pours structure side wall 1 in foundation pit, form foundation pit SMW as shown in Figure 5 and Figure 6 and go along with sb. to guard him Structure.
Step S30 extracts fashioned iron 21 after the completion of the construction of foundation pit SMW supporting construction 2, to slip casting after the extraction of fashioned iron 21 Pipe 23 carries out slip casing by pressure, and slurries will be wrapped in 24 distending of the rubber ring outside Grouting Pipe 23 under the action of interior pressure, until quilt The slurries of pressurization stop pressurization after filling up the gap left in foundation pit SMW pile body 22 after fashioned iron 21 is extracted.
After the completion of the main structure construction of foundation pit SMW supporting construction 2, fashioned iron 21 is extracted, to note after the extraction of fashioned iron 21 It starches pipe 23 and carries out slip casing by pressure, slurries are cement slurry, as shown in fig. 7, slurries under the action of interior pressure, will be wrapped in Grouting Pipe 24 distending of rubber ring outside 23, and overflow.(such as reach 0.5MPa) to a certain extent when pressure is gradually increased, pressurized slurries Filling will be generated along earth formation, infiltration, densification, cleaves and flows, to reach the gap after filling section steel 21 is extracted, mentioned Height leaves cement soil pile anti-permeability performance purpose.
By the utility model it can be seen from above-mentioned the technical solution of the utility model by the way that " filling section steel is left after extracting The gap of cement soil pile " and " one layer of low ratio foamed polyethylene benzene plate is added between SMW supporting construction pile body and waterproof roll layer The technology of separation layer " improves foundation pit main structure side wall waterproof effect.
Embodiment two:
Embodiment two has lacked one added between SMW supporting construction pile body and waterproof roll layer compared with embodiment one Layer low ratio foamed polyethylene benzene plate separation layer 4.
Embodiment three:
Embodiment three has lacked the rubber ring 24 outside Grouting Pipe 23 compared with embodiment one.In this case, working as foundation pit SMW branch After the completion of the main structure construction of protection structure 2, fashioned iron 21 is extracted, slip casing by pressure is carried out to Grouting Pipe 23 after the extraction of fashioned iron 21, Slurries are cement slurry, and slurries overflow inside Grouting Pipe 23 along extravasating hole 231, under the action of interior pressure along landing surface knot Structure generates filling, infiltration, densification, splitting flowing, to reach the gap after filling section steel 21 is extracted, cement earth pile is left in raising Body anti-permeability performance purpose.
Example IV:
The utility model also provides a kind of foundation pit SMW supporting construction for improving waterproof performance comprising multiple SMW pile bodies 22, Grouting Pipe 23 is provided in each SMW pile body 22, Grouting Pipe 23 is equipped with extravasating hole 231, is enclosed with rubber outside Grouting Pipe 23 Cushion rubber 24 is full of cement slurry in Grouting Pipe 23 and in the cavity between Grouting Pipe 23 and SMW pile body 22.Foundation pit SMW supporting The structure of Grouting Pipe 23 in structure is identical as the associated description in above-described embodiment, no longer elaborates here.
Foundation pit SMW supporting construction in the example IV can not also include rubber ring 24.
It is to be illustrated so that each fashioned iron of correspondence buries two Grouting Pipes 23 as an example, but this is practical in above-described embodiment It is novel to be not limited thereto, each fashioned iron embedded one or more root Grouting Pipes 23 can also be corresponded to and realize this reality to reach With novel purpose.
Although the utility model has been described by way of example and in terms of the preferred embodiments, embodiment does not limit the utility model.Not It is detached from the spirit and scope of the utility model, any equivalent change or retouch done also belongs to the guarantor of the utility model Protect range.Therefore the protection scope of the utility model should be based on the content defined in the claims of this application.

Claims (7)

1. a kind of structure for improving foundation pit side-wall waterproof performance, which is characterized in that the knot for improving foundation pit side-wall waterproof performance Structure includes:
Structure side wall (1), waterproof roll layer (5), sand finish layer (3) and foundation pit SMW supporting construction in sequentially connected foundation pit (2);
The foundation pit SMW supporting construction (2) includes: multiple SMW pile bodies (22), the slip casting being arranged in each SMW pile body (22) It manages (23);Multiple extravasating holes (231) are set on the Grouting Pipe (23);In the Grouting Pipe (23) and Grouting Pipe (23) with Filled with cement slurry in cavity between SMW pile body (22).
2. a kind of structure for improving foundation pit side-wall waterproof performance according to claim 1, which is characterized in that in the waterproof Low ratio foamed polyethylene board separation layer (4) is additionally provided between coiled material layer (5) and the sand finish layer (3).
3. a kind of structure for improving foundation pit side-wall waterproof performance according to claim 1 or 2, which is characterized in that the note Rubber ring (24) are wrapped in outside slurry pipe (23).
4. a kind of structure for improving foundation pit side-wall waterproof performance according to claim 1, which is characterized in that the Grouting Pipe (23) inner side slot of the burial place close to every fashioned iron of foundation pit SMW supporting construction.
5. a kind of foundation pit SMW supporting construction for improving waterproof performance, which is characterized in that the foundation pit SMW supporting construction includes:
Multiple SMW pile bodies (22), the Grouting Pipe (23) being arranged in each SMW pile body (22);It is arranged on the Grouting Pipe (23) Multiple extravasating holes (231);It is filled in the Grouting Pipe (23) and in the cavity between Grouting Pipe (23) and foundation pit SMW pile body (22) There is cement slurry.
6. a kind of foundation pit SMW supporting construction for improving waterproof performance according to claim 5, which is characterized in that the note Rubber ring (24) are wrapped in outside slurry pipe (23).
7. a kind of foundation pit SMW supporting construction for improving waterproof performance according to claim 5 or 6, which is characterized in that described Inner side slot of the burial place of Grouting Pipe (23) close to every fashioned iron of foundation pit SMW supporting construction.
CN201821125826.0U 2018-07-16 2018-07-16 Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance Expired - Fee Related CN208533543U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821125826.0U CN208533543U (en) 2018-07-16 2018-07-16 Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821125826.0U CN208533543U (en) 2018-07-16 2018-07-16 Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance

Publications (1)

Publication Number Publication Date
CN208533543U true CN208533543U (en) 2019-02-22

Family

ID=65387979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821125826.0U Expired - Fee Related CN208533543U (en) 2018-07-16 2018-07-16 Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance

Country Status (1)

Country Link
CN (1) CN208533543U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319314A (en) * 2022-01-24 2022-04-12 信息产业部电子综合勘察研究院 Construction method for constructing large-thickness collapsible loess foundation by utilizing profile steel cement soil mixing wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319314A (en) * 2022-01-24 2022-04-12 信息产业部电子综合勘察研究院 Construction method for constructing large-thickness collapsible loess foundation by utilizing profile steel cement soil mixing wall

Similar Documents

Publication Publication Date Title
CN204112308U (en) A kind of simple and easy sleeve valve grouting device based on bowlder stone, Thief zone coefficient stratum
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN102606176B (en) Collapsible loess tunnel construction method
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN103924987B (en) A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof
CN102286984A (en) Water-stop curtain and construction method thereof
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN104988907A (en) Construction method of concrete pile
CN105484269B (en) Foundation pit enclosure structure seepage prevention and treatment construction method under blasting condition
CN107023026A (en) A kind of sealing bottom type caisson wall and construction method
CN204530730U (en) The novel closed cutting off water system of a kind of water rich strata foundation ditch
CN202194149U (en) Waterproof curtain
CN112761166A (en) Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN105731978A (en) Grouting slurry for reinforcing tunnel face of jacking culvert of fine-sand layer and grouting method
CN107653872A (en) The rigid joint of ultra-deep ground-connecting-wall integrates water-stopping system and its construction method
CN206800431U (en) A kind of sealing bottom type caisson wall
CN208533543U (en) Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance
CN102995647A (en) Underground water control method used for grouting and seepage insulation of pile hole
CN102787608A (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN105350544B (en) For water-stop curtain and its construction method containing block stone region
CN108277815A (en) The cofferdam structure and its construction method constructed for water intaking header structure in river
CN111379267A (en) Water plugging method for solving water gushing at bottom of foundation pit
CN206655716U (en) A kind of tunnel drainage structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190222