- template
- bench
- marking time
- fixed
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model provides a non - design, can all rotary die plate bodys system for bench is prefabricated solves the longer problem of stair bench production cycle at the construction field (site), including the fixed die block of level, the vertical side form board of placing, the template of marking time and the end mould that corresponds with bench both ends, the template of marking time have the multiunit, the template of marking time is formed by the concatenation of two mutually perpendicular's two rectangular form templates, each group marks time the template next -door neighbour and arranges the structure of marking time that forms the bench, the side form board be platelike structure, each group that the next -door neighbour arranged marks time concave, the umbo that the template formed the cockscomb structure and constructs, and recess that the template of marking time lateral surface formed is equipped with the fixed part respectively, side form board and mark time and be equipped with split bolt between the template, the utility model discloses realize that the bench is prefabricated in advance at the construction field (site), realization batch production, concrete placement and outward appearance shaping quality can be guaranteed prior to major structure preparation in batches in advance at the construction field (site) to the bench, it is extravagant to reduce labour's input and material, reduces construction cost.
Description
Technical field
The utility model is related to the prefabricated field of stair bench, is more particularly to used for the prefabricated non-type of bench, can have enough to meet the need
Template system.
Background technology
Architectural stair is a kind of special structural elements in building, and its shape and structure is complex, and dimensional requirement is more smart
Really.Currently, commonly used reinforced concrete cast-in-situ bench in architectural engineering, this kind of bench its formwork erection when being cast is multiple
Miscellaneous, and easily affected by outside environmental elements when formwork erection and casting, bench concrete appearance Forming Quality is difficult to protect
Card, the bench after simultaneously casting needs the long period to cannot be used for transport channel before carrying out maintenance, and form removal, and this is in certain journey
Duration be have impact on degree;Next to that carrying out bench in factory prefabricated, batch production prefabricated bench production efficiency is high, and bench makes and is subject to
External environment impact is easily controllable compared with primary structural component quality, but the input such as original equipment, factory building and operation cost are higher, are not having
On the premise of mandatory popularization policy or subsidy, prefabricated components factory quantity and scale can not meet existing requirement of engineering.
Utility model content
For above-mentioned situation, for overcoming the defect of prior art, the purpose of the utility model is exactly to provide one kind for ladder
The prefabricated non-type of section, template system can be had enough to meet the need it is therefore intended that solve stair bench fabrication cycle at the construction field (site) longer and
The late maintaining time is longer, makes more difficult problem.
Its technical scheme is, including the fixing bed die of level, the side template vertically placed, template of marking time, and with bench two
Hold corresponding end mould;Described template of marking time has multigroup, and template of marking time is formed by two orthogonal two strip template splicings,
Each group mark time template arranged adjacent formed bench tread structure;Described side template is platy structure;The each group of arranged adjacent
Template of marking time forms jagged concave, convex structure, and the recess that template of marking time lateral surface is formed is respectively equipped with fixed part, fixed part
It is provided with two fixed arms, two fixed arms are affixed to merge with two templates of template recess of marking time respectively and are detachably fixed with template of marking time
Connect, each fixed arm is detachably fixed the fix bar connecting same level setting respectively, is fixedly connected in same fix bar
Fixed part forms the fixed system to template of marking time, and described fixed system has multiple and along template of marking time length direction cloth
Put;The lateral surface of described side template is provided with the multiple fix bars corresponding with template of marking time, the corresponding fix bar of side template
Be provided with wooden a tree, used in making timber for boats and side template between, between side template and wooden a tree, used in making timber for boats, be detachably fixed between wooden a tree, used in making timber for boats and fix bar and be connected, side template interior
Be provided with interval between the medial surface that side and template splicing of marking time are formed, this interval be respectively arranged at two ends with end mould, end mould outer
Be provided with locating rod at side, described locating rod is detachably fixed with fix bar and is connected, two ends mould and side template, template of marking time it
Between form the chamber that pours for pouring, described pour chamber only upper end open, side template and marking time is provided with to drawing spiral shell between template
Bolt.
Described bed die is provided with the concave, convex shape structure corresponding with bench, and bed die is fixed by screws on fixed base,
Pedestal is provided with the standing screw for matching with split bolt.
Described fixed part is made up of the angle bar of two vertical weldings, and the bottom surface of two angle bar is respectively equipped with through hole, and angle bar passes through
Wood screw passes through through hole and template of marking time to form described being detachably fixed to be connected, between the corresponding fixed part of adjacent template of marking time
It is provided with vertical interval, forms the structure of two adjacent fixed part stackings, described fix bar is located between the fixed part of stacking, Gu
Fixed pole is provided with location hole, forms described being detachably fixed by U-bolt and be connected between fix bar and the fixed part of stacking.
Described fix bar one end tilts to be provided with a resigning portion, and the other end of fix bar is horizontal ends, resigning portion and fixation
Angle between bar and bench upper and lower end and an angle of marking time are adapted, positioned at pour its resigning portions of fix bar of chamber both sides with
Horizontal ends are corresponding, and horizontal ends are provided with bolt hole, and horizontal ends are fixedly connected with the railing of an inclination by angle bar, described hurdle
Bar is be arranged in parallel with resigning portion, and described locating rod is angle bar, and locating rod is fixedly connected with resigning portion and railing by bolt.
It is prefabricated in advance at the construction field (site) that the utility model realizes bench, realizes batch production, bench can be prior to agent structure
Shift to an earlier date batch making at the construction field (site), compared with traditional cast-in-place bench, ensure that concreting and outward appearance Forming Quality, subtract
Few labour puts into and waste of material, reduces construction cost, reduces live building waste discharge;Prefabricated bench produces with batch production
Compare, reduce equipment and place puts into, save component conveying process, reduce cost of transportation;Form bracing system makes work simultaneously
Skill is simple, and to different bench strong adaptabilities, it is convenient that plank sheathing is changed, and form bracing system is steel construction, using conventional type steel
Make, processing technology is simple, non-type design several bench it is adaptable to difference is marked time, and can be finely adjusted according to size of marking time,
Bench is marked time and is adopted plank sheathing, and it is convenient partly or wholly to change, and bench concrete is poured using common process, need not carry out steam
The complicated procedures of forming such as maintenance.Bench concrete can avoid high temperature, the heavy rain period selects a good opportunity and pours as needed, using Field Force, equipment
Build, natural curing of watering after the completion of pouring.
Brief description
Fig. 1 is the schematic diagram of the utility model embodiment one.
Fig. 2 is fix bar, fixed part, the cooperation schematic diagram of U-bolt.
Fig. 3 is the enlarged diagram of part A in Fig. 1.
Fig. 4 is use schematic diagram of the present utility model.
Specific embodiment
Below in conjunction with accompanying drawing, specific embodiment of the present utility model is described in further detail.
As shown in Figures 1 to 4, for the prefabricated non-type of bench, embodiment that template system can be had enough to meet the need, solid including level
Fixed bed die 1, the side template 2 vertically placed, template of marking time 3, and end corresponding with bench two ends mould 4;Bed die 1, side template 2,
Template of marking time 3 and end mould 4 adopt wooden black template to cut out saw, and its size and size are selected according to the design size of prefabricated bench
Select, described bed die 1 is provided with the concave, convex shape structure corresponding with bench, bed die 1 is fixed by screws on fixed base 10,
Pedestal 10 is provided with the standing screw 11 for matching with split bolt 17, and described template 3 of marking time has multigroup, template of marking time
3 are formed by two orthogonal two strip template splicings, each group mark time template 3 arranged adjacent formed bench tread structure,
Template of marking time 3 is used for forming marking time of prefabricated bench;Described side template 2 is platy structure, and side template 2 acts on prefabricated bench
The planar structure at the back side at;The each group of arranged adjacent template 3 of marking time forms jagged concave, convex structure, outside template of marking time 3
The recess that face is formed is respectively equipped with fixed part, and fixed part is provided with two fixed arms 5, and described fixed part is by the angle of two vertical weldings
Iron is constituted, and the bottom surface of two angle bar is respectively equipped with through hole, angle bar passes through through hole by wood screw and template 3 of marking time formed described can
Dismounting is fixedly connected, and adjacent marking time is provided with vertical interval between the corresponding fixed part of template 3, forms two adjacent fixed part stackings
Structure, described fix bar 6 is located between the fixed part of stacking, and fix bar 6 is provided with location hole, fix bar 6 and stacking
Between fixed part, the described fixation being detachably fixed connection, being fixedly connected in same fix bar 6 is formed by U-bolt 12
Portion forms the fixed system to template 3 of marking time, and described fixed system has multiple and along template 3 of marking time length direction arrangement;
The lateral surface of described side template 2 is provided with the multiple fix bars 6 corresponding with template 3 of marking time, the corresponding fix bar of side template 2
It is provided with wooden a tree, used in making timber for boats 7, between side template 2 and wooden a tree, used in making timber for boats 7, detachably solid by wood screw between wooden a tree, used in making timber for boats 7 and fix bar 6 between 6 and side template 2
It is provided with interval, the two ends at this interval are divided between the medial surface that fixed connection, the medial surface of side template 2 and template 3 of marking time are spliced to form
It is not provided with end mould 4, side template 2 and mark time and be provided with split bolt 17 between template 3, in side template 2, template of marking time 3 outside respectively
Setting vertically place to drawing steel pipe 16, pour chamber 18 both sides to drawing steel pipe 16 to be attached by split bolt 17, realization
Clamping to side template 2, template of marking time 3;Described fix bar 6 one end tilts to be provided with a resigning portion 13, the other end of fix bar 6
For horizontal ends 14, the angle between resigning portion 13 and fix bar 6 and bench upper and lower end and an angle of marking time are adapted, positioned at pouring
Its resigning portion 13 of fix bar 6 building chamber 18 both sides is corresponding with horizontal ends 14, and horizontal ends 14 are provided with bolt hole, and horizontal ends 14 are led to
Cross the railing 15 that angle bar is fixedly connected with an inclination, described railing 15 is be arranged in parallel with resigning portion 13, and described locating rod 8 is
Angle bar, locating rod 8 is fixedly connected with resigning portion 13 and railing 15 by bolt, is provided with locating rod 8, institute at the lateral surface of end mould 4
The locating rod 8 stated is detachably fixed with fix bar 6 and is connected, and is formed and be used for pouring between two ends mould 4 and side template 2, template of marking time 3
Pour chamber 18, described pours chamber 18 only upper end open.
A kind of non-type prefabricated for bench, the construction method embodiment that can have enough to meet the need template system include following step
Suddenly:
A, determined according to the size of architectural design bench and need the size of prefabricated bench, the size according to prefabricated bench cuts out saw
Bed die 1, template of marking time 3, side template 2 and end mould 4, template used adopts wooden black template;
B, making pedestal 10, pedestal 10 can be poured using concrete, for considering split bolt 17, at the bottom of pedestal 10
Portion arranges standing screw 11, and bed die 1 is fixed by screws on the upper surface of pedestal 10;
C, template 3 of marking time is carried out being spliced to form the concave, convex structure marked time, template of marking time 3 is vertically placed and fixed temporarily,
Fixation temporarily can adopt gluing;
D, by multiple fixed parts along same level every step be fixed on mark time template 3 lateral surface formation depressed part at, will
One fix bar 6 is placed on the horizontal plane that above-mentioned multiple fixed part is formed, and puts and set another group and fix on this fix bar 6 upper surface
Portion, this group fixed part is fixedly connected equally every step arrangement and with the depressed part of template 3 lateral surface formation of marking time, and forms adjacent stepping on
The fixed part not structure in same level of step template 3 recess, and fix bar 6 is located at the knot between two-layer fixed part
Structure, be detachably fixed between fix bar 6 and two-layer fixed part be connected formation one fixed system, described fixed system have multiple and
Length direction arrangement along template 3 of marking time;
E, the corresponding fix bar 6 of template 3 of marking time horizontal ends 14 connect railing 15, the template of marking time of railing 15 corresponding position
3 are fixed with end mould 4 temporarily, and what railing 15 was corresponding mark time, and template 3 fits, the two ends of railing 15 pass through respectively angle bar with solid
The horizontal ends 14 of fixed pole 6 are detachably fixed connection, and the fixation of template of so far marking time 3 system completes;
F, side template 2 is vertically fixed temporarily, the lateral surface of side template 2 is detachably fixed connection spaced wood a tree, used in making timber for boats 7,
Wooden a tree, used in making timber for boats 7 outer end is arranged in a vertical direction and the corresponding fix bar 6 of fix bar 6 in template 3 system of marking time, and side template 2 is corresponding solid
The horizontal ends 14 of fixed pole 6 connect railing 15, and the side template 2 of railing 15 corresponding position is fixed with end mould 4 temporarily, and railing 15 is corresponding
Side template 2 fit, the two ends of railing 15 are detachably fixed with the horizontal ends 14 of fix bar 6 by angle bar respectively and are connected, extremely
The fixation of this side template 2 system completes;
G, bed die 1 of marking time, template of marking time 3, side template 2 and end mould 4 are cleaned out and brushing releasing agent;
H, by marking time, template 3 system lifts on the pedestal 10 being located to bed die 1 and fixes temporarily, according to arrangement of reinforcement blanking simultaneously
Assembling reinforcement, operates during colligation on pedestal 10, in this step, needs to arrange pre-buried pin shaft hole, hole for hoist, takes off according to design
Mould suspension hook, each hole adopts PVC when reserving, the two ends Continuous pressing device for stereo-pattern of tubing prevents from entering during concreting;Or adopt
Tub(60mm×60mm)Preformed hole, is temporarily fixed on two side templates 2 with wood screw, after concreting is complete, takes out
Wood screw simultaneously chisels out tub;
I, side template 2 system is lifted on the pedestal 10 being located to bed die 1, and side template 2 body will be realized by locating rod 8
System, being fixedly connected of template of marking time 3 system;
J, be respectively provided with side template 2 system, template of marking time 3 system vertical placement to drawing steel pipe 16, pour chamber 18
Both sides to drawing steel pipe 16 to be attached by split bolt 17, realize the clamping to side template 2 system, template of marking time 3 system,
Side template 2 system, template of marking time 3 system are formed with end mould 4 and pour chamber 18;
K, pour to pouring chamber 18, during for avoiding pouring, concreting, to pouring outside chamber 18, is pouring chamber 18
Upper end open at be provided with the baffle plate 19 of two relative tilts, two baffle plate 19 lower end connects with pouring chamber 18, between the baffle plate 19 of upper end two
Distance be gradually increased, to prefabricated bench natural curing after pouring.
It is prefabricated in advance at the construction field (site) that the utility model realizes bench, realizes batch production, bench can be prior to agent structure
Shift to an earlier date batch making at the construction field (site), compared with traditional cast-in-place bench, ensure that concreting and outward appearance Forming Quality, subtract
Few labour puts into and waste of material, reduces construction cost, reduces live building waste discharge;Prefabricated bench produces with batch production
Compare, reduce equipment and place puts into, save component conveying process, reduce cost of transportation;Form bracing system makes work simultaneously
Skill is simple, and to different bench strong adaptabilities, it is convenient that plank sheathing is changed, and form bracing system is steel construction, using conventional type steel
Make, processing technology is simple, non-type design several bench it is adaptable to difference is marked time, and can be finely adjusted according to size of marking time,
Bench is marked time and is adopted plank sheathing, and it is convenient partly or wholly to change, and bench concrete is poured using common process, need not carry out steam
The complicated procedures of forming such as maintenance.Bench concrete can avoid high temperature, the heavy rain period selects a good opportunity and pours as needed, using Field Force, equipment
Build, natural curing of watering after the completion of pouring.
Claims (4)
1. it is used for the prefabricated non-type of bench, template system can be had enough to meet the need, including the bed die that level is fixing(1), the vertical side placed
Template(2), template of marking time(3), and end corresponding with bench two ends mould(4)It is characterised in that described template of marking time(3)Have
Multigroup, template of marking time(3)Formed by two orthogonal two strip template splicings, each group is marked time template(3)Arranged adjacent shape
Become the tread structure of bench;Described side template(2)For platy structure;The each group of arranged adjacent is marked time template(3)Form sawtooth
The concave, convex structure of shape, template of marking time(3)The recess that lateral surface is formed is respectively equipped with fixed part, and fixed part is provided with two fixed arms
(5), two fixed arms(5)Respectively with template of marking time(3)Two templates of recess are affixed merging and template of marking time(3)It is detachably fixed
Connect, each fixed arm(5)It is detachably fixed the fix bar connecting same level setting respectively(6), it is fixedly connected on same fixation
Bar(6)On fixed part formed to template of marking time(3)Fixed system, described fixed system has multiple and along marking time template
(3)Length direction arrangement;Described side template(2)Lateral surface be provided with and mark time template(3)Locate corresponding multiple fixations
Bar(6), side template(2)Corresponding fix bar(6)With side template(2)Between be provided with wooden a tree, used in making timber for boats(7), side template(2)With wooden a tree, used in making timber for boats(7)
Between, wooden a tree, used in making timber for boats(7)With fix bar(6)Between be detachably fixed connection, side template(2)Medial surface and template of marking time(3)Splicing shape
Become medial surface between be provided with interval, this interval be respectively arranged at two ends with end mould(4), hold mould(4)Lateral surface at be provided with positioning
Bar(8), described locating rod(8)With fix bar(6)It is detachably fixed connection, two ends mould(4)With side template(2), template of marking time
(3)Between formed and pour chamber for pour(18), described pours chamber(18)Only upper end open, side template(2)With mould of marking time
Plate(3)Between be provided with split bolt(17).
2. the non-type prefabricated for bench according to claim 1, template system can be had enough to meet the need it is characterised in that described
Bed die(1)It is provided with the concave, convex shape structure corresponding with bench, bed die(1)It is fixed by screws in fixed base(10)On, platform
Seat(10)Be provided with for split bolt(17)The standing screw matching(11).
3. the non-type prefabricated for bench according to claim 1, template system can be had enough to meet the need it is characterised in that described
Fixed part be made up of the angle bar of two vertical weldings, the bottom surface of two angle bar is respectively equipped with through hole, angle bar pass through wood screw pass through logical
Hole and template of marking time(3)What formation was described is detachably fixed connection, adjacent template of marking time(3)It is provided with perpendicular between corresponding fixed part
To interval, form the structure of two adjacent fixed parts stackings, described fix bar(6)It is located between the fixed part of stacking, fixing
Bar(6)It is provided with location hole, fix bar(6)Pass through U-bolt and the fixed part of stacking between(12)Detachable described in being formed
It is fixedly connected.
4. the non-type prefabricated for bench according to claim 1, template system can be had enough to meet the need it is characterised in that described
Fix bar(6)One end tilts to be provided with a resigning portion(13), fix bar(6)The other end be horizontal ends(14), resigning portion(13)
With fix bar(6)Between angle and bench upper and lower end and an angle of marking time be adapted, positioned at pouring chamber(18)The fixation of both sides
Bar(6)Its resigning portion(13)With horizontal ends(14)Corresponding, horizontal ends(14)It is provided with bolt hole, horizontal ends(14)By angle bar
It is fixedly connected with the railing of an inclination(15), described railing(15)With resigning portion(13)It is arranged in parallel, described locating rod(8)
For angle bar, locating rod(8)By bolt and resigning portion(13)And railing(15)It is fixedly connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620837202.6U CN205928989U (en) | 2016-08-04 | 2016-08-04 | A non - design, can all rotary die plate bodys system for bench is prefabricated |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620837202.6U CN205928989U (en) | 2016-08-04 | 2016-08-04 | A non - design, can all rotary die plate bodys system for bench is prefabricated |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205928989U true CN205928989U (en) | 2017-02-08 |
Family
ID=57924335
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620837202.6U Withdrawn - After Issue CN205928989U (en) | 2016-08-04 | 2016-08-04 | A non - design, can all rotary die plate bodys system for bench is prefabricated |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205928989U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108818894A (en) * | 2018-08-03 | 2018-11-16 | 上海住信住宅工业有限公司 | A kind of precast stair mold |
-
2016
- 2016-08-04 CN CN201620837202.6U patent/CN205928989U/en not_active Withdrawn - After Issue
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108818894A (en) * | 2018-08-03 | 2018-11-16 | 上海住信住宅工业有限公司 | A kind of precast stair mold |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106113230B (en) | The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need | |
CN207954218U (en) | A kind of folded assembling die for beating precast concrete laminated floor slab | |
CN105220619B (en) | A kind of method of quick manufacture two-wire nose circle solid pier | |
CN205935641U (en) | Template formwork system of aluminum alloy shear force wall | |
CN103774561B (en) | The job execution of speedway prefabricated small box girder frock method streamlined | |
CN204019724U (en) | Make the mold of prefabricated case beam framework of steel reinforcement | |
CN107460889A (en) | Integral movable support formwork in underground comprehensive pipe gallery construction and construction method thereof | |
CN205928989U (en) | A non - design, can all rotary die plate bodys system for bench is prefabricated | |
CN106285002A (en) | Cast-in-place walls difference of height tool-type hoisting die construction method | |
CN207959244U (en) | Prefabricated assembling type reinforced frame raft foundation alter-pouring strips mould plate | |
CN204221939U (en) | A kind of precast concrete cable channel cover plate mold system | |
CN105804396B (en) | A kind of non-type, template system precast stair bench and construction can be had enough to meet the need | |
CN207436503U (en) | Efficient construction of precast floorslab hangs membrane module | |
CN205955197U (en) | A fixing device that be used for prefabricated non - design of bench, can all rotary die boards | |
CN204826427U (en) | Two accuse precast concrete cushions of floor cover to reinforcement | |
CN206941968U (en) | Reinforcing bar limiting card with the upper oblique bayonet socket being parallel to each other | |
CN207469596U (en) | A kind of beam column outer rim is exempted to tear concrete mold open | |
CN102121312A (en) | Construction process for concrete bargeboard in pseudo-classic architecture | |
CN205976477U (en) | Formula of sinking bathroom hangs mould device | |
CN214531520U (en) | Controller for thickness of floor slab and thickness of protective layer of floor slab reinforcing steel bar | |
CN105984036A (en) | Bubble control technique for producing PC (polycarbonate) boards with modular molds | |
CN108908663A (en) | A kind of Novel interior wall plate formwork erection and its application method | |
CN209397710U (en) | Novel pre-fabricated one | |
CN207920076U (en) | The stair tread formwork that both sides are provided with shear wall installs device | |
CN108590042B (en) | Multifunctional stirrup for controlling thickness of steel bar protection layer and floor slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20170208 Effective date of abandoning: 20180213 |
|
AV01 | Patent right actively abandoned |