CN108346001A - A kind of steel tower regular visit project order method of adjustment and system - Google Patents

A kind of steel tower regular visit project order method of adjustment and system Download PDF

Info

Publication number
CN108346001A
CN108346001A CN201810137471.5A CN201810137471A CN108346001A CN 108346001 A CN108346001 A CN 108346001A CN 201810137471 A CN201810137471 A CN 201810137471A CN 108346001 A CN108346001 A CN 108346001A
Authority
CN
China
Prior art keywords
project
matrix
inspection
steel tower
regular visit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810137471.5A
Other languages
Chinese (zh)
Inventor
严军荣
卢玉龙
江雅芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Houbo Technology Co Ltd
Original Assignee
Hangzhou Houbo Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Houbo Technology Co Ltd filed Critical Hangzhou Houbo Technology Co Ltd
Priority to CN201810137471.5A priority Critical patent/CN108346001A/en
Publication of CN108346001A publication Critical patent/CN108346001A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C1/00Registering, indicating or recording the time of events or elapsed time, e.g. time-recorders for work people
    • G07C1/20Checking timed patrols, e.g. of watchman

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of steel tower regular visit project order method of adjustment and systems.Its system includes generating steel tower inspection project matrix module, read extraordinary maintenance task and generating project matching matrix module, adjustment regular visit project order module.Steel tower inspection project matrix is generated according to the project order of steel tower regular visit task;Steel tower extraordinary maintenance record is read, the inspection project by comparing regular visit obtains the matching value of inspection project with the Maintenance Significant Items in extraordinary maintenance record, generates project matching matrix;Regular visit task oriental matrix is calculated according to steel tower Maintenance Significant Items matrix and project matching matrix, element in regular visit task oriental matrix is ranked up, and then adjusts regular visit project order.The method and system of the present invention solve the technical issues of emergency maintenance project cannot be adjusted to the regular visit project preferentially executed.

Description

A kind of steel tower regular visit project order method of adjustment and system
Technical field
The invention belongs to communication iron tower maintenance technology fields, are adjusted more particularly to a kind of steel tower regular visit project order Method and system.
Background technology
Communication iron tower is mainly by manually carrying out regular visit and extraordinary maintenance at present.Regular visit is usually according to fixed suitable Sequence executes inspection project, is unable to the emergency maintenance project of priority processing steel tower.There is presently no adjustment steel tower regular visit projects The technical solution of sequence.A kind of steel tower regular visit project order method of adjustment and system are proposed thus.
Invention content
The regular visit that the technical problem to be solved by the present invention is to cannot be adjusted to preferentially to execute by emergency maintenance project The problem of project, proposes a kind of steel tower regular visit project order method of adjustment and system.
The realization of the present invention relies on existing communication iron tower maintenance system, and communication iron tower maintenance is divided into regular visit and interim Safeguard two kinds, wherein regular visit refers to according to safeguarding that the inspection of project is periodically fixed in the monitoring time of index request, face When safeguard to refer to when emergency occurs in steel tower or when extreme weather occurs needs the extraordinary maintenance that carries out.
The steel tower regular visit project order of the present invention adjusts system, including generates steel tower inspection project matrix module, reads It takes extraordinary maintenance task and generates project matching matrix module, adjustment regular visit project order module.
Generate steel tower inspection project matrix module:The inspection project of steel tower regular visit is ranked up, identifies inspection item Mesh number amount is denoted as N, and inspection project is numbered successively with number from big to small, and number is indicated with i, generates the steel tower of 1 × N Inspection project matrix X.
It reads extraordinary maintenance task and generates project matching matrix module:Steel tower extraordinary maintenance record is read, comparison is passed through The inspection project of regular visit obtains the matching value of inspection project with the Maintenance Significant Items in extraordinary maintenance record, according to inspection project It is sequentially generated project matching matrix Y;
Wherein, the steel tower extraordinary maintenance is recorded as the extraordinary maintenance task record of steel tower in time T, and the time, T was set in advance It sets;The inspection project for comparing regular visit refers to judging that extraordinary maintenance task is remembered with the Maintenance Significant Items in extraordinary maintenance record With the presence or absence of the Maintenance Significant Items being equal with certain inspection project in record, with variable yiThe matching value of inspection project is indicated, if interim dimension There are the Maintenance Significant Items being equal with certain inspection project in shield task record, then inspection project matching value yi=1, the otherwise inspection Project matching value yi=0;The project matching matrix Y=diag (yi), matrix Y is the diagonal matrix of N × N.
Adjust regular visit project order module:It is calculated according to steel tower inspection project matrix X and project matching matrix Y regular Element in patrol task oriental matrix R, descending permutation matrix R, according to the corresponding inspection project tune of element in the matrix R after sequence Whole regular visit project order;
Wherein, the regular visit task that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y refers to Show matrix R, calculation formula R=XY.
Steel tower regular visit project order adjusts system block diagram, as shown in Figure 1.
The steel tower regular visit project order method of adjustment of the present invention is realized as follows:
Step 1 is ranked up the inspection project of steel tower regular visit, identify the inspection number of entry, be denoted as N, from greatly to Small that inspection project is numbered successively with number, number is indicated with i, generates the steel tower inspection project matrix X of 1 × N.
Step 2 reads steel tower extraordinary maintenance record, during the inspection project by comparing regular visit is recorded with extraordinary maintenance Maintenance Significant Items obtain the matching value of inspection project, generate project matching matrix Y according to inspection project order;
Wherein, the steel tower extraordinary maintenance is recorded as the extraordinary maintenance task record of steel tower in time T, and the time, T was set in advance It sets;The inspection project for comparing regular visit refers to judging that extraordinary maintenance task is remembered with the Maintenance Significant Items in extraordinary maintenance record With the presence or absence of the Maintenance Significant Items being equal with certain inspection project in record, with variable yiThe matching value of inspection project is indicated, if interim dimension There are the Maintenance Significant Items being equal with certain inspection project in shield task record, then inspection project matching value yi=1, the otherwise inspection Project matching value yi=0;The project matching matrix Y=diag (yi), matrix Y is the diagonal matrix of N × N.
Step 3 calculates regular visit task oriental matrix R according to steel tower inspection project matrix X and project matching matrix Y, Element in descending permutation matrix R, it is suitable according to the corresponding inspection project adjustment regular visit project of element in the matrix R after sequence Sequence;
Wherein, the regular visit task that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y refers to Show matrix R, calculation formula R=XY.
Steel tower regular visit project order method of adjustment flow chart, as shown in Figure 2.
The method and system of the present invention this have the advantage that:It is found from regular visit project and extraordinary maintenance task items Matched emergency maintenance project is adjusted to the forefront of regular visit project, for it is preferential execute emergency maintenance project provide according to According to.
Description of the drawings
Fig. 1 is the steel tower regular visit project order adjustment system block diagram of the present invention;
Fig. 2 is the steel tower regular visit project order method of adjustment flow chart of the present invention.
Specific implementation mode
It elaborates below to the preferred embodiment of the present invention.
The realization of the present invention relies on existing communication iron tower maintenance system, and communication iron tower maintenance is divided into regular visit and interim Safeguard two kinds, wherein regular visit refers to according to safeguarding that the inspection of project is periodically fixed in the monitoring time of index request, face When safeguard to refer to when emergency occurs in steel tower or when extreme weather occurs needs the extraordinary maintenance that carries out.The present invention passes through interim Safeguard that the project with regular visit compares, and adjusts the sequence of steel tower regular visit task.In the present embodiment, to somewhere triangle The regular visit project order adjustment system and method for tower are described.
The steel tower regular visit project order of the present invention adjusts system, including generates steel tower inspection project matrix module, reads It takes extraordinary maintenance task and generates project matching matrix module, adjustment regular visit project order module.
Generate steel tower inspection project matrix module:The inspection project of steel tower regular visit is ranked up, identifies inspection item Mesh number amount is denoted as N, and inspection project is numbered successively with number from big to small, and number is indicated with i, generates the steel tower of 1 × N Inspection project matrix X.In the present embodiment, index request is safeguarded according to existing triangle tower, the patrol plan totally 9 safeguarded, That is N=9, in order arrangement are followed successively by:Microwave antenna inspection, the inspection of tower part, it is antiseptic and rustproof check, structural bolts connection it is elastic Degree inspection, malformation and the inspection of yielding of foundation situation, steel tower verticality and height check, tower lamp inspection is looked into, steel tower ground connection inspection It looks into, surrounding enviroment and auxiliary device inspection are numbered and indicated with i with inspection project is numbered successively from 9 to 1, generation 1 × 9 Steel tower inspection project matrix X=(9,8,7,6,5,4,3,2,1).
It reads extraordinary maintenance task and generates project matching matrix module:The steel tower extraordinary maintenance is recorded as in time T The extraordinary maintenance task record of steel tower, the time, T was arranged in advance;The inspection project for comparing regular visit is recorded with extraordinary maintenance In Maintenance Significant Items refer to judging with the presence or absence of the Maintenance Significant Items that are equal with certain inspection project in extraordinary maintenance task record, with change Measure yiIndicate the matching value of inspection project, if there are the Maintenance Significant Items being equal with certain inspection project in extraordinary maintenance task record, Then inspection project matching value yi=1, otherwise inspection project matching value yi=0;The project matching matrix Y=diag (yi), Matrix Y is the diagonal matrix of N × N.In the present embodiment, time T is 3 months, and the extraordinary maintenance for reading the steel tower in nearly 3 months is appointed Business record, wherein extraordinary maintenance task totally 3 times, including extraordinary maintenance project be antenna case, screw tightness degree, steel tower knot Whether structure deform, verticality situation, tower lamp situation, is compared with regular visit project, obtains each inspection project matching value point It Wei not y9=y6=y5=y4=y3=1, y8=y7=y2=y1=0, the project that 9 × 9 are generated according to inspection project order matches square Battle array Y=diag (yi)=diag (1,0,0,1,1,1,1,0,0), matrix Y are diagonal matrix.
Adjust regular visit project order module:It is calculated according to steel tower inspection project matrix X and project matching matrix Y regular Element in patrol task oriental matrix R, descending permutation matrix R, according to the corresponding inspection project tune of element in the matrix R after sequence Whole regular visit project order;
Wherein, the regular visit task that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y refers to Show matrix R, calculation formula R=XY.In the present embodiment, the regular visit task oriental matrix R=XY of 1 × N is calculated =(9,0,0,6,5,4,3,0,0), element obtains (9,6,5,4,3,0,0,0,0) in descending permutation matrix R, according to each element pair The inspection project answered obtains the regular visit project order after project order adjusts:Microwave antenna inspection, structural bolts connection Tightness inspection, malformation and the inspection of yielding of foundation situation, steel tower verticality and height check, tower lamp inspection look into, tower part Inspection, antiseptic and rustproof inspection, the inspection of steel tower ground connection, surrounding enviroment and auxiliary device inspection.
The steel tower regular visit project order method of adjustment of the present invention is realized as follows:
Step 1 is ranked up the inspection project of steel tower regular visit, identify the inspection number of entry, be denoted as N, from greatly to Small that inspection project is numbered successively with number, number is indicated with i, generates the steel tower inspection project matrix X of 1 × N.This implementation In example, index request is safeguarded according to existing triangle tower, the patrol plan safeguarded totally 9, i.e. N=9 arrange successively in order For:Tightness inspection, malformation and the base of microwave antenna inspection, the inspection of tower part, antiseptic and rustproof inspection, structural bolts connection The inspection of plinth depression situation, steel tower verticality and height check, tower lamp inspection is looked into, steel tower is grounded inspection, surrounding enviroment and auxiliary device It checks, with inspection project is numbered successively from 9 to 1, number is indicated with i, generates 1 × 9 steel tower inspection project matrix X= (9,8,7,6,5,4,3,2,1)。
Step 2, the steel tower extraordinary maintenance are recorded as the extraordinary maintenance task record of steel tower in time T, and the time, T was set in advance It sets;The inspection project for comparing regular visit refers to judging that extraordinary maintenance task is remembered with the Maintenance Significant Items in extraordinary maintenance record With the presence or absence of the Maintenance Significant Items being equal with certain inspection project in record, with variable yiThe matching value of inspection project is indicated, if interim dimension There are the Maintenance Significant Items being equal with certain inspection project in shield task record, then inspection project matching value yi=1, the otherwise inspection Project matching value yi=0;The project matching matrix Y=diag (yi), matrix Y is the diagonal matrix of N × N.In the present embodiment, Time T is 3 months, reads the extraordinary maintenance task record of the steel tower in nearly 3 months, wherein extraordinary maintenance task totally 3 times, including Extraordinary maintenance project be antenna case, screw tightness degree, iron tower structure whether deform, verticality situation, tower lamp situation, with Regular visit project is compared, and it is respectively y to obtain each inspection project matching value9=y6=y5=y4=y3=1, y8=y7=y2 =y1=0,9 × 9 project matching matrix Y=diag (y are generated according to inspection project orderi)=diag (1,0,0,1,1,1,1, 0,0), matrix Y is diagonal matrix.
Step 3 calculates regular visit task oriental matrix R according to steel tower inspection project matrix X and project matching matrix Y, Element in descending permutation matrix R, it is suitable according to the corresponding inspection project adjustment regular visit project of element in the matrix R after sequence Sequence;
Wherein, the regular visit task that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y refers to Show matrix R, calculation formula R=XY.In the present embodiment, the regular visit task oriental matrix R=XY of 1 × N is calculated =(9,0,0,6,5,4,3,0,0), element obtains (9,6,5,4,3,0,0,0,0) in descending permutation matrix R, according to each element pair The inspection project answered obtains the regular visit project order after project order adjusts:Microwave antenna inspection, structural bolts connection Tightness inspection, malformation and the inspection of yielding of foundation situation, steel tower verticality and height check, tower lamp inspection look into, tower part Inspection, antiseptic and rustproof inspection, the inspection of steel tower ground connection, surrounding enviroment and auxiliary device inspection.
Certainly, those of ordinary skill in the art is it should be appreciated that above example is intended merely to illustrate this hair It is bright, and be not intended as limitation of the invention, as long as within the scope of the invention, all to the variation of above example, modification Protection scope of the present invention will be fallen into.

Claims (6)

1. a kind of steel tower regular visit project order adjusts system, it is characterised in that including generating steel tower inspection project matrix mould Block reads extraordinary maintenance task and generates project matching matrix module, adjustment regular visit project order module;
The generation steel tower inspection project matrix module:The inspection project of steel tower regular visit is ranked up, identifies inspection item Mesh number amount is denoted as N, and inspection project is numbered successively with number from big to small, and number is indicated with i, generates the steel tower of 1 × N Inspection project matrix X;
The reading extraordinary maintenance task and generation project matching matrix module:Steel tower extraordinary maintenance record is read, comparison is passed through The inspection project of regular visit obtains the matching value of inspection project with the Maintenance Significant Items in extraordinary maintenance record, according to inspection project It is sequentially generated project matching matrix Y;
The adjustment regular visit project order module:It is calculated according to steel tower inspection project matrix X and project matching matrix Y regular Element in patrol task oriental matrix R, descending permutation matrix R, according to the corresponding inspection project tune of element in the matrix R after sequence Whole regular visit project order.
2. steel tower regular visit project order according to claim 1 adjusts system, extraordinary maintenance task and life are read It is characterized in that at project matching matrix module, the steel tower extraordinary maintenance is recorded as the extraordinary maintenance task of steel tower in time T Record, the time, T was arranged in advance;Maintenance Significant Items during the inspection project for comparing regular visit is recorded with extraordinary maintenance refer to sentencing With the presence or absence of the Maintenance Significant Items being equal with certain inspection project in disconnected extraordinary maintenance task record, with variable yiIndicate inspection project Matching value, if there is the Maintenance Significant Items being equal with certain inspection project, the inspection project matching value in extraordinary maintenance task record yi=1, otherwise inspection project matching value yi=0;The project matching matrix Y=diag (yi), matrix Y is the diagonal of N × N Matrix.
3. steel tower regular visit project order according to claim 1 adjusts system, regular visit project order is adjusted Module is characterized in that, the regular visit task that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y Oriental matrix R, calculation formula R=XY.
4. a kind of steel tower regular visit project order method of adjustment, it is characterised in that include the following steps:
Step 1 is ranked up the inspection project of steel tower regular visit, identifies the inspection number of entry, is denoted as N, uses from big to small Number is successively numbered inspection project, and number is indicated with i, generates the steel tower inspection project matrix X of 1 × N;
Step 2 reads steel tower extraordinary maintenance record, the inspection project by comparing regular visit and the dimension in extraordinary maintenance record Shield project obtains the matching value of inspection project, and project matching matrix Y is generated according to inspection project order;
Step 3 calculates regular visit task oriental matrix R, descending according to steel tower inspection project matrix X and project matching matrix Y Element in permutation matrix R adjusts regular visit project order according to the corresponding inspection project of element in the matrix R after sequence.
5. steel tower regular visit project order method of adjustment according to claim 4, step 2 is characterized in that, described Steel tower extraordinary maintenance is recorded as the extraordinary maintenance task record of steel tower in time T, and the time, T was arranged in advance;The comparison is periodically patrolled The inspection project of inspection and the Maintenance Significant Items in extraordinary maintenance record refer to judge to whether there is in extraordinary maintenance task record and certain The equivalent Maintenance Significant Items of inspection project, with variable yiThe matching value for indicating inspection project, if existing in extraordinary maintenance task record The Maintenance Significant Items being equal with certain inspection project, then inspection project matching value yi=1, otherwise inspection project matching value yi=0; The project matching matrix Y=diag (yi), matrix Y is the diagonal matrix of N × N.
6. steel tower regular visit project order method of adjustment according to claim 4, step 3 is characterized in that, described The regular visit task oriental matrix R that 1 × N is calculated according to steel tower inspection project matrix X and project matching matrix Y is calculated public Formula is R=XY.
CN201810137471.5A 2018-02-10 2018-02-10 A kind of steel tower regular visit project order method of adjustment and system Withdrawn CN108346001A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810137471.5A CN108346001A (en) 2018-02-10 2018-02-10 A kind of steel tower regular visit project order method of adjustment and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810137471.5A CN108346001A (en) 2018-02-10 2018-02-10 A kind of steel tower regular visit project order method of adjustment and system

Publications (1)

Publication Number Publication Date
CN108346001A true CN108346001A (en) 2018-07-31

Family

ID=62959291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810137471.5A Withdrawn CN108346001A (en) 2018-02-10 2018-02-10 A kind of steel tower regular visit project order method of adjustment and system

Country Status (1)

Country Link
CN (1) CN108346001A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110969719A (en) * 2019-11-12 2020-04-07 深圳市科比特航空科技有限公司 Automatic inspection method, system, terminal equipment and storage medium

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130018691A1 (en) * 2011-07-15 2013-01-17 Hitachi, Ltd. Management system and management method
CN102981859A (en) * 2012-12-03 2013-03-20 广东欧珀移动通信有限公司 Method, device and mobile terminal for automatically adjusting icons
CN104050541A (en) * 2014-06-27 2014-09-17 国家电网公司 Maintenance cycle management system for grid equipment
CN106161088A (en) * 2016-07-01 2016-11-23 成都视达科信息技术有限公司 A kind of server automatic detecting method and system based on multithreading
CN106651731A (en) * 2016-12-25 2017-05-10 杭州博烁晟斐智能科技有限公司 Historical-data-based communication tower to-be-solved problem set generation method and system
CN106875084A (en) * 2016-12-28 2017-06-20 北京元心科技有限公司 Patrol and examine later stage task creation method and system
CN106934484A (en) * 2016-12-08 2017-07-07 国网浙江省电力公司 A kind of live O&M based on PDA day work planing method
CN106991538A (en) * 2017-04-11 2017-07-28 华北电力大学(保定) A kind of method for maintaining and device evaluated based on Wind turbines Degrees of Importance of Components

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130018691A1 (en) * 2011-07-15 2013-01-17 Hitachi, Ltd. Management system and management method
CN102981859A (en) * 2012-12-03 2013-03-20 广东欧珀移动通信有限公司 Method, device and mobile terminal for automatically adjusting icons
CN104050541A (en) * 2014-06-27 2014-09-17 国家电网公司 Maintenance cycle management system for grid equipment
CN106161088A (en) * 2016-07-01 2016-11-23 成都视达科信息技术有限公司 A kind of server automatic detecting method and system based on multithreading
CN106934484A (en) * 2016-12-08 2017-07-07 国网浙江省电力公司 A kind of live O&M based on PDA day work planing method
CN106651731A (en) * 2016-12-25 2017-05-10 杭州博烁晟斐智能科技有限公司 Historical-data-based communication tower to-be-solved problem set generation method and system
CN106875084A (en) * 2016-12-28 2017-06-20 北京元心科技有限公司 Patrol and examine later stage task creation method and system
CN106991538A (en) * 2017-04-11 2017-07-28 华北电力大学(保定) A kind of method for maintaining and device evaluated based on Wind turbines Degrees of Importance of Components

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110969719A (en) * 2019-11-12 2020-04-07 深圳市科比特航空科技有限公司 Automatic inspection method, system, terminal equipment and storage medium

Similar Documents

Publication Publication Date Title
US20120116696A1 (en) Systems, devices and methods for predicting power electronics failure
CN103792420B (en) Based on the anti-electricity-theft of load curve and supervision of power consumption method
CN106199276B (en) The intelligent diagnosis system and method for exception information in a kind of power information acquisition system
CN104392391A (en) Power grid running safety risk quantification method
CN104218676A (en) Intelligent warning system and method for power dispatching automation master station
JP2014154728A (en) Solar cell panel monitoring program, solar cell panel monitoring device and solar cell panel monitoring method
CN108923542A (en) A kind of VR system for power scheduling
CN103973663A (en) Method and device for dynamic threshold anomaly traffic detection of DDOS (distributed denial of service) attack
CN104299116A (en) Quantitative evaluation method for security risk of operation of power network
CN112152224A (en) Voltage sag treatment optimization method and system
CN109827077A (en) A kind of water flow leakage loss method for early warning, system, device and storage medium
CN104933272A (en) Power-stealing prevention analysis method and apparatus
CN108680798B (en) Lightning monitoring and early warning method and system
CN108197254B (en) A kind of data recovery method based on neighbour
CN103837777A (en) Method and system for power quality assessment of power supply system
CN107104848A (en) Information technology system monitoring method and device
CN109917184A (en) A kind of stealing detection method and system
CN108334962A (en) Steel tower patrol task list method of adjustment and system based on steel tower problem weight
CN103400224B (en) GIS device repair method and GIS device maintenance aid decision-making system
CN117691645A (en) Energy storage system for intelligent micro-grid
CN108346001A (en) A kind of steel tower regular visit project order method of adjustment and system
CN117375158A (en) Intelligent operation and maintenance method and system for vehicle retired battery pack echelon energy storage system
CN112418638A (en) Early warning system and early warning method for operation and maintenance risks of DC power supply system for station
CN110165674B (en) Active filter safety management system
CN108416511A (en) It is a kind of based on the patrol task method of adjustment and system of safeguarding duration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180731

WW01 Invention patent application withdrawn after publication