CN102493342A - 连续梁静载预压托架施工方法 - Google Patents
连续梁静载预压托架施工方法 Download PDFInfo
- Publication number
- CN102493342A CN102493342A CN2011103735970A CN201110373597A CN102493342A CN 102493342 A CN102493342 A CN 102493342A CN 2011103735970 A CN2011103735970 A CN 2011103735970A CN 201110373597 A CN201110373597 A CN 201110373597A CN 102493342 A CN102493342 A CN 102493342A
- Authority
- CN
- China
- Prior art keywords
- finish rolling
- deformed bar
- rolling deformed
- bracket
- joist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
本发明属于连续梁托架预压施工的技术领域,具体是一种连续梁静载预压托架施工方,解决现有托架预压影响施工进度,施工成本高的问题。步骤如下:预埋精轧螺纹钢筋,在托架顶面铺设前、后托梁;在前、后托梁的顶面安装底模系;在底模系顶面安装纵向、横向分配梁;将精轧螺纹钢筋的顶端通过连接器引入横向分配梁顶面以上;安装张拉系统;对精轧螺纹钢筋进行分级预压;预压后逐级卸载。本发明具有如下有益效果:有效地利用了连续梁挂篮的和梁体的相关材料作为加载荷载、传递力、分配力,操作方便简单,结构轻盈,拆装方便,施工循环周期短,能够实现托架快速安全预压;能够更加准确模拟托架的受力状态,操作更加安全可靠,经济效益更好。
Description
技术领域
本发明属于连续梁托架预压施工的技术领域,具体涉及一种连续梁静载预压托架施工方法。
背景技术
随着高速铁路与高速公路的迅猛发展,跨公路、跨铁路、跨河高桥墩连续梁逐渐增加。原有的托架预压的施工方法都是采用吊装砂袋方法进行预压,该施工方法有多方面缺点,首先预压过程中砂子和砂袋的用量较大,成本比较高,其次不能够很好的模拟混凝土浇筑时的真实荷载状况,最后施工周期比较长,一般吊装砂袋需要3天时间,卸载时同样需要2到3天时间。
发明内容
本发明为了解决现有托架预压主要通过砂袋进行预压,影响施工进度,而且施工成本高的问题,提供了一种连续梁静载预压托架施工方法。
本发明采用如下的技术方案实现:
一种连续梁静载预压托架施工方法,其特征在于步骤如下:
1)、预埋精轧螺纹钢筋
承台施工时,在承台内垂直对应于连续梁各部位的位置处预埋精轧螺纹钢筋,连续梁部位对应位置处的精轧螺纹钢筋的数量×85%精轧螺纹钢筋的最大抗拉力≥1.2倍连续梁部位的施工荷载,精轧螺纹钢筋底端采用锚垫板与螺母作为加强锚固点,
2)、在托架顶面铺设前托梁和后托梁;
3)、在前托梁和后托梁的顶面安装底模系;
4)、在底模系顶面安装纵向分配梁以及横向分配梁;
5)、精轧螺纹钢筋连接,将精轧螺纹钢筋的顶端通过连接器引入横向分配梁顶面以上;
6)、安装与精轧螺纹钢筋连接的张拉系统,张拉系统包括千斤顶、油泵、锚垫板、螺帽以及井字架;
7)、对精轧螺纹钢筋按照30%,70%,100%,120%进行分级预压;
8)、预压一天后,按照预压相反方向进行逐级卸载。
本发明具有如下有益效果:有效地利用了连续梁挂篮的和梁体的相关材料(挂篮前后托梁、挂篮底模系统、连续梁竖向预应力精轧螺纹钢筋、连续梁张拉用的油泵千斤顶)作为加载荷载、传递力、分配力,操作方便简单,结构轻盈,拆装方便,施工循环周期短(1~2天),能够实现托架快速安全预压;和普通砂袋托架预压施工方法相比:能够更加准确模拟托架的受力状态,操作更加安全可靠,经济效益更好。
附图说明
图1为本发明的静载托架预压组装图
图2为具体实施方式举例中的截面特性图
图3为具体实施方式举例中的荷载分布图
图4为具体实施方式举例中的锚点位置布置图
图中:1-托架,2-前托梁,3-后托梁,4-底模系,5-横向分配梁,6-纵向分配梁,7-锚垫板,8-井字架,9-千斤顶,10-螺母,11-精轧螺纹钢筋,12-承台,13-锚点。
具体实施方式
结合附图对本发明的具体实施方式作进一步说明。
一、连续梁静载预压托架施工方法,步骤如下:
1、预埋精轧螺纹钢筋
在承台12施工时,在承台12内按照托架预压锚点布置图(根据连续梁各部位在承台内垂直对应的位置设置,连续梁部位对应位置处的精轧螺纹钢筋的数量×85%精轧螺纹钢筋的最大抗拉力≥1.2倍连续梁部位的施工荷载,)进行精轧螺纹钢筋预埋,预埋时,在精轧螺纹钢筋11下部采用锚垫板7与螺母作为加强锚固点。托架预压锚点设计时,充分考虑托架受力分布,以保证更加准确模拟0号块混凝土浇筑时托架受力状态,且保证每根精轧螺纹钢筋受力基本一致。
2、前托梁、后托梁安装
吊装前托梁2、后托梁3(属于挂挂篮配件)时,检查前后托梁的有无变形、损伤、裂纹等现象。
3、底模系安装在前托梁和后托梁上
底模系安装(属于挂篮配件)时,充分考虑托架受力分布情况,底板下面一般控制在60cm,腹板下面一般控制在40cm,翼缘板下面一般控制在60cm。
4、纵、横向分配梁安装在底模系上
横向分配梁采用单根I32a工字钢,间距一般控制50cm左右。纵向分配梁采用双拼I32a工字钢,具体详见附图尺寸,间距与锚点布置图对应。
5、精轧螺纹钢筋连接
通过塔吊或者吊车将精轧螺纹钢筋(采用连续梁竖向精轧螺纹钢筋代用)通过PSB785精轧螺纹钢筋连接器进行连接到分配梁顶面一米,连接之前在精轧螺纹钢筋用红油漆做好标记,以保证每根精轧连接长度。在连接过程中,应该避免连接好的精轧螺纹松动。
6、安装张拉设备
张拉设备(包括井字架8、锚垫板、螺母、千斤顶、油泵),千斤顶和油表需经过校核。
7、张拉预压
张拉按照混凝土的浇筑顺序,由低到高,先底板处后腹板处最后翼缘板处,进行分级张拉,30%、50%、70%、100%、120%分级张拉,每级张拉完成后,持荷30分钟,并相应的测点测量托架变形量。变形观测点布置,每侧布置6个测点,测点布置在前后托梁上面左中右各3个点,并做好标记。
二、举例说明静载预压托架施工的设计过程
1、梁体荷载计算
1.1、零号块悬臂混凝土荷载计算
零号块梁体长12m,墩顶宽为4.8m,所有一侧悬臂端为(12-4.8)/2=3.6m。截面特性图详见附图2
(1)翼缘板混凝土重:P1=((0.26+0.3)÷2×0.55+(0.3+0.65)÷2×2.1)×3.6×2.6÷2.65=40.72KN/m;
(2)腹板混凝土重:P2=0.9×6.650×3.6×2.6÷0.9=622.44 KN/m;
(3) 顶底板混凝土重:P3=[(0.3×0.6+(0.3×0.9÷2)×2)×3.6+5.5×1×3.6+5.1×0.4×3.6] ×2.6÷5.5=136 KN/m。
1.2、零号块悬臂端模板、桁架小型机具荷载计算
模板、桁架及小型机具:P4=2.5KN/㎡
1.3、零号块悬臂端人员荷载计算
人员荷载:P5=2.5KN/㎡
详见荷载分布图,(附图3)
综上所述:零号块悬臂端总重量为208.42+15+10.8=234.22t。
1.4、零号块悬臂端荷载分布
(1)翼缘板荷载:P11= P1+ (P4+P5) ×3.6
=40.72+(2.5+2.5)×3.6
=58.72 KN/m
因此翼缘板重量为:Gy=58.72×2.65=155.6KN
(2)腹板荷载: P21= P2+ (P4+P5) ×3.6
=622.44+(2.5+2.5)×3.6
=640.44KN/m
因此腹板重量为:Gf=640.44×0.8=512.4KN
(3)顶底板荷载:P31= P3+ (P4+P5) ×3.6
=136+(2.5+2.5)×3.6
=154KN/m
因此底板板重量为:Gd=154×5.1=785.4KN
单侧悬臂端梁体重为:G=2×(Gy+ Gf)+ Gd
=2×(155.6+ 512.4)+785.4
=2121.4KN
2、 静载预压托架施工设计
张拉采用连续梁竖向精轧螺纹钢筋,直径为25mm的抗拉强度为785Mpa。利用85%的抗拉强度,因此每根精轧螺纹钢筋承受的最大拉力为Fmax=0.85×785×252×3.14/4=327.4KN。单侧悬臂端梁体总重量为2121.4KN,设计15个锚点,锚点位置详见布置图(附图4)。
3、静载预压托架施工过程
3.1、技术人员根据每根精轧螺纹承受的应力,分别计算出分级张拉的油表读数,并绘制张拉预压表格。详见附表1。
3.2、张拉按照混凝土的浇筑顺序,由低到高,先底板处后腹板处最后翼缘板处。分级进行张拉,共分5基进行张拉,分别为30%、50%、70%、100%、120%。
3.3、变形观测点设置在前后托梁的左中右各3个点。
3.4、每张拉完成一级持荷30分钟后,技术人员按照观测点进行变形观测,并随时观察托架的结构安全。荷载加载完毕后,每隔12小时对托架进行变形观测一次,预压24小时。
3.5、预压结束后,卸载顺序与加载顺序相反。
静载预压托架施工方法的优点是操作方便简单快捷,预压荷载控制准确,施工时效比较高,施工更加安全可靠。
Claims (1)
1.一种连续梁静载预压托架施工方法,其特征在于步骤如下:
1)、预埋精轧螺纹钢筋
承台施工时,在承台内垂直对应于连续梁各部位的位置处预埋精轧螺纹钢筋,连续梁部位对应位置处的精轧螺纹钢筋的数量×85%精轧螺纹钢筋的最大抗拉力≥1.2倍连续梁部位的施工荷载,精轧螺纹钢筋底端采用锚垫板与螺母作为加强锚固点;
2)、在托架顶面铺设前托梁和后托梁;
3)、在前托梁和后托梁的顶面安装底模系;
4)、在底模系顶面安装纵向分配梁以及横向分配梁;
5)、精轧螺纹钢筋连接,将精轧螺纹钢筋的顶端通过连接器引入横向分配梁顶面以上;
6)、安装与精轧螺纹钢筋连接的张拉系统,张拉系统包括千斤顶、油泵、锚垫板、螺帽以及井字架;
7)、对精轧螺纹钢筋按照30%,70%,100%,120%进行分级预压;
8)、预压一天后,按照预压相反方向进行逐级卸载。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103735970A CN102493342A (zh) | 2011-11-22 | 2011-11-22 | 连续梁静载预压托架施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011103735970A CN102493342A (zh) | 2011-11-22 | 2011-11-22 | 连续梁静载预压托架施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102493342A true CN102493342A (zh) | 2012-06-13 |
Family
ID=46185198
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011103735970A Pending CN102493342A (zh) | 2011-11-22 | 2011-11-22 | 连续梁静载预压托架施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102493342A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103174097A (zh) * | 2013-04-11 | 2013-06-26 | 新疆北新路桥集团股份有限公司 | 大跨径桥梁上部钢结构支撑预应力反张拉加载预压的方法 |
CN103184725A (zh) * | 2013-02-28 | 2013-07-03 | 湖北建科结构加固有限责任公司 | 框架梁等效减载加固法 |
CN104746438A (zh) * | 2015-01-28 | 2015-07-01 | 中国水利水电第五工程局有限公司 | 一种挂篮千斤顶预压方法 |
CN109235267A (zh) * | 2018-09-28 | 2019-01-18 | 东莞理工学院 | 一种塔柱横梁支架预压的施工方法 |
CN109252448A (zh) * | 2018-09-28 | 2019-01-22 | 东莞理工学院 | 一种桥梁塔柱横梁支架的预压施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101408021A (zh) * | 2008-11-18 | 2009-04-15 | 中铁大桥局集团第二工程有限公司 | 移动式托架、模板整体系统及其施工连续梁的方法 |
CN101761034A (zh) * | 2010-03-25 | 2010-06-30 | 中国建筑第六工程局有限公司 | 一种悬灌连续梁边墩直线段的施工方法 |
CN201924289U (zh) * | 2011-01-30 | 2011-08-10 | 中交三航局第三工程有限公司 | 一种高墩大跨度连续刚构桥0号块托架结构 |
CN202000261U (zh) * | 2011-01-19 | 2011-10-05 | 中铁二十局集团第四工程有限公司 | 预应力平衡法托架 |
-
2011
- 2011-11-22 CN CN2011103735970A patent/CN102493342A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101408021A (zh) * | 2008-11-18 | 2009-04-15 | 中铁大桥局集团第二工程有限公司 | 移动式托架、模板整体系统及其施工连续梁的方法 |
CN101761034A (zh) * | 2010-03-25 | 2010-06-30 | 中国建筑第六工程局有限公司 | 一种悬灌连续梁边墩直线段的施工方法 |
CN202000261U (zh) * | 2011-01-19 | 2011-10-05 | 中铁二十局集团第四工程有限公司 | 预应力平衡法托架 |
CN201924289U (zh) * | 2011-01-30 | 2011-08-10 | 中交三航局第三工程有限公司 | 一种高墩大跨度连续刚构桥0号块托架结构 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103184725A (zh) * | 2013-02-28 | 2013-07-03 | 湖北建科结构加固有限责任公司 | 框架梁等效减载加固法 |
CN103184725B (zh) * | 2013-02-28 | 2015-05-06 | 湖北建科结构加固有限责任公司 | 框架梁等效减载加固法 |
CN103174097A (zh) * | 2013-04-11 | 2013-06-26 | 新疆北新路桥集团股份有限公司 | 大跨径桥梁上部钢结构支撑预应力反张拉加载预压的方法 |
CN104746438A (zh) * | 2015-01-28 | 2015-07-01 | 中国水利水电第五工程局有限公司 | 一种挂篮千斤顶预压方法 |
CN109235267A (zh) * | 2018-09-28 | 2019-01-18 | 东莞理工学院 | 一种塔柱横梁支架预压的施工方法 |
CN109252448A (zh) * | 2018-09-28 | 2019-01-22 | 东莞理工学院 | 一种桥梁塔柱横梁支架的预压施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102051858B (zh) | 一种千斤顶加载三角桁架挂篮以及荷载试验施工方法 | |
CN102493342A (zh) | 连续梁静载预压托架施工方法 | |
CN103437291B (zh) | 整体式水箱预压施工工艺 | |
CN105510047B (zh) | 一种轿车摆臂道路模拟试验装置 | |
CN210442209U (zh) | 多功能偏心受压加载装置 | |
CN102706734A (zh) | 不对称抗侧力结构的加载试验装置及方法 | |
CN202164552U (zh) | 0号块托架预压反力架装置 | |
CN105152032A (zh) | 封闭环境厂房内桥式起重机的安装方法 | |
CN202023150U (zh) | 用于桥梁挂篮施工中的反力架预压系统 | |
CN101624164B (zh) | 用于机组发电机定子的吊装工法及其专用机构 | |
CN205209895U (zh) | 盾构隧道衬砌管片抗弯试验用加载装置 | |
CN205999802U (zh) | 一种连续梁桥零号段、现浇段支架新型预压装置 | |
CN104264551B (zh) | 一种火箭橇无缝滑轨的铺设调校施工方法 | |
CN102995669A (zh) | 大吨位基桩抗拔静载试验连接装置、加载反力系统和方法 | |
CN101824801A (zh) | 自锚式托架的非原位预压方法及其自锚式托架 | |
CN104746438B (zh) | 一种挂篮千斤顶预压方法 | |
CN102944408B (zh) | 锚链拉力试验机推链装置 | |
CN202323730U (zh) | 连续梁静载预压托架装置 | |
CN203188130U (zh) | 预应力反张拉预压牛腿式鹰架支撑装置 | |
CN102926330B (zh) | 一种适用于桥梁施工用挂蓝的安装方法 | |
CN201738246U (zh) | 连续梁挂篮地面预压装置 | |
CN105040598A (zh) | 一种悬浇箱梁0号块的预压施工装置及其预压施工方法 | |
CN103983755A (zh) | 变载光纤应变岩溶塌陷过程模拟试验系统 | |
CN206496913U (zh) | 一种弹性车轮的径向和轴向刚度测试工装 | |
CN107460862B (zh) | 一种基底承载力及摩阻力联合测试装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120613 |