CN102407856A - Hot standby redundancy method and system for central control unit of train - Google Patents

Hot standby redundancy method and system for central control unit of train Download PDF

Info

Publication number
CN102407856A
CN102407856A CN2011102819201A CN201110281920A CN102407856A CN 102407856 A CN102407856 A CN 102407856A CN 2011102819201 A CN2011102819201 A CN 2011102819201A CN 201110281920 A CN201110281920 A CN 201110281920A CN 102407856 A CN102407856 A CN 102407856A
Authority
CN
China
Prior art keywords
ccu
control unit
configuration file
train
cpu
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102819201A
Other languages
Chinese (zh)
Other versions
CN102407856B (en
Inventor
王�锋
郭向红
石勇
武生国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Yangtze Co Ltd
Original Assignee
CNR Dalian Electric Traction R& D Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNR Dalian Electric Traction R& D Center Co Ltd filed Critical CNR Dalian Electric Traction R& D Center Co Ltd
Priority to CN201110281920.1A priority Critical patent/CN102407856B/en
Publication of CN102407856A publication Critical patent/CN102407856A/en
Application granted granted Critical
Publication of CN102407856B publication Critical patent/CN102407856B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Hardware Redundancy (AREA)

Abstract

The invention provides a hot standby redundancy method and a hot standby redundancy system for a central control unit of a train, wherein the hot standby redundancy method for the central control unit of the train comprises the following steps: a first Central Control Unit (CCU) as a slave control unit acquires a first life signal indicating the state of a second CCU at the second CCU as a master control unit; and if the first CCU judges that the first life signal indicates that the second CCU has a fault, loading a main configuration file to be set as a main control unit. According to the hot standby redundancy method and system for the train central control unit, when the second CCU breaks down, the first CCU loads the main configuration file to take over the work of the second CCU, and the received train information is stored in the first CCU, so that the control work can be ensured to be uninterrupted, and the reliability of train network control is improved.

Description

The hot backup redundancy method of train Central Processing Unit (CPU) and system
Technical field
The present invention relates to Train Control Technology, relate in particular to a kind of hot backup redundancy method and system of train Central Processing Unit (CPU).
Background technology
The networked control system of the train system is applied to comprise in the trains such as locomotive, subway, light rail, motor train unit usually, is one of 7 big subsystems of train, is the core subsystem of train.Train Central Processing Unit (CPU) (Central Control Unit is called for short CCU) is the brain of networked control system of the train system, and CCU is configured through loading configuration file, comprises process data source port and place configuring ports to application layer in the configuration file.The various information of train all are pooled among the CCU through the place port of CCU, and CCU carries out relevant action through the actuating unit of other subsystems of source port transmitting control commands control after judging computing, to guarantee that train moves according to related needs.Communicate through MVB (Multifunction Vehicle Bus is called for short MVB) network between CCU and other sensors and the actuating unit.
A MVB network segment has only a CCU in the prior art; The traction of full train, braking, service direction, high-pressure system, car door, air-conditioning, broadcasting etc. are all accomplished by this CCU, and are very high to the reliability requirement of CCU, if this CCU breaks down; The power module fault of CCU for example; Then CCU can't control train, and the driver can't realize the control to train, accident such as possibly cause that train breaks up.
Summary of the invention
The present invention provides a kind of hot backup redundancy method and system of train Central Processing Unit (CPU), to improve the reliability of networked control system of the train.
The present invention provides a kind of hot backup redundancy method of train Central Processing Unit (CPU), comprising:
The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of said the 2nd CCU state at the 2nd CCU as main control unit; Wherein, Be loaded with master configuration file in the said main control unit; Said from control unit, being loaded with from configuration file, said master configuration file comprises source port configuration information and place port configuration information, saidly comprises the place port configuration information from configuration file;
A said CCU indicates said the 2nd CCU et out of order if said Dai-ichi Mutual Life Insurance signal is known in judgement, then loads said master configuration file, to be set to main control unit.
The present invention provides a kind of hot backup redundancy system of train Central Processing Unit (CPU), comprises a CCU and the 2nd CCU;
Be used for obtaining in order to indicate the Dai-ichi Mutual Life Insurance signal of said the 2nd CCU state as a said CCU at said the 2nd CCU as main control unit from control unit; If knowing said Dai-ichi Mutual Life Insurance signal, judgement indicates said the 2nd CCU et out of order; Then load said master configuration file, to be set to main control unit, wherein; Be loaded with master configuration file in the said main control unit; Said from control unit, being loaded with from configuration file, said master configuration file comprises source port configuration information and place port configuration information, saidly comprises the place port configuration information from configuration file.
Can know by technique scheme; The hot backup redundancy method of train Central Processing Unit (CPU) provided by the invention and system; The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state at the 2nd CCU as main control unit; The one CCU indicates the 2nd CCU et out of order if the Dai-ichi Mutual Life Insurance signal is known in judgement, then loads master configuration file, to be set to main control unit.Through the setting of a CCU, receive the train information that each sensor sends, with the operation conditions of monitoring train, and from the 2nd CCU, obtain in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state.When the 2nd CCU et out of order, a CCU loads master configuration file to take over the work of the 2nd CCU, owing to store the train information that receives among the CCU, can guarantee that Control work is uninterrupted, has improved the reliability of networked control system of the train.
Description of drawings
The hot backup redundancy method diagram of circuit of the train Central Processing Unit (CPU) that Fig. 1 provides for the embodiment of the invention;
The hot backup redundancy system architecture scheme drawing of the train Central Processing Unit (CPU) that Fig. 2 provides for the embodiment of the invention.
The specific embodiment
For the purpose, technical scheme and the advantage that make the embodiment of the invention is clearer, will combine the embodiment of the invention below, to the technical scheme in the embodiment of the invention carry out clear, intactly describe.Need to prove that in accompanying drawing or specification sheets, similar or components identical is all used identical Reference numeral.
The hot backup redundancy method diagram of circuit of the train Central Processing Unit (CPU) that Fig. 1 provides for the embodiment of the invention.As shown in Figure 1, the hot backup redundancy method of the train Central Processing Unit (CPU) that present embodiment provides specifically can be used for the redundancy setting of the train Central Processing Unit (CPU) CCU of networked control system of the train system.The hot backup redundancy method of the train Central Processing Unit (CPU) that present embodiment provides specifically comprises:
Step 10, conduct are being obtained in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state for the 2nd CCU of main control unit from the first Central Processing Unit (CPU) CCU of control unit; Wherein, Be loaded with master configuration file in the main control unit; From control unit, be loaded with from configuration file, master configuration file comprises source port configuration information and place port configuration information, comprises the place port configuration information from configuration file;
Particularly, a CCU and the 2nd CCU are arranged in the MVB network segment simultaneously, and in operational process, one of them CCU is as main control unit, and another CCU conduct is from control unit.Can like backboard signal value master slave relation be set according to the equipment operation situation of a CCU and the 2nd CCU when initial, the master slave relation of a CCU and the 2nd CCU also can be set according to the control needs according to sampling.Be set to from control unit like a CCU, the 2nd CCU is set to main control unit.
The 2nd CCU as main control unit is loaded with master configuration file; Comprise source port configuration information and place port configuration information in the master configuration file; The 2nd CCU comes source of configuration port and place port according to this master configuration file; To receive the train information that each sensor sends through the place port, the 2nd CCU generates control command according to train information after judging computing, carries out relevant action through the source port transmitting control commands with the actuating unit of controlling other subsystems again.CCU as from control unit is loaded with from configuration file; From configuration file, comprise the place port configuration information; The one CCU with the train information that sends through place port receiving sensor, monitors the operating condition of train according to disposing the place port from configuration file.The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state from the 2nd CCU as main control unit, and the Dai-ichi Mutual Life Insurance signal is specifically in order to indicate the 2nd CCU to work well or the 2nd CCU et out of order.
Step 20, a CCU indicate the 2nd CCU et out of order if the Dai-ichi Mutual Life Insurance signal is known in judgement, then load master configuration file, to be set to main control unit.
If as the 2nd CCU et out of order of main control unit, then a CCU loads master configuration file, to be set to main control unit.Master configuration file specifically can be stored among the CCU in advance; Identical with the master configuration file of storing among the 2nd CCU; To take over the 2nd CCU work; Receive the train information that each sensor sends through the place port, after judging computing, generate control command, carry out relevant action through the source port transmitting control commands with the actuating unit of controlling other subsystems again according to train information.
The hot backup redundancy method of the train Central Processing Unit (CPU) that present embodiment provides; The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state at the 2nd CCU as main control unit; The one CCU indicates the 2nd CCU et out of order if the Dai-ichi Mutual Life Insurance signal is known in judgement; Then load master configuration file, to be set to main control unit.Through the setting of a CCU, receive the train information that each sensor sends, with the operation conditions of monitoring train, and from the 2nd CCU, obtain in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU state.When the 2nd CCU et out of order, a CCU loads master configuration file to take over the work of the 2nd CCU, owing to store the train information that receives among the CCU, can guarantee that Control work is uninterrupted, has improved the reliability of networked control system of the train.
In the present embodiment, a CCU loads after the master configuration file in the step 20, specifically can also comprise the steps:
Step 30, a CCU send switching command to the 2nd CCU;
Switching command is specifically in order to indicate the 2nd CCU to be set to from control unit.The one CCU can constantly send this switching command to the 2nd CCU, till the 2nd CCU response.The one CCU also can send this switching command to the 2nd CCU with Preset Time at interval, till the 2nd CCU response.Particularly, a CCU can also generate in order to indicate the alerting signal of the 2nd CCU fault, and personnel keep in repair the 2nd CCU with the indication Train Management.
Step 40, the 2nd CCU load from configuration file when receiving switching command, being set to from control unit, and obtain in order to indicate second life signal of a CCU state from a CCU.
It is normal that the 2nd CCU of et out of order recovers, and specifically can recover normal through reset mode, when receiving switching command; Loading is from configuration file; To be set to from control unit, through the train information that place port receiving sensor sends, the operating condition of monitoring train.Specifically can be stored in advance the 2nd CCU from configuration file, with among the CCU can be identical from configuration file.The 2nd CCU is set to behind control unit, takes over the work of a CCU, obtains second life signal that is used to indicate a CCU state from a CCU, and with when the CCU et out of order, the principal and subordinate who carries out control unit is switched.
In the present embodiment, step 10, as from the first Central Processing Unit (CPU) CCU of control unit before the 2nd CCU as main control unit obtains in order to the Dai-ichi Mutual Life Insurance signal of indicating the 2nd CCU state, specifically can also comprise the steps:
Step 50, a CCU load from configuration file, to be set to from control unit according to first indication information that receives;
Step 60, the 2nd CCU load master configuration file, to be set to main control unit according to second indication information that receives.
First indication information and second indication information specifically can pass through the indication information in order to indication principal and subordinate setting of the input equipment input of a CCU and the 2nd CCU for the Train Management personnel respectively.
In the present embodiment, the hot backup redundancy method of this train Central Processing Unit (CPU) specifically can also comprise the steps:
Step 70, obtaining as a CCU in order to indicating the 3rd life signal of a CCU state,, then generating alerting signal and send if judge and know that the 3rd life signal indicates a CCU et out of order from control unit as the 2nd CCU of main control unit.
When as the time from a CCU et out of order of control unit; The 2nd CCU as main control unit generates alerting signal to carry out the fault alarm of a CCU; Can improve from the promptness of the malfunction monitoring of control unit, and then improve the reliability of networked control system of the train.
In the present embodiment, the hot backup redundancy method of this train Central Processing Unit (CPU) specifically can also comprise the steps:
Step 80, receive train information, generate control command according to train information, and the source port of control command through the master configuration file configuration sent as the 2nd CCU of the main control unit place port through the master configuration file configuration;
Step 90, conduct receive train information from a CCU of control unit through the place port from the configuration file configuration.
The hot backup redundancy system architecture scheme drawing of the train Central Processing Unit (CPU) that Fig. 2 provides for the embodiment of the invention.As shown in Figure 2, the hot backup redundancy system of the train Central Processing Unit (CPU) that present embodiment provides specifically can realize each step of the hot backup redundancy method of the train Central Processing Unit (CPU) that any embodiment of the present invention provides, and this repeats no more.The hot backup redundancy system of the train Central Processing Unit (CPU) that present embodiment provides specifically comprises a CCU11 and the 2nd CCU12.Be used for obtaining in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU12 state as a CCU11 at the 2nd CCU12 as main control unit from control unit; If knowing the Dai-ichi Mutual Life Insurance signal, judgement indicates the 2nd CCU12 et out of order; Then load master configuration file, to be set to main control unit, wherein; Be loaded with master configuration file in the main control unit; From control unit, be loaded with from configuration file, master configuration file comprises source port configuration information and place port configuration information, comprises the place port configuration information from configuration file.Particularly, a CCU11 and the 2nd CCU12 are arranged in the MVB13 network segment simultaneously.
The hot backup redundancy system of the train Central Processing Unit (CPU) that present embodiment provides; The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU12 state at the 2nd CCU12 as main control unit; The one CCU11 knows that the Dai-ichi Mutual Life Insurance signal is the 2nd CCU12 et out of order if judge; Then load master configuration file, to be set to main control unit.Through the setting of a CCU11, receive the train information that each sensor sends, with the operation conditions of monitoring train, and from the 2nd CCU12, obtain in order to indicate the Dai-ichi Mutual Life Insurance signal of the 2nd CCU12 state.When the 2nd CCU12 et out of order, a CCU11 loads master configuration file to take over the work of the 2nd CCU12, owing to store the train information that receives among the CCU11, can guarantee that Control work is uninterrupted, has improved the reliability of networked control system of the train.
In the present embodiment, a CCU11 also is used for sending switching command to the 2nd CCU12.Correspondingly, the 2nd CCU12 is used for when receiving switching command, loads from configuration file, and obtains in order to indicate second life signal of a CCU11 state, to be set to from control unit from a CCU11.
In the present embodiment, a CCU11 also is used for loading from configuration file, to be set to from control unit according to first indication information that receives.The 2nd CCU12 also is used for loading master configuration file, to be set to main control unit according to second indication information that receives.
In the present embodiment; The 2nd CCU12 also is used for when as main control unit; Obtaining in order to indicate the 3rd life signal of a CCU11 state as a CCU11 from control unit; Indicate a CCU11 et out of order if the 3rd life signal is known in judgement, then generate alerting signal and transmission.
In the present embodiment, the 2nd CCU12 also is used for when as main control unit, and the place port reception train information through the master configuration file configuration generates control command according to train information, and the source port of control command through the master configuration file configuration sent.The one CCU11 also is used for when as from control unit the time, receives train information through the place port from the configuration file configuration.
In the present embodiment, a CCU11 and the 2nd CCU12 all can adopt following Hardware configuration: two-way DC/DC redundant power; 2 MVBs (MVB) interface; 1 Ethernet 10Base-T/100Base-Tx Ethernet interface; 1 USB 1.1/2.0; 2 RS-232 only are used for debugging; The 500Mhz treater; 256Mbyte RAM; 2048Mbyte Flash memory.
Each CCU supports the input of two-way DC power supply, and the two-way power supply can be independence or independent power supply, and power module satisfies the test specification that " during power supply hit 10ms, needs to keep system works " among the EN50155.CCU provides 2 DB-9MVB interfaces, and system provides DB-9F and two kinds of interface modes of DB-9M.The cable that is connected into the MVB network uses shielded cable.2 serial ports that are exclusively used in debugging are provided, and this serial ports can be used to connect final terminal or PC, is used for the system software debugging.1 10Base-T/100Base-Tx Ethernet interface is provided, and interface adopts the M12 connector.Network interface can be used for communicating with the locomotive communication network.The netting twine that is connected with network interface also has the M12 plug, preferably uses shielding netting wire.Each CCU makes network interface all have different MAC Addresss, and burning can be carried out according to client's needs in this address when dispatching from the factory.Have 1 USB 1.1/2.0 interface, interface adopts USB TYPE-A connector.1 16 bit address configuration switch is provided, can the set device address.Have 7 indicator lamps, the pairing status of equipment of each indicator lamp can be as shown in table 1.
Table 1
Figure BDA0000093096060000081
CCU provides 1 system reset switch, is used for carrying out when crashing appears in system system's hard reset.After pressing switch, system just can carry out hard reset automatically.Support the input of remote system reset switch signal; This signal is a 110V DC signal; Be used to respond the reset signal that the driving position reset button on the train sends, when reset signal greater than 72V DC, time length during greater than 0.5 second, system can re-power automatically and reset.
What should explain at last is: above embodiment is only in order to explaining technical scheme of the present invention, but not to its restriction; Although with reference to previous embodiment the present invention has been carried out detailed explanation, those of ordinary skill in the art is to be understood that: it still can be made amendment to the technical scheme that previous embodiment is put down in writing, and perhaps part technical characterictic wherein is equal to replacement; And these are revised or replacement, do not make the spirit and the scope of the essence disengaging various embodiments of the present invention technical scheme of relevant art scheme.

Claims (10)

1. the hot backup redundancy method of a train Central Processing Unit (CPU) is characterized in that, comprising:
The first Central Processing Unit (CPU) CCU as from control unit obtains in order to indicate the Dai-ichi Mutual Life Insurance signal of said the 2nd CCU state at the 2nd CCU as main control unit; Wherein, Be loaded with master configuration file in the said main control unit; Said from control unit, being loaded with from configuration file, said master configuration file comprises source port configuration information and place port configuration information, saidly comprises the place port configuration information from configuration file;
A said CCU indicates said the 2nd CCU et out of order if said Dai-ichi Mutual Life Insurance signal is known in judgement, then loads said master configuration file, to be set to main control unit.
2. the hot backup redundancy method of train Central Processing Unit (CPU) according to claim 1 is characterized in that, a said CCU loads after the said master configuration file, also comprises:
A said CCU sends switching command to said the 2nd CCU;
Said the 2nd CCU loads saidly from configuration file when receiving said switching command, being set to from control unit, and obtains in order to indicate second life signal of a said CCU state from a said CCU.
3. the hot backup redundancy method of train Central Processing Unit (CPU) according to claim 2; It is characterized in that; Said conduct, also comprised before the 2nd CCU as main control unit obtains in order to the Dai-ichi Mutual Life Insurance signal of indicating said the 2nd CCU state from the first Central Processing Unit (CPU) CCU of control unit:
A said CCU is according to first indication information that receives, load said from configuration file, to be set to from control unit;
Said the 2nd CCU loads said master configuration file, to be set to main control unit according to second indication information that receives.
4. the hot backup redundancy method of train Central Processing Unit (CPU) according to claim 1 is characterized in that, also comprises:
Said the 2nd CCU as main control unit is obtaining in order to indicate the 3rd life signal of a said CCU state as the said CCU from control unit; Indicate a said CCU et out of order if said the 3rd life signal is known in judgement, then generate alerting signal and transmission.
5. the hot backup redundancy method of train Central Processing Unit (CPU) according to claim 1 is characterized in that, also comprises:
Said the 2nd CCU as main control unit receives train information through the place port that said master configuration file disposes, and generates control command according to said train information, and with the source port transmission of said control command through said master configuration file configuration;
Said CCU as from control unit receives said train information through said place port from the configuration file configuration.
6. the hot backup redundancy system of a train Central Processing Unit (CPU) is characterized in that: comprise a CCU and the 2nd CCU;
Be used for obtaining in order to indicate the Dai-ichi Mutual Life Insurance signal of said the 2nd CCU state as a said CCU at said the 2nd CCU as main control unit from control unit; If knowing said Dai-ichi Mutual Life Insurance signal, judgement indicates said the 2nd CCU et out of order; Then load said master configuration file, to be set to main control unit, wherein; Be loaded with master configuration file in the said main control unit; Said from control unit, being loaded with from configuration file, said master configuration file comprises source port configuration information and place port configuration information, saidly comprises the place port configuration information from configuration file.
7. the hot backup redundancy system of train Central Processing Unit (CPU) according to claim 6 is characterized in that:
A said CCU also is used for sending switching command to said the 2nd CCU;
Correspondingly, said the 2nd CCU is used for when receiving said switching command, loads saidly from configuration file, and obtains in order to indicate second life signal of a said CCU state, to be set to from control unit from a said CCU.
8. the hot backup redundancy system of train Central Processing Unit (CPU) according to claim 7 is characterized in that:
A said CCU also is used for according to first indication information that receives, load said from configuration file, to be set to from control unit;
Said the 2nd CCU also is used for loading said master configuration file, to be set to main control unit according to second indication information that receives.
9. the hot backup redundancy system of train Central Processing Unit (CPU) according to claim 6 is characterized in that:
Said the 2nd CCU also is used for when as main control unit; Obtaining in order to indicate the 3rd life signal of a said CCU state as a said CCU from control unit; Indicate a said CCU et out of order if said the 3rd life signal is known in judgement, then generate alerting signal and transmission.
10. the hot backup redundancy system of train Central Processing Unit (CPU) according to claim 6 is characterized in that:
Said the 2nd CCU also is used for when as main control unit; Place port through said master configuration file configuration receives train information; Generate control command according to said train information, and the source port of said control command through said master configuration file configuration sent;
A said CCU also is used for when as from control unit the time, receives said train information through said place port from the configuration file configuration.
CN201110281920.1A 2011-09-21 2011-09-21 Hot backup redundancy method and hot backup redundancy system of train central control unit Active CN102407856B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110281920.1A CN102407856B (en) 2011-09-21 2011-09-21 Hot backup redundancy method and hot backup redundancy system of train central control unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110281920.1A CN102407856B (en) 2011-09-21 2011-09-21 Hot backup redundancy method and hot backup redundancy system of train central control unit

Publications (2)

Publication Number Publication Date
CN102407856A true CN102407856A (en) 2012-04-11
CN102407856B CN102407856B (en) 2015-04-29

Family

ID=45910289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110281920.1A Active CN102407856B (en) 2011-09-21 2011-09-21 Hot backup redundancy method and hot backup redundancy system of train central control unit

Country Status (1)

Country Link
CN (1) CN102407856B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103738366A (en) * 2013-12-26 2014-04-23 北京交控科技有限公司 Computer system
CN104723986A (en) * 2013-12-19 2015-06-24 北汽福田汽车股份有限公司 Controller and control system
CN104898640A (en) * 2015-04-08 2015-09-09 南车株洲电力机车有限公司 Levitation controller fault diagnosis method
WO2016061878A1 (en) * 2014-10-23 2016-04-28 中车大连电力牵引研发中心有限公司 Data processing method, tcn standby gateway device and data processing system
CN105959193A (en) * 2016-06-01 2016-09-21 中车大连电力牵引研发中心有限公司 Train control method and system
CN107222329A (en) * 2017-04-26 2017-09-29 苏州华启智能科技有限公司 The vehicle-mounted broadcast system master control hot spare method of subway
CN107957692A (en) * 2016-10-14 2018-04-24 中国石油天然气集团公司 Controller redundancy approach, apparatus and system
WO2019134490A1 (en) * 2018-01-03 2019-07-11 比亚迪股份有限公司 Vehicle on-board device control system abnormality processing method, device and system
CN111845867A (en) * 2020-07-16 2020-10-30 中车青岛四方车辆研究所有限公司 Data safety redundancy method of central control unit of train network control system
CN113460124A (en) * 2020-03-30 2021-10-01 比亚迪股份有限公司 Train running time processing method and device, computer equipment and storage medium
CN113911168A (en) * 2021-11-18 2022-01-11 中车大连电力牵引研发中心有限公司 Multi-node feedback central control unit redundancy method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60180355A (en) * 1984-02-28 1985-09-14 Nec Corp Redundancy/waiting system of communication controller applied to data exchange
US5123099A (en) * 1987-07-15 1992-06-16 Fujitsu Ltd. Hot standby memory copy system
CN1764080A (en) * 2005-11-15 2006-04-26 中兴通讯股份有限公司 Device and method for realizing ASC
CN1775606A (en) * 2005-12-19 2006-05-24 北京交通大学 Wireless locomotive signal dual-engine warm standby control method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60180355A (en) * 1984-02-28 1985-09-14 Nec Corp Redundancy/waiting system of communication controller applied to data exchange
US5123099A (en) * 1987-07-15 1992-06-16 Fujitsu Ltd. Hot standby memory copy system
CN1764080A (en) * 2005-11-15 2006-04-26 中兴通讯股份有限公司 Device and method for realizing ASC
CN1775606A (en) * 2005-12-19 2006-05-24 北京交通大学 Wireless locomotive signal dual-engine warm standby control method

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104723986A (en) * 2013-12-19 2015-06-24 北汽福田汽车股份有限公司 Controller and control system
CN104723986B (en) * 2013-12-19 2017-02-15 北汽福田汽车股份有限公司 Controller and control system
CN103738366A (en) * 2013-12-26 2014-04-23 北京交控科技有限公司 Computer system
WO2016061878A1 (en) * 2014-10-23 2016-04-28 中车大连电力牵引研发中心有限公司 Data processing method, tcn standby gateway device and data processing system
CN105591774A (en) * 2014-10-23 2016-05-18 中车大连电力牵引研发中心有限公司 Data processing method, TCN (Train Communication Network) standby gateway device and data processing system
CN104898640A (en) * 2015-04-08 2015-09-09 南车株洲电力机车有限公司 Levitation controller fault diagnosis method
CN104898640B (en) * 2015-04-08 2017-08-18 南车株洲电力机车有限公司 A kind of suspension controller method for diagnosing faults
CN105959193A (en) * 2016-06-01 2016-09-21 中车大连电力牵引研发中心有限公司 Train control method and system
CN107957692A (en) * 2016-10-14 2018-04-24 中国石油天然气集团公司 Controller redundancy approach, apparatus and system
CN107222329A (en) * 2017-04-26 2017-09-29 苏州华启智能科技有限公司 The vehicle-mounted broadcast system master control hot spare method of subway
CN107222329B (en) * 2017-04-26 2020-04-14 苏州华启智能科技有限公司 Master control hot standby method of subway vehicle-mounted broadcasting system
WO2019134490A1 (en) * 2018-01-03 2019-07-11 比亚迪股份有限公司 Vehicle on-board device control system abnormality processing method, device and system
CN113460124A (en) * 2020-03-30 2021-10-01 比亚迪股份有限公司 Train running time processing method and device, computer equipment and storage medium
CN111845867A (en) * 2020-07-16 2020-10-30 中车青岛四方车辆研究所有限公司 Data safety redundancy method of central control unit of train network control system
CN113911168A (en) * 2021-11-18 2022-01-11 中车大连电力牵引研发中心有限公司 Multi-node feedback central control unit redundancy method
CN113911168B (en) * 2021-11-18 2024-01-02 中车大连电力牵引研发中心有限公司 Multi-node feedback central control unit redundancy method

Also Published As

Publication number Publication date
CN102407856B (en) 2015-04-29

Similar Documents

Publication Publication Date Title
CN102407856A (en) Hot standby redundancy method and system for central control unit of train
RU2674493C1 (en) Method for exchanging smoke and fire alarm data of train based on combination of independent modules and 3u chassis design
CN106375072B (en) Redundancy control method for locomotive communication network
CN106444553B (en) Scattered acquisition driving system based on two-by-two-out-of-two architecture
CN104309598B (en) A kind of locomotive brake gear control method and system
KR101572940B1 (en) Method and system for restoring communication disruption using gateway
CN204156887U (en) For the locomotive communicating system of fixed-interlock train
CN110758356B (en) Emergency braking control circuit based on coupler coupling detection
KR102304852B1 (en) Apparatus and method for checking or monitoring vehicle control unit
CN103825791A (en) Method for controlling parallel redundancy of MVB master
CN202615229U (en) Central control device in train network control system
CN115782967B (en) Method for controlling two ends of train by single-set vehicle-mounted equipment and vehicle-mounted equipment
US20150358199A1 (en) Train-information management device and train-information management method
CN205203008U (en) Possesses empty control unit of vehicle electricity who is listed as tail function
CN113114551B (en) Dual-redundancy LIN bus communication device
CN203739890U (en) Train network control system
CN202541531U (en) Primary network train control monitoring device based on MVB (Multifunction Vehicle Bus) bus
CN104670247A (en) Train network control system
CN105629913A (en) Railway machine room signal power supply and environment monitoring system
CN204258834U (en) Locomotive network system for managing
CN105027455A (en) Train information management device
CN111512663B (en) Slave component fault monitoring device for a master component of a multiplex network
KR101126640B1 (en) System and method for diagnosticating of most network using wireless network
CN112350909A (en) Communication system and method based on RS485 bus
JP2015039924A (en) On-vehicle network system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA CNR CORPORATION LIMITED

Free format text: FORMER OWNER: DALIAN ELECTRIC TRACTION RESEARCH + DEVELOPMENT CENTER OF CHINA NORTH LOCOMOTIVE CO.,LTD.

Effective date: 20140414

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 116022 DALIAN, LIAONING PROVINCE TO: 100078 FENGTAI, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20140414

Address after: 100078 Beijing Fengtai District city park is a district 15 building

Applicant after: China CNR Corporation Limited

Address before: 116022 Shahekou, Liaoning, China No. 51 The Strip

Applicant before: Dalian Electric Traction Research & Development Center of China North Locomotive Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant