DSB BMS 201801 January Monthly QA Report #5 v1.1
DSB BMS 201801 January Monthly QA Report #5 v1.1
DSB BMS 201801 January Monthly QA Report #5 v1.1
V 1.1
2/1/2018
Prepared By:
CASE
Associates
Incorporated
Contract # 430000266
Department of Services for the Blind BMS Project – January 2018 QA Monthly Report #5
Table of Contents
Document Revision History ............................................................................................. 2
Table of Contents .............................................................................................................. 3
Executive Summary .......................................................................................................... 5
Overall Project Progress ...........................................................................................................5
Major Risks Identified During the Current Monthly Assessment Process .........................5
Overall Project Health ...............................................................................................................6
Overall Project QFP Status – Stable ........................................................................................6
QFPs rated as Stable .................................................................................................................6
QFPs rated as Needs Attention ................................................................................................7
QFPs rated as needing Immediate Attention..........................................................................7
QFPs Not Rated – NR ................................................................................................................7
Quality Focal Point (QFP) Summary Chart .............................................................................7
Recommendations for QFPs Rated Stable (Stable) ................................................... 10
Recommendations for QFPs Rated Needs Attention (Attention) ............................. 10
Recommendations for QFPs Rated Alert (Alert) ......................................................... 10
Detail Quality Focal Point Assessment ........................................................................ 11
QFP 1 - Project Phase Readiness/Completion ..................................................................... 11
QFP 2 - Requirements Management ...................................................................................... 12
QFP 3 - Project Schedule ........................................................................................................ 13
QFP 4 - Communications ........................................................................................................ 14
QFP 5 - Risk and Issue Management..................................................................................... 15
QFP 6 - BMS Vendor Performance ........................................................................................ 16
QFP 7 - Technical Transition, Business Process Re-Engineering .................................... 16
QFP 8 - Project Organization and Leadership ...................................................................... 17
QFP 9 - Project Resources ..................................................................................................... 19
QFP 10 – Project/Quality Management and Reporting........................................................ 19
QFP 11 - Budget Planning and Tracking............................................................................... 20
QFP 12 - Scope and Change Control..................................................................................... 21
QFP 13 – Roles, Responsibilities, and Communications ................................................... 22
QFP 14 - IT Architecture .......................................................................................................... 22
QFP 15 - IT Acquisition Management .................................................................................... 23
QFP 16 - Project Library and Configuration Management .................................................. 23
QFP 17 - System Definition Process ..................................................................................... 24
QFP 18 - System Design Process .......................................................................................... 25
QFP 19 - Data Conversion/Migration ..................................................................................... 25
QFP 20 – Configuration/Construction Process.................................................................... 26
QFP 21 - Testing (Functional, Capacity, and Performance) ............................................... 27
QFP 22 - User Acceptance, Business Process Transition ................................................. 28
QFP 23 – Training .................................................................................................................... 28
QFP 24 - Inter/Intra-Agency Coordination and Implementation ......................................... 29
QFP 25 - Implementation Process ......................................................................................... 29
QFP 26 - Deployment Process ............................................................................................... 30
Executive Summary
CASE Associates Inc. (CAI) has completed the January 2018 monthly QA report #5 for the
period from December 20, 2017, through January 31, 2018. The project has been in full
implementation for two months. The project has completed the GAP analysis for all the
program areas (BEP, VR, Fiscal and OTC) and completed all AWARE system training for
Subject Matter Experts (SMEs) before initiating VR, Fiscal and OTC adaptation configuration
sessions.
The vendor (Alliance) submitted the fully resourced project schedule to the project team in
December. The DSB PM has made the necessary changes to this schedule to meet DSB’s
project goals. The project schedule was approved by the BMS Steering Committee on January
25, 2018.
The project team has prepared the required documents for the OCIO approval for IT Pool
implementation monies for the project. The initial review has been completed by the OCIO and
final approval is expected very soon.
CAI performed the following activities during the monthly reporting period to determine the
Business Management System (BMS) Project’s health:
Participated in project team meetings to observe, review, and discuss project progress
and issues.
Participated in the January 2018 Steering Committee Meeting.
Attended and observed the OTC AWARE training session in the Seattle office and made
recommendations for improvement to the Alliance trainers.
Reviewed the project SharePoint site project documents and many of the Alliance
deliverables.
Participated in a conference call with the OCIO oversight representative (KPR) to review
the project status. Also met with the new OCIO oversight consultant (Whitney
Dickinson) to provide her the major QA findings to date.
The project scope has been fully defined by the project team
Scope Stable and Alliance. The Project Sponsor and Project Team have
worked closely with Alliance to accurately identify the final
scope of deliverables.
The BMS Steering Committee approved the project schedule
on January 25, 2018. The BEP business area is scheduled to
Schedule Stable go first into production in April 2018. Currently, there is little
slack-time in the approved project schedule. CAI is not
concerned at this time since the project scope is well defined
and stable.
DSB will be submitting the application for Implementation
Funding from the IT Pool in late January or early February
Budget Stable 2018. The project team has identified potential cost savings by
eliminating several customizations that may not be essential in
meeting the business need. These savings can fund other
project areas within the current scope of the project.
1
Expected assessment results for the next reporting period (next month)
The next month indicators signify expected changes in the QFP ratings.
- This Quality Focal Point (or group of QFPs) is expected to have the same
rating in next month’s Periodic QA Evaluation.
- The risk is increasing the Quality Focal Point. It may be changed to
Alert in next month’s evaluation
- The risk is decreasing on the Quality Focal Point. It may be changed to
Attention or Stable in next month’s Evaluation.
- The risk is increasing the Quality Focal Point. It may be changed to
Attention or Alert in next month’s evaluation.
- The risk is decreasing on the Quality Focal Point. It may be changed to
Stable in next month’s evaluation.
2 QFP
5 2 - Requirements Management
The Requirements Management process is appropriate and thorough. The Requirements Management QFP assesses
the functional needs of the product and/or service performed by the business, including business process workflow. There
are various types of requirements but not limited to business and workflow, product, software, hardware, and security
requirements.
Stable Attention Alert
Risk Level
2.1 Are the Requirements understood and confirmed? Findings: Yes. All requirements have been identified during the contract
negotiations. The BEP, VR, Fiscal and OTC GAP analyses are complete. Changes to the requirements have been made but
no show-stoppers have been identified. In fact, there appears to be functionality in the AWARE product that can be used
without additional adaptation but more of a change in the business process. Only one major GAP was identified in BEP, but
the plan is to use AWARE analytics to resolve this gap. The project team is reviewing the Aware Analytics approach and
more will be known next month.
2.2 Are requirements traceable to design? Findings: Yes. This is a COTS product implementation and DSB requirements will be
configurable in the AWARE system. For those DSB requirements that are not part of the AWARE system, the agency has
been working with staff to develop appropriate workarounds for their business needs. This approach was discussed early on
in the project and all stakeholders have agreed to this approach.
2.3 Are requirement change impacts understood and documented? Findings: Yes. The project team has been clear throughout
the planning and initial stages of implementation that this is a COTS solution and the agency will not be making
“customizations” to this system. The Project Sponsor, PM, Business Analyst and the OCM leaders in this project have been
articulating this message from the initial discussions on the project.
2.4 Are test conditions defined to validate requirements compliance? Findings: Unknown at this time. Evaluation of this QFP
will occur in a future report as the implementation of the system becomes more mature.
Recommendations: None
3 QFP
3 3 - Project Schedule
The project is appropriately planned. The Project Schedule QFP provides an assessment of the breadth and depth of
project planning, scope definition, the scheduling of the tasks, including identification of internal and external dependencies.
Traditional methodology defines the schedule for the completing the entire project scope.
Stable Attention Alert
Risk Level
3.1 Are all appropriate tasks identified in the Work Breakdown Structure (WBS)/Project Schedule? Findings: Yes. The project
schedule was agreed to during contract negotiations. The BMS and Alliance PM’s have developed the integrated project
schedule that has been approved by the project Steering Committee.
3.2 Are dependencies among tasks identified, including decision dependencies? Findings: Yes. CAI has conducted our initial
review and the working integrated complete project schedule has the required detail WBS to meet the project demands.
3.3 Has a Project Schedule been established and is it reasonable based on resources (budget), productivity, assumptions, and
dependencies? Findings: Yes. The overall project schedule was negotiated during the contract signing. An integrated
project schedule was approved by the BSM project Steering Committee on January 25, 2018. The BMS PM is continually
reviewing and updating the BMS project schedule.
3.4 Is the Project Schedule detailed enough to monitor progress? Findings: Yes. The integrated project schedule provides the
required detail of the tasks, activities, and dependencies to track and monitor progress in the project.
3.5 Is the Project Schedule used to track progress and updated on a regular basis? Findings: Yes. The BMS project manager is
tracking percent completion and all tasks.
3.6 Are external project dependencies identified in the Project Schedule? Findings: Yes. The BMS PM and Business Analyst
have done an incredible job in identifying all dependencies in the project. As the project progresses, the project team is
carefully monitoring for any dependencies not previously identified, and if necessary develop a strategy for mitigation.
3.7 Have appropriate interim and major milestones been defined? Findings: Yes. The integrated project schedule has the
milestones, dates, and deliverables identified. Only the initial project activities that have been started are complete.
3.8 Has the Project Plan been reviewed, approved and signed off by the project Stakeholders/Product Owner? Findings: Yes.
The Integrated Project Management Plan is complete and was approved by the BMS project Steering Committee on January
25, 2018.
3.9 Is there an appropriate process for updating the Project Schedule with actuals and tracking project progress? Findings: Yes.
The Project Manager has a process for updating all project schedule updates on a routine basis.
3.10 Are reasonable plans available to manage the Project? Findings: Yes. The BMS Project Manager is Rolanda Maddox and
she is experienced and will be using the appropriate tools to manage the project. Her backup is Brent Carr.
Recommendations: None
4 QFP
5 4 - Communications
The project communications are effective and adequately controlled. The Communications QFP examines the project
status reporting and communication processes for task completion and budget.
Stable Attention Alert
Risk Level
4.1 Have communications been planned, identified and documented? Findings: Yes. A communication plan has been completed.
4.2 Is the Communications Plan being followed? Findings: Yes. The project team is consistently following the written
communications plan. All major communications are documented and are copied to the project SharePoint site. CAI will be
reviewing the Communications Plan and documents throughout the project to periodically to see if it is being followed and if it is
effective.
4.3 Does the project receive appropriate and timely executive and project sponsor attention? Findings: Yes. The Project Sponsor
and Project Team generally meet weekly to review key issues, risks and next steps/actions for the week. The Project Sponsor
is a member of the BMS Project Steering Committee.
4.4 Are project status and activities being monitored and reported in enough detail and with enough frequency to ensure early
detection of problems or schedule slippage? Findings: Yes. The project status, including the review of the project schedule, is
reported weekly at the BMS Project Team meetings. The team creates a weekly agenda they follow, and they have created a
register to record and track new or changes to Risks and Issues on a weekly basis. They have also instituted a project Kanban
board to track the backlog of activities, all blocking issues, and completed tasks. CAI will continue to attend weekly team
Kanban meetings to monitor issues and progress. During the months of December 2017 and January 2018, most of the project
effort was to complete the training on the AWARE system for the project SME’s.
Recommendation(s): None
5 QFP
2 5 - Risk and Issue Management
Project risks and issues are identified and appropriately managed. The Risk and Issue Management QFP provides an
assessment of the risk identification, mitigation strategy and contingency planning for high probability and/or high impact
risks. It also assesses the continuing validity of high impact assumptions.
Stable Attention Alert
Risk Level
5.1 Are project risks and issues identified and categorized as to likelihood and impact? Findings: Yes. The project maintains a
register to track and monitor risks using Priority / Probability / Impact as ways to prioritize workload. An additional issue register
is maintained and monitored by the project team. CAI is monitoring the team process for updating and mitigating all risks and
issues during the project.
5.2 Are appropriate risk and issue mitigation strategies in place with appropriate monitoring measures? Findings: Yes. A risk
register and mitigation plan are in place. The Project Team updates and discusses the risk register with the Project Sponsor
generally on a weekly basis and with the Steering Committee as necessary.
5.3 For high probability or high impact risks, are contingency plans developed in case the risk mitigation strategy fails? Findings:
Yes. CAI has observed that the project team is proactive in identifying risks and issues and immediately developing
contingency strategies when necessary. CAI continuously reviews any contingency plans for completeness and asks for
additional elaboration and monitoring should that be necessary.
5.4 Are ongoing risk identification, assessment and management processes in place and operating effectively? Findings: Yes. The
project teams meet weekly to review and assess the identified project risks. The project team is closely working with agency
Subject Matter Experts (SMEs) to ensure business requirements are being addressed in the project.
5.5 Have project assumptions been verified & appropriate monitoring measures been put in place to ensure failed assumptions do
not become risks? Findings: Yes. The project has identified the key assumptions as best as possible in the planning phase.
There were no surprises identified during the BEP initial implementation. Completion of the BEP GAP analysis and BEP
training went well during this last reporting period.
Recommendation(s): None
7.2 Has the Technical Transition Plan been reviewed and approved? Findings: Yes. CTS has approved the Azure Government
Cloud platform and the data security protocols for hosting the Alliance SaaS. (See above comment)
7.3 Has the Vendor architecture been assessed relative to the BMS architecture? Findings: N/A. This is a COTS system and
technical architecture is not an issue.
7.4 Are there appropriate resources to implement the Plan? Findings: Yes. Currently, it appears that the required resources
are available. The hiring of the Test lead and the Configuration Specialist were completed in November 2017 and the
onboarding and training and are progressing to meet the project schedule. From discussions with the Project Sponsor and
PM, the hiring of two temporary data entry staff is not necessary. A project team member has been able to assume that role
and is doing a great job in entering quality data.
7.5 Has the Business Process Re-Engineering Plan been defined? Findings: Yes. The project’s Business Analyst has done a
complete review of all business processes in the agency identifying and is documenting current-state business workflows and
is able to take that information not the adaptation phases of each module.
7.6 Has the Business Process Re-Engineering Plan been reviewed and approved? Findings: Yes. The Steering Committee
and Project Sponsor have approved the business re-engineering plans for the project.
7.7 Has the BMS workflow been assessed relative to changes from the System 7 “as-is” processes? Findings: Yes. The pre-
work by the project Business Analyst has identified the “as-is” or current workflows. Reviewing and documenting the current-
state work-flows is paying off as the project team and business SME’s are prepared and ready for the first business team to
move into adaptation (configuration) in the new AWARE system.
7.8 Are there appropriate resources to implement the Plan? Findings: Yes. The project has one highly skilled and capable
business analyst on the project team. It will be critical to ensure that this resource is available throughout the life of the
project.
Recommendation(s): None
8.2 Have Executive Sponsor(s) have been designated? Findings: Yes. The BMS Project Sponsor is the agency CIO, Mary
Craig.
8.3 Project Management roles and responsibilities with lines of authority and accountability have been defined, assigned and
agreed upon? Findings: Yes. The BMS Project Resource Management Plan v1.2 clearly defines the roles and
responsibilities, lines of authority and accountability. CAI will monitor if the Resource Management Plan needs to be updated
as the project progresses.
8.4 Is management committed to the project? Findings: Yes. Management has clearly communicated to the agency that they
are fully committed to the project and have allocated the required resources for the project to succeed.
8.5 Are management and Staff are committed to the project? Findings: Yes. One of the key success factors for this project is the
commitment by management and staff to move to the AWARE system. CAI has observed during this reporting period that
staff are fully engaged in the project at all levels.
8.6 Do Stakeholders Support and Buy-in to the project? Findings: Yes. The project is underway and staff buy-in to the project is
high. CAI will be monitoring stakeholder’s continued support as the project progresses. Stakeholder engagement is critical to
the project success.
8.7 Has a Change Leadership Plan been prepared? A project Change Leadership Plan identifies the steps and procedures that
will be followed should key project staff (e.g., Project Manager, Technical Lead, etc.) no longer be available. Findings: Yes.
Although the Project Charter does not refer to a change leadership plan, the project team has developed a Resource Plan
that provides the necessary steps and actions for project resourcing challenges.
8.8 Is the Change Leadership Process adequately supported by Agency Management? Findings: Yes. There is a solid
commitment by the DSB Steering Committee and the Project Sponsor to maintain and follow the Resource Plan.
8.9 Are there appropriate resources to implement the Change Leadership Plan? Findings: Yes. CAI will be reviewing the
adequacy of the Resource Plan as the project progresses.
Recommendation(s): None
9 QFP
7 9 - Project Resources
The project is appropriately resourced. The Project Resources QFP assesses three resource components: (1) The
capacity and skill set of the assigned project staff; (2) supporting tools and facilities; and (3) budget or financial resources.
Stable Attention Alert
Risk Level
9.1 Is the level of effort planned for each project deliverable at an appropriate activity level; and, is it reasonable? Findings: Yes.
A final project schedule has been approved by the Steering Committee the interim and major milestones in the project have
been baselined. Staffing for these activities is carefully monitored by the project team and also by the Alliance team. CAI has
observed a high degree of attention by the Project Team to ensure the business objectives are going to be met.
9.2 Are appropriate staff resources (skill set and quantity) available and assigned to complete the project? Findings: Yes. The
project team has been appropriately staffed with Subject Matter Experts (SMEs) identified across the agency and committed
to the project. The project team is monitoring, adjusting, and ensuring the right staff is available at the appropriate time in the
project schedule.
9.3 Are appropriate staff support resources (skill and quantity) available and assigned to provide on-going operations support?
Findings: Unknown currently. The current project plan discusses the cut-over and on-going implementation of the project
but only at a high-level. CAI will be reviewing these tasks and activities as the project progresses.
9.4 Are appropriate tools and other necessary facilities available and effectively utilized? Findings: Yes. The project team is
moving to a new location in the next several months that will allow the project team to be more centralized with larger rooms
for project staff.
9.5 Is the Budget (financial resources) sufficient to support the Project? Findings: Yes. The Executive Sponsor and PM are
monitoring the budget carefully and have found several planned and budgeted customizations that may not be necessary and
will save project costs and provide some flexibility in other project areas.
Recommendation(s): None.
10.1 Have formal Project Management and Quality Management Plans been developed? Findings: Yes. The Project
Management Plan contains a section on quality management.
10.2 Are the Plans being followed? Findings: Yes. The project team is using appropriate PMI practices for managing the project.
10.3 Have appropriate metrics and processes been put in place to successfully manage the project? Findings: Yes. The Project
Manager is tracking tasks, tasks completion percentages, and vendor deliverables according to the project schedule. The
Project Manager is using the traditional PMI metrics for controlling and monitoring the project.
10.4 Have objective quality metrics been put in place for project deliverables? Findings: Yes. The project has acceptance criteria
for vendor deliverables.
10.5 Are Project Progress and Deliverables measured against the metrics? Findings: Yes. The working project schedule will be
used to monitor progress.
10.6 Are the results of the metric measurements reported to the appropriate sponsor, users, and other stakeholders? Findings:
Yes. The project team provides the major accomplishments and key issues at the monthly Steering Committee meetings.
10.7 Are appropriate corrective actions put in place when measurements are not acceptable? Findings: Yes.
10.8 Are appropriate status reports prepared for tracking and monitoring all project tasks? Findings: Yes. The Project Manager is
preparing, reporting and monitoring on the project schedule tasks and activities. As the project progresses, CAI will review
the current set of reports and processes for completeness and usability to reduce risk to the project.
Recommendation(s): None.
11.3 Are the appropriate funds budgeted in order to conduct required activities and complete and support the project? Findings:
Yes. The project team is drafting the document required by the OCIO’s office to receive implementation funds from the IT
Pool. The preliminary review of the document by OCIO staff found no red flags in the application and funding should be
approved in the next month.
11.4 Does the Project Manager maintain a tracking report of expenditure? Findings: Yes. CAI will be reviewing the project’s
expenditure tracking during the next reporting period.
Recommendation(s): None
12 QFP
6 12 - Scope and Change Control
The project scope is appropriately controlled. The Scope and Change Control QFP assesses the implementation and
adherence to change requests.
Stable Attention Alert
Risk Level
12.1 Is the scope is being adhered to? Note: Changes in scope usually impact the budget. Findings: Yes. The Project
Management Plan contains a section on scope management. The Project Sponsor and Project Manager follow this plan.
12.2 Are change requests appropriately identified, escalated, and resolved in a timely manner? Findings: Yes.
12.3 Are change requests effectively recognized, analyzed for impact, and approved prior to inclusion in the project scope?
Findings: Yes. The project team is adept at identifying all issues and impacts to the scope of the project. Their concerns are
discussed during daily standups and weekly team meetings and any keys issues are brought to the Steering Committee for
their review, discussion, and approval.
12.4 Is there a Change Management Plan that has been approved and adopted in the project? Findings: Yes.
Recommendation(s): None
13.1 Has a formal Communications Plan been developed? Findings: Yes. This is further expanded on in the OCM analysis to
ensure complete up and down communications in the project.
13.2 Is the Communications Plan being executed? Findings: Yes.
13.3 Are communications identified in the plan and implemented by the Project team effective? Findings: Yes.
The employee out-reach has been effective and excitement in the project is growing across the agency.
13.4 Are the external project communication dependencies included in project status reporting? Findings: Yes.
13.5 Are the project roles and responsibilities documented and understood by all parties? Findings: Yes. The Project Charter
clearly outlines roles and responsibilities for project staff.
Recommendation(s): None
14 QFP
6 14 - IT Architecture
The project adheres to architecture standards. The IT Architecture QFP verifies that the Project conforms to IT Architecture
standards.
Stable Attention Alert
Risk Level
14.1 The computing environment supports connectivity, portability, scalability, and interoperability? Findings: Yes
14.2 The Project supports the State of Washington IT Architecture Framework? Findings: Yes.
14.3 The Project supports the State of Washington IT Architecture Framework strategic objectives? Findings: Yes.
14.4 The Project supports the State of Washington IT Architecture Framework for increasing data security? Findings: Yes. The
project received approval from the Office of Cybersecurity on vendor security compliance.
Recommendation(s): None
16.5 Are there procedures for reviewing changes to items in the library? Findings: Yes. The project site uses the standard
features of SharePoint for changes to project documentation.
16.6 Is it relatively easy to access and find project documentation? Findings: Yes. It is important that the project team keep the
information on the SharePoint current.
16.7 Is there a process in place to archive older documents? Findings Yes. The project will be using the features of SharePoint
library to store and manage project documentation.
Recommendation(s): None
18 QFP
5 18 - System Design Process
The system design process is appropriate and thorough. The Systems Design QFP assess the Systems Design are
reasonable and acceptable for implementation in accordance with the project methodology being used (e.g., waterfall,
rolling wave or iterative, or Agile).
Stable Attention Alert
Risk Level NOT RATED
18.1 Are specifications/designs in agreement with the system/business requirements? Findings: N/A, evaluation of this QFP will
occur in a future report as the implementation of the system becomes more mature.
18.2 Are the application specifications reasonable and acceptable? Findings: N/A, evaluation of this QFP will occur in a future
report as the implementation of the system becomes more mature.
18.3 IsI the system architecture reasonable and acceptable? Findings: N/A, evaluation of this QFP will occur in a future report as
the implementation of the system becomes more mature.
18.4 Are the Database Conversion and Migration specifications reasonable and acceptable? Findings: N/A, evaluation of this QFP
will occur in a future report as the implementation of the system becomes more mature.
18.5 Are
A the Interface specifications reasonable and acceptable? Findings: N/A, evaluation of this QFP will occur in a future report
as the implementation of the system becomes more mature.
Recommendation(s): None
19.3 Is the Data Replication/Migration complete? Findings: N/A, evaluation of this QFP will occur in a future report as the
implementation of the system becomes more mature.
19.4 Has the replicated/migrated data been tested to verify they function according to the specifications? Findings: N/A,
evaluation of this QFP will occur in a future report as the implementation of the system becomes more mature.
19.5 Are the unit test scripts complete and thorough with respect to the business processes? Findings: N/A, evaluation of this
QFP will occur in a future report as the implementation of the system becomes more mature.
Recommendation(s): None.
23 QFP 23 – Training
5
The project staff and system users are appropriately trained in a timely manner. The Training QFP assesses the
training plans and materials and methods for training are appropriate and complete.
Stable Attention Alert
Risk Level
23.1 Has formal Training Plan been developed? Findings: Yes. Alliance has a complete training plan for their product line. The
project team has been proactive in getting staff trained on the appropriate AWARE modules before adaptation sessions
begin to ensure understanding of how the module works and is appropriately configured to meet the business requirements.
23.2 Are the Training Plans being followed? Findings: Yes.
Recommendation(s): None.
25.3 Was the actual training conducted acceptable by the staff? Findings: N/A, evaluation of this QFP will occur in a future report
2
as the implementation of the system becomes more mature.
25.4 Was system documentation completed and approved? Findings: N/A, evaluation of this QFP will occur in a future report as
2
the implementation of the system becomes more mature.
25.5 Have the implementation acceptance criteria been met and approved? Findings: N/A, evaluation of this QFP will occur in a
2
future report as the implementation of the system becomes more mature.
Recommendation(s): None
The following project meetings were attended in-person or remotely for this reporting period.
Meeting Name Date(s)
Project Team Meetings 12/20, 1/31
BMS Steering Committee meetings 1/25
AWARE OTC training in Seattle 1/16
OCIO briefing with the new OCIO consultant (Whitney Dickinson) 1/12
Meeting with the BMS PM to discuss project status 1/23
Documents Reviewed:
The following project documents were reviewed for content and purpose during this reporting period.
Document Name Comments
Incorporated comments if
Reviewed DSB comments on the QA report
appropriate
Weekly progress report summaries As they are produced
Needs to be updated as
BMS Risk Register
changes are being made
Needs to be updated as
BMS Issue Register
changes are being made
Needs to be updated as
BMS Decision Log
changes are being made
BMS Project Action Log Is this document still used?
OCIO December Project Status Report
Working Integrated Project Schedule 20171226 (Note: This
project schedule was approved by the BMS Steering Committee
with the recommended date changes identified by the BSM PM)
AWARE Infrastructure Assessment
Reviewed the SharePoint Site Library for project artifacts
Office of CyberSecurity - Design Review Summary - DSB BMS
Aware Data Conversion Overview
BMS Communications Plan r1
BMS OCM Roadmap
Data Conversion Build Tracking Matrix - WA DSB Draft
DSB BMS OCM Plan v1
WA DSB Data Conversion Plan
WA DSB High-Level Test Management Plan
The following project documents were delivered during this reporting period.
Document Name
DSB BMS January 2018 Monthly QA Report #5
OCIO Project Website posting of the December/January QA Report
Prepared and updated DSB SharePoint Matrix and shared with OCIO consultants to indicate
where key project documents are located on the BMS SharePoint site.
The following project documents will be reviewed/delivered and meeting attended in next month’s
reporting period.
Document Name
DSB BMS 2017 February Monthly QA Report
Post QA report to the OCIO project website
Purpose
The purpose of this report is to provide DSB with an independent, in-depth (deep dive) quality
assessment of the Business Management System Replacement Project. CAI assesses the overall
health of the project, as well as how key project stakeholders feel about the effort and new system. CAI
measures progress, or lack thereof, of key project deliverables and provides DSB with
recommendations on how to address identified issues.
Methodology
CAI Consultants used the following methodology to complete this quarterly assessment and to prepare
this report:
1. Review project documents and deliverables. The documents that are reviewed are listed in
Appendix A under the Documents Reviewed section of this report.
2. Attend meetings, listen and participate in daily/weekly conference calls with project team
members and stakeholders. Conduct interviews with BMS Project Manager, project team
members, project participants and other stakeholders to determine the project's status and
identify possible issues and risks. CAI activities during the reporting period are listed in
Appendix A.
3. Based on CAI's informed judgment, the documents reviewed, meetings attended, and
interviews conducted, CAI comes to an independent, unbiased opinion of the status and the
health of the project.
The Quality Focal Point is impacting the project and needs immediate
attention. CAI includes a Recommendation for every QFP rated Alert. The
Alert recommended action is a corrective measure to improve the QFP that is
currently impacting the project.
The Quality Focal Point needs some improvement, so it won’t impact the
project. CAI includes a Recommendation for every QFP rated Attention.
Attention
The recommended action is a corrective measure to improve the QFP, so it
won’t impact the project.
The Quality Focal Point is stable and not currently impacting the project.
CAI may include a Suggestion in a QFP rated as Stable. CAI rated the
Stable
QFP as stable because it is not impacting the project at this time. The
suggested action is a preventive measure to keep the QFP stable.
- This Quality Focal Point (or group of QFPs) is expected to have the same rating in
next month’s Periodic QA Evaluation.
- The risk is increasing the Quality Focal Point. It may be changed to Alert in
next month’s evaluation
- The risk is decreasing on the Quality Focal Point. It may be changed to
Attention or Stable in next month’s evaluation.
- The risk is increasing the Quality Focal Point. It may be changed to Attention
or Alert in next month’s evaluation.
- The risk is decreasing on the Quality Focal Point. It may be changed to Stable in
next month’s evaluation.
Open QA Recommendations
The following table lists the open QA Recommendations from the baseline and previous Assessments, along with their status and any revisions. As a note, new recommendations are
identified above and not included in this table:
There are no open recommendations in the January 2018 monthly QA report #5.
ID BMS Action CAI
Recommendation QFP / QA Rating /
Impact Owner Taken and Confirmation of
Date – Source Description Recommendation Status
Status Status
Target completion:
January 31, 2018
#1 Readiness Assessment CAI recommends finalizing Medium High Project We are currently working Confirmed Completion
June 2017 the staffing plan and Sponsor with agency executives Date:
determine how to best backfill to firm up the project 11/17/2017
current operations for key Staffing Plan and create
staff that will be working on the best processes for
the BMS Replacement backfill. The final The September 29,
Project. Ensure that Staffing Plan will be 2017, target date is
Executive Management dependent on the joint reasonable. CAI will be
supports the need for a clear resource plan developed reviewing the status of
plan that the Agency staff feel with the vendor during this recommendation in
will be sufficient. contract negotiations. the next monthly report.
Target completion:
September 29, 2017
#2 Readiness Assessment CAI recommends providing High High Project To date, there have Confirmed Completion
June 2017 more rigor around the Manager been two formal Date:
execution of the Project communications 11/17/2017
Communication Plan. Ensure distributed to all staff
users, stakeholders and from executive
project participants are kept management. These The September 15,
apprised of the status of the communications 2017, target date is
Project, even if it means provided a personable, reasonable. CAI will be
explicitly stating delays or the detailed overview of the reviewing the status of
reason(s) for the apparent project, what to expect, this recommendation in
need for minimal what resources are the next monthly report.
communication. (It should be needed internally and
ongoing status regarding
Target completion:
September 15, 201
#3 Readiness Assessment CAI recommends that the High High Project The Project Confirmed Completion
June 2017 content of the Project Manager Management Plan Date:
Management Plans must (PMP) includes an Org 11/17/2017
be clear on how the Chart and
project will be managed, Roles/Responsibilities of
specifically: each role in the The September 29,
decision-making 2017, target date is
Target completion:
September 29, 2017
#4 Readiness Assessment CAI recommends beginning High High Project At the time of QA Completed June 30,
June 2017 to identify alternative streams Sponsor Readiness Assessment, 2017
of funding if the project the state budget had not
budget is not approved by the been signed. On June NOTE: DSB is still in the
legislators. 30, 2017, the final state process of completing
budget was signed and the Investment Plan but
Target completion:
November 10, 2017