The new F-35 Joint Strike
Fighter is transforming from a paper airplane
into a real airplane. The shift got underway
in November, when the fighter subcontractors began
fabricating the first actual airframe components. This
is always a tense time for a big procurement program,
but F-35 officials are confident that they will keep
development turbulence at a minimum.
The changeover has not
been without its rough spots, however. What had been
a nearly problem-free program
began to experience some difficulties. The F-35 for
years had seen little or no cost, schedule, or design
problems, but, in recent months, it has seen some
of eachfor example, unanticipated weight
growth.
The Air Force and prime contractor Lockheed Martin
are not exactly novices at handling fighter growing
pains. They have the recent experience of bringing
in the F/A-22 Raptor, a highly complex aircraft.
Lessons derived from the Raptors past difficulties
with avionics and aerodynamics will be applied to
the new
strike fighter, enabling program officials to head
off many problems before they occur.
|
Pictured here
is Lockheed Martins X-35 Joint Strike
Fighter concept demonstrator. The first development
F-35 will emerge late next year. (Lockheed Martin photo by Tom Reynolds) |
The F-35 is also benefitting from the Raptors
technologyprimarily in the areas of avionics,
propulsion, and stealth. Some 30 percent of the mission
software in the strike fighters avionics comes
from the F/A-22, said Tom Burbage, executive vice
president at Lockheed Martin and JSF general manager.
Reuse of
that code will reduce the nominal cost of the F-35
program by roughly $400 million, said Burbage.
The F-35s Pratt & Whitney F135 engine, which
will be installed in the initial production aircraft,
is derived from the F/A-22s PW F119 power plant,
and program officials say the engine has performed
flawlessly so far. An alternative engine, the General
Electric F136, will be introduced around the fifth
production lot. Thereafter, the two engine makers
will compete for annual sales. The two engines will
be functionally
identical to ensure either engine can be used at
any time.
The strike fighter program also has benefitted from
USAF and industry F-117 and F/A-22 stealth technology
experience.
Ambitious Effort
The F-35 program is the largest Defense Department
acquisition effort ever. Its an ambitious undertaking
to replace thousands of legacy fighter and attack
aircraft with three highly common variants of a single
fighter.
The Air Force, Marine Corps, and Navy each have their
own variant. The three JSFs are designed with maximum
commonality in mind, to simplify and streamline development,
supply, and maintenance.
The Air Forces F-35A will be a conventional
takeoff and landing (CTOL) version to replace F-16s
and A-10s.
The Navy plans to replace F-18A/Cs and introduce
stealth into its fleet with its carrier variant (CV)
F-35C.
The Marine Corps version, the F-35B, will be a short
takeoff and vertical landing (STOVL) aircraft to
succeed its elderly AV-8 Harriers and early F/A-18s.
|
The F-35 started to become
a real airplane
with the fabrication of the first major airframe
components in November. Progressive, Inc., H.M.
Dunn, and Brek Manufacturing were first to cut
F-35 structural parts. (Lockheed Martin photo) |
Each F-35 is expected to be able to perform all the
missions of the legacy aircraft it replaces.
For the Air Force, the role of the JSF may become
more a function of training specialization or commander
requirements.
How we decide to employ that [aircraft], as
a service, is going to be up to our leaders of the
time, Col.
Daniel Conroy, chief of Air Combat Commands
JSF management office at Langley AFB, Va., said
in an interview.
Right now, youve got F-16s that do SEAD
[suppression of enemy air defenses] only, youve
got F-16s that concentrate on interdiction, youve
got the A-10 in the CAS [close air support] role, explained
Conroy, adding, You could design ... all
those capabilities in a single squadron. Then,
he said, a combatant commander can roll
[the F-35] into his warfighting effort any way
he wants to.
Alternately, Conroy said, USAF could decide to
continue to organize squadrons the way it does
today, developing
different mission expertise in specific squadrons.
The US military needs the Joint Strike Fighter
primarily in an air-to-ground role. The Air Force
plans to
use it to complement its new F/A-22 fighter.
Likewise, the Navy wants a similar complement
for its new
F/A-18E/F.
The JSF will also have an aerial combat capability,
due largely to another unique aspect of the programextensive
international cooperation in the development
of the aircraft. To fulfill the needs of the
JSF programs
international partners, the F-35 will have a
reasonable, inherent air-to-air capability, said
Air Force Maj. Gen. John L. Hudson, JSF program
manager.
The programs international partners (Australia,
Britain, Canada, Denmark, Italy, the Netherlands,
Norway, and Turkey) want a true multirole aircraftfor
everything from close air support and suppression
of enemy air defenses to aerial combat. They are contributing
to the programs development phase, in exchange
for input into the design and preferential consideration
for their national suppliers.
The partner nations have varying input into the
program, based on the level of their financial
support. The
US will receive more than $4 billion from these
nations to help develop the F-35.
|
Pictured is Pratt & Whitneys first
production-spec F135 power plant. It is derived
from P&Ws successful F119, developed
for the F/A-22 Raptor program.(Lockheed Martin photo) |
Britain was the first international participant
in the program and, as the leading partner, has
significant
input into the design. Britain plans to procure
150 STOVL versions for the Royal Air Force and
Royal
Navy to replace the GR7 and the Sea Harrier.
Britain is already making plans based on the
JSFs
advanced capabilities. The strike fighter is extremely
important to us, said Air Chief Marshal
Jock Stirrup, Chief of the RAF. In an interview
last fall,
Stirrup said the RAF envisions the JSF will perform
most of the heavy lifting in well-defended
zones because of its stealth characteristics.
Meanwhile, the RAFs Eurofighter Typhoon
fleet will operate in a standoff role in the
early days of a conflict.
Britain expects the JSF to mount offensive air
operations from either afloat or ashore, Stirrup
explained. Hence, we have formed what we
call Joint Force Harrier ... under a single command,
RAFs
Fighter Command. This unified force, now
flying Harriers, will later migrate to the JSF.
That will
give Britain a powerful, precision attack
capability, he
said.
The F-35 will bring a leap in technology and
be one of the more flexible fighters, said
Conroy. It will also have a range that
will exceed any of our legacy fighters, he
added.
That technology leap creates a minor concern
for the international consortium. Some participants
have said
that technology transfer has been too difficultan
issue the program office continues to work.
Access to sensitive US technology is always
a concern and needs to be treated with the utmost care, said
Jon Schreiber, JSFs director of international
programs.
Schreiber said partner nations have been assured
they will receive an aircraft, at the end of
the day, that
meets their national requirements and that
is not
only superior from a performance standpoint,
but one that is more affordable from a life
cycle cost perspective
and [which] can be operated and maintained
[abroad].
Affordability has been a central theme from
Day 1 for the JSF program, which has been billed
as the
affordable solution both from a sustainability
and up-front cost perspective.
In the year since Air Force Magazine reported
that the F-35 program had reached its first
major development
milestone with cost and schedule on track,
development cost has risen. (See The
F-35 Steps Out, April
2003, p. 46.) At that time, Hudson said, So
far, our cost performance has been excellent.
In that same article, however, Hudson did allude
to potential software difficulties and efforts
to save
weight. Now, those two issues, plus some design
problems, are adding to a cost increase and
schedule delays.
The Key Problems
My two biggest concerns are weightbecause
thats
one of the drivers for performanceand
software, Hudson
told Air Force Magazine in January.
Every additional pound limits performance,
but contract specifications primarily are
directed toward achieving
certain performance requirements for each
individual system, not toward maintaining
a specific weight
for those systems.
The empty weight of this airplane is about
27,000 poundsits
a pretty good size airplane, Hudson
said. That is without weapons or gas. When
you put 18,000 pounds of gas in it, two
2,000-pound bombs, two air-to-air
missiles, ... you are up to about 50,000
pounds at takeoff or around the low 40s
at maneuvering weight, he
added.
|
The X-35 (left) and an F-16D display different
profiles. The new strike fighter maintains low-observable
characteristics by carrying weapons and fuel internally.(Lockheed Martin photo by Tom Reynolds) |
Hudson projects that the Air Forces CTOL version
will be about 1,400 pounds heavy when
it becomes operational. He said that the
Navys CV
aircraft probably will also be about 1,400
pounds beyond its target weight and the
Marine Corps STOVL
version about 2,200 pounds overweight.
Those extra pounds translate into reduced
capability in a key performance parametercombat
radius. The KPP requirement for the Air
Forces CTOL combat
radius is 590 nautical miles. At its target
weight, said Hudson, that version of the
strike fighter would
actually have a radius of about 660 nautical
miles. However, he said, If were
at the 1,400 pounds heavy figure, were
at about 640 [nautical] miles.
Hudson emphasized, Thats still pretty
darn good, but its obvious that weight
is degrading range.
On the software issue, Hudson said, We have
our work cut out for us to stay ahead of the game on
software. While
JSF avionics have not yet caused problems,
they pose an area of potential concern.
There are about six million lines of code
in the airplane and another six million
in the
simulator, plus about
three million in associated systems. Some
of that
15 million lines of code can be lifted
from other programs,
such as the F/A-22. However, given the
F/A-22s
troubled avionics history, F-35 program
officials cast a cautious eye toward software
development.
We know that software is, and will continue
to be, a big challenge for us, Hudson acknowledged,
but he added that avionics design is going
pretty well.
The avionics are critical to the aircraft. In
some ways, this is an extremely sophisticated
set of avionics and sensors that needs an airplane
to carry
it ... into combat, Hudson said.
|
The F-35s short
takeoff and vertical landing variant was specifically
designed for Marine Corps
use. However, USAF has now decided to acquire this
aircraft to replace the A-10 (see box below). The
exact number has not yet been specified. (Lockheed Martin Photo by Tom Reynolds) |
A slowdown in design of the Air Forces CTOL
airframe is also causing some problems. The CTOL design
is not
coming as quickly as wed like, said
Hudson, adding that it is going
to take us a little longer than wed
anticipated.
The Air Forces CTOL F-35 is still scheduled
to undergo its critical design review next month, the
last major developmental milestone before
the aircraft
begin flying. At the CDR, program officials
expect to lock in the strike fighters CTOL design
as much as is possible before flight testing begins
in
late 2005.
The CV and STOVL variants will have separate
CDRs. Hudson said, Weve got
some schedule pressure on both of those.
All these current program challenges
led the Office of the Secretary of Defense
late last
year to direct
a slow downbeginning with the Fiscal
2005 budgetin
the F-35s development program.
The delay has forced the program office
to move funds from production
accounts into development. That means
fewer aircraft will be built in this
decade than originally planned.
(See DOD Shuffles JSF Schedule,
Dollars, p.
47.)
The Pentagon still plans to produce a
total of 2,443 aircraft: 1,763 for the
Air Force
and 680
for the
Navy and Marine Corps. And the program
is still slated to
achieve initial operational capability
for the Marines in 2010, the Air Force
in 2011,
and the
Navy in 2012.
Program officials also noted that since
the F-35 does not operate under a cost
cap like
the F/A-22
does,
production funds (and aircraft) that
are cut in the near term can be added
in again
later.
The Scorecard
In other ways, the JSF is on track, said
Hudson. He rated the program good on
four of six key performance parameters
common across all three variants.
(The progress of two KPPs is unknown
at this time.) The KPPs are the core
fighter capabilities that cannot
be traded away in a tug of war between
capabilities and affordability. The common
KPPs are:
Radio frequency signature.
- Combat radius.
- Sortie generation.
- Logistics footprint.
- Mission reliability.
- Interoperability.
Hudson said that radio frequency signature,
also known as radar cross section (the
very low observability
feature) was in good shape, to a great
extent because of previous stealth work
with the
F-117 and F/A-22.
He said, We learned a lot from
these systems, not only about how to
make it work but how to keep
it supportable, so its not a burden
to our maintainers. That
last comment also supports elements of
both the logistics footprint and mission
reliability.
Combat radius, as stated earlier, depends
primarily on weight. Even though the
CTOL version is
heavier than its target weight, program
officials still
expect to see a better-than-required
combat radius.
Hudson projected that the CTOL variant
will demonstrate the needed sortie generation
rates as it heads
into Aprils CDR.
He said the logistics footprint is defined
as the number of C-17 loads it
takes to deploy a fighter squadron for
a combat operation. The footprint
is on track, he said, adding that the
F-35 will be significantly
easier to deploy than the F-16.
Interoperability is an unknown, but Hudson
said that most interoperability factors,
such as the
way the
fighter will communicate with joint and
coalition aircraft, ships, and space
assets, are progressing
well. Other
interoperability factors, he said, are
in the category of we just dont
know if well meet
[them]. The reason, though, is
simply that the standards
... havent been defined yet or
theyre shifting, said
Hudson. He added, Theres
some uncertainty out there about what
those standards are going to look
like.
Another unknown is mission reliability.
The rate for that KPP must be at least
93 percent
for
USAFs
F-35A.
Despite the programs current problems, Hudson
maintains that it has been successful
in the past in hitting its milestones on time. And
there have been
naysayers at every turn.
|
This is an artists
conception of an F-35. Combat-ready F-35s are
expected to
have all the
capabilities of the F-16s, A-10s, Harriers, and
F/A-18 Hornets that they replace, plus more. (Photo Illustration by Erik Simonsen) |
Ive been in the program almost five years, Hudson
said. In that time, people said
the concept demonstrators wouldnt
be able to fly. They did.
He went on to say critics also questioned
the ability of the CV and STOVL versions
to fly
in time for
the 2001 downselect. There was a Congressional
mandate
that those variants would fly 20 hours
before source selection. That requirement
was met,
Hudson said,
and source selection occurred on
the day and the time we said.
The delays began to emerge last spring,
when the preliminary design review
took longer
than expected.
The PDR took
an extra three months to close, said
Hudson. That was due primarily to weapons
bay issues and internal routing issues,
but we got through that, he
noted.
Still, Hudson said, Weve got some significant
challenges ahead.
DOD Shuffles JSF Schedule, Dollars
The Defense Department in February announced
that the F-35 Joint Strike Fighter program
was being
restructured because the cost of the system development
and demonstration phase was increased by $7.5
billion. The restructure will yield a net
zero change in the overall program, according
to DOD.
The cost estimate for the development phase
rose from $33 billion to $40.5 billion when officials
had to extend the program schedule by one year
to accommodate additional design work, known
risks, and [to provide] a higher-confidence, risk-adjusted
cost estimate, stated a DOD budget document
outlining the restructure.
Schedule delays on this very complex
aircraft are prudent and necessary to mature
its design and
ensure its ultimate success, noted the
Pentagon in its news release on the 2005 budget.
In the near term, $5.1 billion was shifted
out of procurement appropriations in Fiscal 2005-09.
As a result, there will be 70 fewer aircraft
built by 2009.
Additional design work is necessary because
some integration activities are taking longer
than
planned, and all three variants are estimated
to be at least
1,400 pounds overweight. Officials point out,
though, that weight growth is not uncommon.
To my knowledge, theres not a single
aircraft in the last 50 years that hasnt
had weight growth, said DOD Comptroller
Dov S. Zakheim at the Feb. 2 DOD budget press
briefing. Weight
growth correlates phenomenally well with increase
in cost, he added. The department needs
to address the problem now, not later, he
said, so significant research and development
funding is now going to be devoted to cutting
the F-35s
weight.
Officials said production funds may be added
back into the F-35s budget in later years,
because the Air Force and Navy quantity requirements
have
not changed. Further, the triservice F-35 does
not operate under a cost cap, as the F/A-22
Raptor does. Therefore, aircraft lost from
the early production
lots could be bought later.
The restructure means USAF in Fiscal 2006 will
buy six fewer of its conventional takeoff and
landing F-35s and 35 fewer through Fiscal 2009.
The Marine
Corps will cut its purchase of the short takeoff
and vertical landing variant by 35 through
2009.
Overall, the Pentagon will acquire 164 fewer
F-35s through 2013.
The restructure also produces a one-year delay
in low-rate initial production. The first aircraft
for the Air Force and Marines will now be built
in Fiscal 2007, not 2006. Officials said there
is no schedule change on the Navys carrier
version; production is still set to start in
Fiscal 2008.
A senior Air Force budget official said that
the changes are not expected to delay the first
flights
of the programs developmental aircraft
or postpone USAFs initial operational
capability date of 2011. |
There Will Be an Air Force F-35 STOVL
The Air Force recently ended any ambiguity over
whether it intended to buy the short takeoff
and vertical landing F-35. The service will buy
some STOVL F-35s.
Top leaders made the announcement on Feb. 12
at the Air Force Associations annual Air
Warfare Symposium in Orlando, Fla.
Gen. Ronald R. Fogleman, Air Force Chief of
Staff in the period 1994-97, first broached the
idea
of acquiring STOVL versions to replace some A-10s.
Until last month, however, service officials had
not made an official commitment.
When asked about the STOVL last fall, Gen.
John P. Jumper, the current Chief, did say, It
is not out of the question that the Air Force would
be interested.
Jumper said that USAF must pay specific
attention to
CAS, but he noted that USAF was developing new
ways to conduct the mission. These included use
of USAF bombers dropping satellite guided bombs
in the CAS role.
The course we are on right now is to
make sure we can get everything we can out of
the A-10, he
said, adding, we know that in the not-too-distant
future, the A-10 will be difficult to make survivable
in the most difficult battlespaces.
That means, Jumper said, were going
to have to have something else. |
Copyright Air Force Association. All rightsreserved.
|