JP3790521B2 - Simple curing morning glory - Google Patents

Simple curing morning glory Download PDF

Info

Publication number
JP3790521B2
JP3790521B2 JP2003104998A JP2003104998A JP3790521B2 JP 3790521 B2 JP3790521 B2 JP 3790521B2 JP 2003104998 A JP2003104998 A JP 2003104998A JP 2003104998 A JP2003104998 A JP 2003104998A JP 3790521 B2 JP3790521 B2 JP 3790521B2
Authority
JP
Japan
Prior art keywords
main body
morning glory
building
connecting material
arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003104998A
Other languages
Japanese (ja)
Other versions
JP2004308299A (en
Inventor
龍夫 小松
Original Assignee
朝日リーラック株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 朝日リーラック株式会社 filed Critical 朝日リーラック株式会社
Priority to JP2003104998A priority Critical patent/JP3790521B2/en
Publication of JP2004308299A publication Critical patent/JP2004308299A/en
Application granted granted Critical
Publication of JP3790521B2 publication Critical patent/JP3790521B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、工事現場の仮囲いや仮設足場に取付けられる簡易養生朝顔に関するものである。
【0002】
【従来の技術】
簡易養生朝顔は、仮設足場の外側に設置される仮囲いの布パイプを利用して取付けられたり、枠組足場等の建枠からも簡単に取付けることができ、鉄骨建方や足場解体や溶接作業等における小物類の落下防止に用いられている。
【0003】
従来の簡易養生朝顔は、図8に示すように、本体金具50と、本体アーム51と、つなぎ材52と、筋違53から構成されている。本体金具50から垂設した垂直材54が枠組足場の建地Tや仮囲いの布パイプに添って取付けられ、フックボルト55やクランプで固定される。本体アーム51は角パイプからなり、その基端部が本体金具50にピンを介して固定され、作業完了後には上方に立てて格納し、再度作業するときは突出状態にセットすることができる。つなぎ材52や筋違53の端部は、本体アーム51の両端部のグラビティロック56に取付けられ、この上に養生シート(図示省略)が張られる。建地の一定のスパンや規格通りのスパンが取れない場合には、つなぎ材52に伸縮手摺棒が用いられる。
【0004】
また、本発明に関連する先行技術文献としては、特許文献1がある。この特許文献1の発明は、簡易養生朝顔ではなく、枠組足場に設けられる比較的頑丈な養生朝顔であり、上弦材と下弦材と縦材からなる横向き台形枠のブラケットと、隣り合うブラケットの先端部間に水平材を掛け渡して平面的な枠を構成し、枠組足場の建地に対して上弦材の基端部をクランプで固定し、下弦材の基端部をコ字形金物で固定している。
【0005】
【特許文献1】
特開平7−207952号公報
【0006】
【発明が解決しようとする課題】
仮設足場の建地のスパンには、メーターサイズで1800,1500,1200,900,600(単位mm)があり、さらにインチサイズ系統、メーターサイズ系統、建設会社固有の系統によってスパンが数10mm異なっており、従来の伸縮手摺棒によるつなぎ材52では、長さ調整が面倒であるなどの問題があった。また、筋違53も各スパンの各系統ごとに多数用意しておかなければならない問題があった。
【0007】
また、本体金具50から垂直材54が垂設されているため、嵩張ると共に、建地への取付けが面倒であるなどの問題があった。さらに、コーナー部では、1本の建地に2本のアームを直角に配設する必要があるが、垂直材54の付いた本体金具50を1本の建地に取付けることはできず、コーナー部の処理に問題が生じていた。
【0008】
本発明は、前述のような問題点を解消すべくなされたもので、その目的は、比較的簡単な構成の長さ調整可能なつなぎ材と少ない種類の筋違で種々のスパンにおける各系統のスパンに容易に対応することができ、さらに本体金具を仮設足場や仮囲いの建地に簡単な取付部材で容易に固定することができると共に、コーナー部の処理も簡単に行うことのできる簡易養生朝顔を提供することにある。
【0009】
【課題を解決するための手段】
本発明の請求項1は、仮囲いや仮設足場の建地に取付けられる本体金具と、この本体金具に基端部が取付けられる本体アームと、隣り合う本体アームの基端部同士及び先端部同士をそれぞれ連結するつなぎ材と、隣り合う本体アーム間に配設される筋違を備えた簡易養生朝顔において、つなぎ材が、第一つなぎ材と第二つなぎ材を長さ調整可能に組み合わせて構成され、つなぎ材及び筋違の端部を本体アームに着脱自在に取付ける取付ピン(グラビティロックなど)が本体アームの基端部と先端部にそれぞれ複数個配設されていることを特徴とする簡易養生朝顔である。
【0010】
本発明の請求項2は、請求項1に記載の簡易養生朝顔において、建地に固定されるクランプが本体金具に設けられていることを特徴とする簡易養生朝顔である。本体金具は、例えば、鉛直に配置された取付板の表面(反建地側)に左右一対の側板を溶接等で固定して構成され、左右一対の側板間に本体アームの基端部を挿入して固定ピンで固定されており、前記取付板の裏面(建地側)にクランプを上下一対で配設し、取付板にボルト・ナット等で固定する。このクランプには、2種類の建地の径に使用できる兼用クランプを用いるのが好ましい。
【0011】
本発明の請求項3は、請求項1または2に記載の簡易養生朝顔において、本体アームが円形鋼管からなることを特徴とする簡易養生朝顔である。本体アームには、従来、角パイプが使用されてきたが、丸パイプを用いることで、後述するように本体アームにクランブが使用できるようにする。
【0012】
本発明の請求項4は、請求項1、2または3に記載の簡易養生朝顔において、第一つなぎ材に対して長さの異なる第二つなぎ材が着脱自在に接続され、かつ、第一つなぎ材と第二つなぎ材の接続端部が長穴とボルトにより位置調整可能に固定されていることを特徴とする簡易養生朝顔である。例えば、第一つなぎ材を共通の外管とし、第二つなぎ材を種々の長さの内管とし、第一つなぎ材の基端部に第二つなぎ材の先端部を挿入して、長さを変えることにより、建地の種々のスパンに対応できるようにし、さらに長穴とボルトにより固定して、長さを微調整することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に対応できるようにする。
【0013】
以上のような構成において、第一つなぎ材に適宜選択した第二つなぎ材を接続することにより、建地の種々のスパンに容易に対応することができる。さらに、長穴とボルトにより長さを微調整して固定することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。また、アーム軸方向に一対のつなぎ材の本体アームへの取付けも、複数個の取付ピンを適宜選択することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。さらに、筋違の本体アームへの取付けも、複数個の取付ピンを適宜選択することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。以上により、比較的簡単な構成の長さ調整可能なつなぎ材と少ない種類の筋違で種々のスパンにおける各系統のスパンに容易に対応することができる。
【0014】
また、本体金具に従来の垂直材に代えてクランプを設けることにより、本体金具部分を簡単でコンパクトな構成とすることができると共に、仮設足場や仮囲いの建地に容易に固定することができる。また、コーナー部では、1本の建地に2本の本体アームを直角に配設する必要があるが、クランプを用いることにより1つのクランプに2つの本体金具を直角配置でき、1本の建地に2本の本体アームを直角に配設することができる。
【0015】
さらに、コーナー部において建地が隣接して設置される部分では、一方の建地に取付けた本体アームに、他方の建地に取付けていない本体アームを固定しなければならないが、本体アームに円形鋼管を使用することにより、両者をクランプで容易に固定することができる。
【0016】
【発明の実施の形態】
以下、本発明を図示する実施の形態に基づいて説明する。図1は本発明の簡易養生朝顔の一例を示す側面図と平面図である。図2は図1の本体アームを示す平面図と側面図と端面図である。図3、図4は図1のつなぎ材を示す平面図と分解側面図である。
【0017】
図1の実施形態において、本発明の簡易養生朝顔は、主として、仮囲いや仮設足場の建地Tに取付けられる本体金具1と、この本体金具1に基端部が取付けられる本体アーム2と、隣り合う本体アーム2、2の基端部同士及び先端部同士をそれぞれ連結するつなぎ材3と、隣り合う本体アーム2、2間に配設される筋違4から構成されている。
【0018】
つなぎ材3は、後述するように第一つなぎ材3aと第二つなぎ材3bを長さ調整可能に組み合わせて構成される。つなぎ材3及び筋違4の端部を本体アーム2に着脱自在に取付ける取付ピン、即ち先端部側面に係止爪を出没自在に設けたグラビティロック5が本体アーム2の基端部と先端部にそれぞれ複数個(図示例では2個)配設され、この複数個のグラビティロック5を適宜選択してつなぎ材3及び筋違4が取付けられる。本体金具1は上下一対のクランプ6、6により建地Tに固定される。
【0019】
図2に示すように、本体アーム2は円形鋼管であり、先端部の上部にグラビティロック5a、5bが間隔a1 をおいて突設され、基端部の上部にグラビティロック5c、5dが間隔a2 をおいて突設されている。本体アーム2の先端面には塞ぎ板10が設けられ、中間部には養生シートを留めるための留めリング11が間隔をおいて複数設けられている。本体アーム2の基端部には本体金具1に取付けるための取付穴12、12が設けられている。
【0020】
図3、図4に示すように、つなぎ材3は円形鋼管から構成され、第一つなぎ材3aが外管、第二つなぎ材3bが内管であり、第一つなぎ材3aの基端部に第二つなぎ材3bの先端部を挿入することで一体的なつなぎ材3とすることができる。第一つなぎ材3aには長さの同じ共通のものを使用し、第二つなぎ材3bに長さの異なるものを使用することにより、建地の種々のスパンSに対応させることができる。なお、これに限らず、第一つなぎ材3aと第二つなぎ材3bに長さの異なるものを使用して組み合わせてもよい。
【0021】
さらに、第二つなぎ材3bの先端部(接合部)に軸方向に長い長穴20を形成し、第一つなぎ材3aの基端部(接合部)に形成したボルト穴21と前記長穴20にボルト22を挿入して固定する。長穴20の長さ分だけ伸縮自在に接続して長さαの微調整ができ、前記各スパンSにおいて、インチサイズ系統、メーターサイズ系統、建設会社固有の系統によって数10mm異なるスパン(S−α)に対応することができる。
【0022】
第一つなぎ材3aの先端部と第二つなぎ材3bの先端部は、偏平に加工されて取付板部23が形成されており、この取付板部23にグラビティロック5が挿入される取付穴24が形成されている。なお、第一つなぎ材3aと第二つなぎ材3bには養生シートの留めリング25が設けられている。
【0023】
図3、図4の図示例は、スパンSがメーターサイズで2000,1800,1500,1200,900,600 (単位mm)の6種類の場合である。なお、図4(c) の場合は、一体型のつなぎ材3としている。
【0024】
図5は、建地のスパンSの例を横方向に連続して例示し(実際にこのように配置されるのではない)、さらにインチサイズ系統、メーターサイズ系統、ある建設会社固有の系統を示したものである。図3、図4のつなぎ材3を使用することにより、スパンS2 〜S6 (1800〜600)に対応することができると共に、αの伸縮微調整によりインチサイズ系統、メーターサイズ系統、ある建設会社固有の系統に対応することができる。
【0025】
さらに、図5において、つなぎ材3を取付けるグラビティロック5を適宜選択することにより、インチサイズ系統、メーターサイズ系統、ある建設会社固有の系統で異なる一対のつなぎ材3、3の間隔Lに対応することができる。
【0026】
また、筋違4も、グラビティロック5を適宜選択することにより、インチサイズ系統、メーターサイズ系統、ある建設会社固有の系統で同じ長さの筋違4を使用することが可能となる。スパンS2 では、同じ長さの筋違4を使用することができる。スパンS3 以下では、インチサイズ系統とある建設会社固有の系統で同じ長さの筋違4を使用することができ、メーターサイズ系統では、異なる筋違4’を使用しなければならないが、用意する筋違いの種類を少なくすることができる。
【0027】
図6は、本体金具1の一例を示したものであり、取付板30と、左右一対の側板31、31と、補強板32から構成されている。取付板30にクランプ6がボルト・ナット33により固定される。このクランプ6は、いわゆる兼用クランプであり、2種類の径の建地に固定することができる。側板31には、本体アーム2の取付穴12、12に対応した固定穴34が形成されており、これら取付穴12と固定穴34に固定ピン35を挿入することにより、本体アーム2を本体金具1に固定することができる。なお、下側の固定穴34は、上の一つの固定穴34を中心とする円弧上に複数個(図示例では3個)配設されており、本体アーム2を前方に傾斜して突出する設置状態や建地側に立てて格納する格納状態等とすることができる。
【0028】
固定ピン35は、図6(d) 、(e) に示すように、L字状のピンであり、先端に離脱防止用の係止爪36が設けられている。この係止爪36は、取付穴12と固定穴34に挿入すると、自動的に落下して固定ピン35の離脱を防止するものであり、2つのピン37、38により固定ピン35に固定され、ピン38の挿入穴を大きくすることによりピン37を中心として所定角度だけ回転し、係止爪36の先端部分が出没できるようにされている。なお、この固定ピン35はワイヤ39を介して側板31に取付けられている。
【0029】
図7は、仮設足場のコーナー部における簡易養生朝顔の平面配置を示したものであり、角部の建地T1 には、直交する2本の本体アーム2のクランプ6を同一高さ位置に取付けることができない。そこで、図7(b) に示すように、クランプ6の基体6aの直交する2面にL形鋼(アングル材)からなる取付板30を取付け、このL形鋼30の二辺にそれぞれ一対の側板31、31を取付けて2つの本体金具1,1を設ければ、図7(a) に示すように、角部の建地T1 に、直交する2本の本体アーム2、2を配置することができる。
【0030】
また、コーナー部において直交する2つの仮設足場の接続部分では、隣接する建地T2 、T3 にそれぞれにクランプ6を配置することができないため、一方の建地T2 にクランプ6を固定し、このクランプ6の本体アーム2とクランプの無い支持されていない本体アーム2’とを固定する必要があるが、本体アームを円形鋼管とすることにより、本体アーム2と本体アーム2’とをダブルクランプで接続することが可能となる。
【0031】
【発明の効果】
本発明は、以上のような構成からなるので、次のような効果が得られる。
【0032】
(1) つなぎ材を、第一つなぎ材と第二つなぎ材を長さ調整可能に組み合わせて構成し、つなぎ材及び筋違の端部を本体アームに着脱自在に取付ける取付ピンを本体アームの基端部と先端部にそれぞれ複数個配設しているため、第一つなぎ材に適宜選択した第二つなぎ材を接続することにより、建地の種々のスパンに容易に対応することができる。さらに、長穴とボルトにより長さを微調整して固定することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。また、アーム軸方向に一対のつなぎ材の本体アームへの取付けも、複数個の取付ピンを適宜選択することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。さらに、筋違の本体アームへの取付けも、複数個の取付ピンを適宜選択することにより、インチサイズ系統、メーターサイズ系統、建設会社固有の系統に容易に対応することができる。以上により、比較的簡単な構成の長さ調整可能なつなぎ材と少ない種類の筋違で種々のスパンにおける各系統のスパンに容易に対応することができる。
【0033】
(2) 本体金具に従来の垂直材に代えてクランプを設けることにより、本体金具部分を簡単でコンパクトな構成とすることができると共に、仮設足場や仮囲いの建地に容易に固定することができる。
【0034】
(3) コーナー部では、1本の建地に2本の本体アームを直角に配設する必要があるが、クランプを用いることにより1つのクランプに2つの本体金具を直角配置でき、1本の建地に2本の本体アームを直角に配設することができる。
【0035】
(4) コーナー部において建地が隣接して設置される部分では、一方の建地に取付けた本体アームに、他方の建地に取付けていない本体アームを固定しなければならないが、本体アームに円形鋼管を使用することにより、両者をクランプで容易に固定することができる。
【図面の簡単な説明】
【図1】本発明の簡易養生朝顔の一例であり、(a) は側面図、(b) は平面図である。
【図2】図1の本体アームであり、(a) は平面図、(b) は側面図、(c) は端面図である。
【図3】図1のつなぎ材の種々の長さのもの(その1)を示す平面図と分解側面図である。
【図4】図1のつなぎ材の種々の長さのもの(その2)を示す平面図と分解側面図である。
【図5】建地のスパンの例を横方向に連続して例示し、インチサイズ系統、メーターサイズ系統、ある建設会社固有の系統別に示した簡易養生朝顔の平面図である。
【図6】図1の本体金具の一例を示したものであり、(a) は平面図、(b) は側面図、(c) は背面図、(d) は固定ピンの側面図、(e) は固定ピンの下面図である。
【図7】仮設足場のコーナー部における簡易養生朝顔の平面配置を示したものであり、(a) は平面図、(b) はクランプの平面図である。
【図8】従来の簡易養生朝顔を示す斜視図である。
【符号の説明】
T……建地
1……本体金具
2……本体アーム
3……つなぎ材
3a…第一つなぎ材(外管)
3b…第二つなぎ材(内管)
4……筋違
5……グラビティロック
6……クランプ
6a…基体
6b…抱持体
10……塞ぎ板
11……留めリング
12……取付穴
20……長穴
21……ボルト穴
22……ボルト
23……取付板部
24……取付穴
25……留めリング
30……取付板
31……側板
32……補強板
33……ボルト・ナット
34……固定穴
35……固定ピン
36……係止爪
37……ピン
38……ピン
39……ワイヤ
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a simple curing morning glory attached to a temporary fence or a temporary scaffolding at a construction site.
[0002]
[Prior art]
The simple curing morning glory can be installed using a temporary enclosure cloth pipe installed outside the temporary scaffolding, or can be easily installed from a building frame such as a framed scaffolding. It is used to prevent the fall of small items such as.
[0003]
As shown in FIG. 8, the conventional simple curing morning glory is composed of a body fitting 50, a body arm 51, a connecting material 52, and a strut 53. A vertical member 54 suspended from the main body metal fitting 50 is attached along the construction site T of the frame scaffold or the cloth pipe of the temporary enclosure, and is fixed by the hook bolt 55 or the clamp. The main body arm 51 is formed of a square pipe, and a base end portion thereof is fixed to the main body metal fitting 50 via a pin. The main body arm 51 can be stowed upward after completion of the operation and set in a protruding state when the operation is performed again. The ends of the connecting material 52 and the strut 53 are attached to the gravity locks 56 at both ends of the main body arm 51, and a curing sheet (not shown) is stretched thereon. When a certain span of the building site or a standard span cannot be obtained, an extendable handrail bar is used as the connecting material 52.
[0004]
Moreover, there exists patent document 1 as a prior art document relevant to this invention. The invention of Patent Document 1 is not a simple curing morning glory, but a relatively strong curing morning glory provided in a frame scaffold, and includes a laterally trapezoidal frame bracket composed of an upper chord material, a lower chord material, and a vertical material, and the tips of adjacent brackets. A flat frame is constructed by spanning horizontal members between the parts, and the base end of the upper chord material is clamped to the building of the frame scaffolding, and the base end of the lower chord material is fixed with a U-shaped hardware. ing.
[0005]
[Patent Document 1]
Japanese Patent Laid-Open No. 7-207952 [0006]
[Problems to be solved by the invention]
There are 1800,1500,1200,900,600 (unit mm) in the span of the construction site of the temporary scaffolding, and the span varies by several tens of millimeters depending on the inch size system, meter size system, and the system unique to the construction company, The connecting material 52 using the conventional telescopic handrail rod has a problem that the length adjustment is troublesome. There is also a problem that a large number of struts 53 must be prepared for each system in each span.
[0007]
Further, since the vertical member 54 is suspended from the main body metal fitting 50, there are problems such as bulkiness and troublesome attachment to the building site. Furthermore, in the corner portion, it is necessary to dispose two arms at a right angle on one building, but the main body bracket 50 with the vertical member 54 cannot be attached to one building, There was a problem with the processing of the department.
[0008]
The present invention has been made to solve the above-described problems, and the object of the present invention is to adjust the length of each system in various spans with a relatively simple length-adjustable binder and a few types of struts. Simple curing that can easily cope with the span, and can easily fix the main body bracket to the temporary scaffolding or temporary enclosure with a simple mounting member, and can also handle the corner easily. To provide morning glory.
[0009]
[Means for Solving the Problems]
Claim 1 of the present invention is a body fitting attached to a building of a temporary enclosure or a temporary scaffold, a body arm to which a base end portion is attached to the body fitting, and base end portions and tip end portions of adjacent body arms. The connecting material is a combination of the first connecting material and the second connecting material so that the length of the connecting material can be adjusted. And a plurality of mounting pins (gravity locks, etc.) for detachably attaching the connecting material and the ends of the struts to the main body arm are provided on the base end portion and the distal end portion of the main body arm. It is a morning glory.
[0010]
A second aspect of the present invention is the simple curing morning glory according to the first aspect, wherein a clamp that is fixed to the building is provided on the main body metal fitting. The main body bracket is configured by, for example, fixing a pair of left and right side plates by welding or the like to the surface (an anti-building site side) of a vertically arranged mounting plate, and inserting the base end portion of the main body arm between the pair of left and right side plates The clamps are fixed on the back surface (building side) of the mounting plate, and a pair of upper and lower clamps are disposed on the mounting plate, and are fixed to the mounting plate with bolts, nuts, and the like. As this clamp, it is preferable to use a dual-purpose clamp that can be used for two types of building diameters.
[0011]
A third aspect of the present invention is the simple curing morning glory according to the first or second aspect, wherein the main body arm is formed of a circular steel pipe. Conventionally, a square pipe has been used for the main body arm. However, by using a round pipe, a crumble can be used for the main body arm as will be described later.
[0012]
According to a fourth aspect of the present invention, in the simplified curing morning glory according to the first, second or third aspect, a second tie having a different length is detachably connected to the first tie, and the first tie It is the simple curing morning glory characterized by the connection end part of a material and a 2nd joining material being fixed so that position adjustment is possible with a long hole and a volt | bolt. For example, the first binder is a common outer tube, the second binder is an inner tube of various lengths, the distal end of the second binder is inserted into the base end of the first binder, It is possible to adapt to various spans of the building site, and by fixing with long holes and bolts, and finely adjusting the length, it can be changed to inch size system, meter size system, construction company specific system Make it available.
[0013]
In the configuration as described above, it is possible to easily cope with various spans of the building by connecting the second joining material appropriately selected to the first joining material. Further, by finely adjusting and fixing the length with a long hole and a bolt, it is possible to easily cope with an inch size system, a meter size system, and a system unique to a construction company. In addition, the attachment of a pair of connecting members to the arm of the arm in the axial direction can be easily accommodated to inch size systems, meter size systems, and systems unique to construction companies by appropriately selecting a plurality of mounting pins. it can. Furthermore, the attachment to the main body arm can be easily accommodated to an inch size system, a meter size system, or a system unique to a construction company by appropriately selecting a plurality of mounting pins. As described above, it is possible to easily cope with spans of various systems in various spans with a relatively simple length-adjustable connecting material and a few types of struts.
[0014]
Further, by providing a clamp instead of a conventional vertical member on the main body bracket, the main body bracket portion can be made simple and compact, and can be easily fixed to a temporary scaffold or a temporary enclosure building. . Also, at the corner, it is necessary to dispose two main body arms at a right angle on one building, but by using a clamp, two main body brackets can be arranged at a right angle on one clamp. Two main body arms can be arranged at right angles on the ground.
[0015]
Furthermore, in the part where the building is installed adjacent to the corner, the body arm that is not attached to the other building must be fixed to the body arm that is attached to one building, but the body arm is circular. By using a steel pipe, both can be easily fixed with a clamp.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described based on the illustrated embodiment. FIG. 1 is a side view and a plan view showing an example of a simple curing morning glory of the present invention. 2 is a plan view, a side view, and an end view showing the main body arm of FIG. 3 and 4 are a plan view and an exploded side view showing the connecting member of FIG.
[0017]
In the embodiment of FIG. 1, the simplified curing morning glory of the present invention mainly includes a main body metal 1 attached to a building T of a temporary enclosure or a temporary scaffold, and a main body arm 2 having a base end attached to the main body 1. It is comprised from the connecting material 3 which connects the base end parts and front-end | tip parts of adjacent main body arms 2 and 2, respectively, and the strut 4 arrange | positioned between the adjacent main body arms 2 and 2. FIG.
[0018]
As will be described later, the connecting material 3 is configured by combining the first connecting material 3a and the second connecting material 3b so that the length can be adjusted. An attachment pin for detachably attaching the end portion of the connecting material 3 and the streak 4 to the main body arm 2, that is, a gravity lock 5 in which a locking claw is provided on the side surface of the front end portion so that it can be protruded and retracted is A plurality of (two in the illustrated example) are provided, and the plurality of gravity locks 5 are appropriately selected to attach the connecting material 3 and the struts 4. The main body 1 is fixed to the building T by a pair of upper and lower clamps 6 and 6.
[0019]
As shown in FIG. 2, the body arm 2 is circular steel tube, gravity lock 5a at the top of the tip, 5b is protruded at intervals a 1, gravity lock 5c at the top of proximal portion, 5d interval It is projected at an a 2. A closing plate 10 is provided on the front end surface of the main body arm 2, and a plurality of fastening rings 11 for fastening the curing sheet are provided at intervals in the middle portion. At the base end of the main body arm 2, mounting holes 12 and 12 for mounting to the main body metal fitting 1 are provided.
[0020]
As shown in FIG. 3 and FIG. 4, the connecting member 3 is formed of a circular steel pipe, the first connecting member 3 a is an outer tube, the second connecting member 3 b is an inner tube, and the base end portion of the first connecting member 3 a. By inserting the tip of the second binder 3b, the integral binder 3 can be obtained. It is possible to cope with various spans S of the building by using a common one having the same length as the first joining material 3a and using a different joining material in the second joining material 3b. However, the present invention is not limited to this, and the first and second binders 3a and 3b may be combined using different lengths.
[0021]
Further, a long hole 20 is formed in the tip end portion (joint portion) of the second tie material 3b in the axial direction, and the bolt hole 21 formed in the base end portion (joint portion) of the first tie material 3a and the long hole 20 are formed. A bolt 22 is inserted into and fixed. The length α can be finely adjusted by connecting the length of the long hole 20 so that it can be expanded and contracted. In each of the spans S, spans different by several tens of millimeters depending on the inch size system, the meter size system, and the system unique to the construction company (S− α).
[0022]
The front end portion of the first tie material 3a and the front end portion of the second tie material 3b are processed flat to form a mounting plate portion 23, and the mounting hole 24 into which the gravity lock 5 is inserted into the mounting plate portion 23. Is formed. In addition, the fastening ring 25 of a curing sheet is provided in the 1st joining material 3a and the 2nd joining material 3b.
[0023]
The example shown in FIGS. 3 and 4 is a case in which the span S is a meter size of 2000, 1800, 1500, 1200, 900, 600 (unit: mm). In the case of FIG. 4 (c), the connecting member 3 is an integral type.
[0024]
FIG. 5 illustrates an example of a span S of a building site continuously in the horizontal direction (not actually arranged in this way), and further shows an inch size system, a meter size system, and a system unique to a construction company. It is shown. By using the connecting material 3 in FIGS. 3 and 4, it is possible to cope with spans S 2 to S 6 (1800 to 600) and to make an inch size system, meter size system, and certain construction by fine adjustment of α. Can handle company-specific systems.
[0025]
Further, in FIG. 5, by appropriately selecting the gravity lock 5 to which the connecting material 3 is attached, the gap L between the pair of connecting materials 3, 3 different in the inch size system, the meter size system, and a system unique to a certain construction company is supported. be able to.
[0026]
In addition, for the streak 4, by appropriately selecting the gravity lock 5, it is possible to use the streak 4 having the same length in an inch size system, a meter size system, or a system unique to a certain construction company. In span S 2 , the same length striation 4 can be used. Below span S 3 you can use the same length streak 4 for inch-size systems and a system unique to a construction company, and for meter-size systems you must use a different streak 4 '. You can reduce the type of streaking.
[0027]
FIG. 6 shows an example of the main body 1, which includes a mounting plate 30, a pair of left and right side plates 31, 31, and a reinforcing plate 32. The clamp 6 is fixed to the mounting plate 30 with bolts and nuts 33. This clamp 6 is a so-called dual-purpose clamp and can be fixed to a building with two different diameters. Fixing holes 34 corresponding to the mounting holes 12 and 12 of the main body arm 2 are formed in the side plate 31. By inserting a fixing pin 35 into these mounting holes 12 and the fixing holes 34, the main body arm 2 is attached to the main body bracket. 1 can be fixed. A plurality of (three in the illustrated example) lower fixing holes 34 are arranged on an arc centered on one upper fixing hole 34, and the main body arm 2 is inclined forward and protrudes. It can be set to an installed state or a stowed state in which it is stood on the building side.
[0028]
As shown in FIGS. 6 (d) and 6 (e), the fixing pin 35 is an L-shaped pin, and a locking claw 36 for preventing separation is provided at the tip. When the locking claw 36 is inserted into the mounting hole 12 and the fixing hole 34, it automatically drops and prevents the fixing pin 35 from being detached. The locking claw 36 is fixed to the fixing pin 35 by two pins 37, 38. By enlarging the insertion hole of the pin 38, the pin 37 is rotated by a predetermined angle around the pin 37 so that the tip end portion of the locking claw 36 can be projected and retracted. The fixing pin 35 is attached to the side plate 31 via a wire 39.
[0029]
FIG. 7 shows a plane arrangement of a simple curing morning glory in the corner portion of the temporary scaffold, and the clamps 6 of the two main body arms 2 orthogonal to each other are placed at the same height position on the corner building T 1. Can't install. Therefore, as shown in FIG. 7 (b), a mounting plate 30 made of L-shaped steel (angle material) is mounted on two orthogonal surfaces of the base body 6a of the clamp 6, and a pair of L-shaped steel 30 is attached to each of two sides. by providing the two body fitting 1, 1 attached to the side plates 31 and 31, as shown in FIG. 7 (a), Kenchi T 1 of the corner, located two body arms 2,2 orthogonal can do.
[0030]
In addition, the clamp 6 cannot be placed on the adjacent building sites T 2 and T 3 at the connecting portion of the two temporary scaffolds that are orthogonal to each other at the corner portion. Therefore, the clamp 6 is fixed to one building site T 2. It is necessary to fix the main body arm 2 of the clamp 6 and the unsupported main body arm 2 ′ without the clamp. However, the main body arm 2 and the main body arm 2 ′ can be doubled by making the main body arm a circular steel pipe. It is possible to connect with a clamp.
[0031]
【The invention's effect】
Since the present invention is configured as described above, the following effects can be obtained.
[0032]
(1) The connecting material is constructed by combining the first connecting material and the second connecting material so that the length can be adjusted, and a mounting pin for detachably attaching the connecting material and the end of the strut to the main arm is attached to the base of the main arm. Since a plurality of the end portions and the front end portions are respectively disposed, it is possible to easily cope with various spans of the building by connecting the second connecting material appropriately selected to the first connecting material. Further, by finely adjusting and fixing the length with a long hole and a bolt, it is possible to easily cope with an inch size system, a meter size system, and a system unique to a construction company. In addition, the attachment of a pair of connecting members to the arm of the arm in the axial direction can be easily accommodated to inch size systems, meter size systems, and systems unique to construction companies by appropriately selecting a plurality of mounting pins. it can. Furthermore, the attachment to the main body arm can be easily accommodated to an inch size system, a meter size system, or a system unique to a construction company by appropriately selecting a plurality of mounting pins. As described above, it is possible to easily cope with spans of various systems in various spans with a relatively simple length-adjustable connecting material and a few types of struts.
[0033]
(2) By providing a clamp instead of a conventional vertical member in the main body bracket, the main body bracket portion can be made simple and compact, and can be easily fixed to a temporary scaffolding or temporary enclosure. it can.
[0034]
(3) In the corner part, it is necessary to arrange two main body arms at a right angle on one building, but by using a clamp, two main body brackets can be arranged at a right angle on one clamp. Two main body arms can be arranged at right angles on the building.
[0035]
(4) At the part where the building is installed adjacent to the corner, the main body arm not attached to the other building must be fixed to the main body arm attached to one building. By using a circular steel pipe, both can be easily fixed with a clamp.
[Brief description of the drawings]
FIG. 1 is an example of a simple curing morning glory of the present invention, (a) is a side view and (b) is a plan view.
2 is a main body arm of FIG. 1, wherein (a) is a plan view, (b) is a side view, and (c) is an end view. FIG.
FIGS. 3A and 3B are a plan view and an exploded side view showing various lengths (part 1) of the connecting material of FIG. 1; FIGS.
FIGS. 4A and 4B are a plan view and an exploded side view showing various lengths (No. 2) of the connecting material in FIG.
FIG. 5 is a plan view of a simple curing morning glory showing examples of the span of a building site continuously in the horizontal direction and shown by an inch size system, a meter size system, and a system unique to a certain construction company.
6 shows an example of the main body fitting of FIG. 1. (a) is a plan view, (b) is a side view, (c) is a rear view, (d) is a side view of a fixing pin, ( e) is a bottom view of the fixing pin.
FIGS. 7A and 7B show a plane arrangement of a simple curing morning glory in a corner portion of a temporary scaffold, wherein FIG. 7A is a plan view and FIG. 7B is a plan view of a clamp.
FIG. 8 is a perspective view showing a conventional simple curing morning glory.
[Explanation of symbols]
T ... Building 1 ... Main body bracket 2 ... Main body arm 3 ... Connecting material 3a ... First connecting material (outer tube)
3b ... Second binder (inner pipe)
4 ... Muscle difference 5 ... Gravity lock 6 ... Clamp 6a ... Base 6b ... Holding body 10 ... Closing plate 11 ... Retaining ring 12 ... Mounting hole 20 ... Long hole 21 ... Bolt hole 22 ... Bolt 23 ... Mounting plate portion 24 ... Mounting hole 25 ... Retaining ring 30 ... Mounting plate 31 ... Side plate 32 ... Reinforcement plate 33 ... Bolt / nut 34 ... Fixing hole 35 ... Fixing pin 36 ... Locking claw 37 …… Pin 38 …… Pin 39 …… Wire

Claims (4)

仮囲いや仮設足場の建地に取付けられる本体金具と、この本体金具に基端部が取付けられる本体アームと、隣り合う本体アームの基端部同士及び先端部同士をそれぞれ連結するつなぎ材と、隣り合う本体アーム間に配設される筋違を備えた簡易養生朝顔において、
つなぎ材が、第一つなぎ材と第二つなぎ材を長さ調整可能に組み合わせて構成され、つなぎ材及び筋違の端部を本体アームに着脱自在に取付ける取付ピンが本体アームの基端部と先端部にそれぞれ複数個配設されていることを特徴とする簡易養生朝顔。
A main body fitting attached to a building of a temporary enclosure or a temporary scaffold, a main body arm to which a base end portion is attached to the main body metal fitting, a connecting material for connecting the base end portions and the front end portions of adjacent main body arms, and In the simple curing morning glory with muscles arranged between adjacent body arms,
The connecting material is configured by combining the first connecting material and the second connecting material so that the length can be adjusted, and the attaching pin for detachably attaching the connecting material and the end of the strut to the main body arm is connected to the base end portion of the main body arm. A simple curing morning glory, characterized in that a plurality of each is arranged at the tip.
請求項1に記載の簡易養生朝顔において、建地に固定されるクランプが本体金具に設けられていることを特徴とする簡易養生朝顔。The simple curing morning glory according to claim 1, wherein a clamp that is fixed to the building is provided on the main body metal fitting. 請求項1または2に記載の簡易養生朝顔において、本体アームが円形鋼管からなることを特徴とする簡易養生朝顔。The simple curing morning glory according to claim 1 or 2, wherein the main body arm is made of a circular steel pipe. 請求項1、2または3に記載の簡易養生朝顔において、第一つなぎ材に対して長さの異なる第二つなぎ材が着脱自在に接続され、かつ、第一つなぎ材と第二つなぎ材の接続端部が長穴とボルトにより位置調整可能に固定されていることを特徴とする簡易養生朝顔。The simple curing morning glory according to claim 1, 2, or 3, wherein a second tie having a different length is detachably connected to the first tie, and the first tie and the second tie are connected. A simple curing morning glory, characterized in that the end is fixed by a long hole and a bolt so that the position can be adjusted.
JP2003104998A 2003-04-09 2003-04-09 Simple curing morning glory Expired - Fee Related JP3790521B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003104998A JP3790521B2 (en) 2003-04-09 2003-04-09 Simple curing morning glory

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003104998A JP3790521B2 (en) 2003-04-09 2003-04-09 Simple curing morning glory

Publications (2)

Publication Number Publication Date
JP2004308299A JP2004308299A (en) 2004-11-04
JP3790521B2 true JP3790521B2 (en) 2006-06-28

Family

ID=33467632

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003104998A Expired - Fee Related JP3790521B2 (en) 2003-04-09 2003-04-09 Simple curing morning glory

Country Status (1)

Country Link
JP (1) JP3790521B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102879031A (en) * 2012-09-01 2013-01-16 安徽南风环境工程技术有限公司 Bracket
JP5823366B2 (en) * 2012-10-22 2015-11-25 リーラック機材株式会社 Morning glory device

Also Published As

Publication number Publication date
JP2004308299A (en) 2004-11-04

Similar Documents

Publication Publication Date Title
CA2535970C (en) Scaffold support bracket and assembly
JP6403281B2 (en) Support structure and scaffold of horizontal member in scaffold
JP3331458B2 (en) Stand bracket
JP3790521B2 (en) Simple curing morning glory
JP4042105B2 (en) Scaffolding bracket
JP6314279B1 (en) Temporary morning glory device
US20050077108A1 (en) Horizontal support member for tube and clamp scaffold assembly
JP3934773B2 (en) Dredging unit and dredging method
US6585314B2 (en) Tablet arm attachment for folding chair having ganging feature
EP0338145A1 (en) Foldable scaffolding unit
JP3222737U (en) Fixing structure of bar to support in temporary scaffold
JP3805443B2 (en) Construction material for temporary scaffolding
JP2700760B2 (en) Morning glory
JP4011436B2 (en) Handrail mounting device and handrail support
JPH089315Y2 (en) Supports attached to vertical pipes such as scaffolds
JP2000314234A (en) Device of mounting cargo receiving stage for single tube scaffolding
JP3051703B2 (en) Handrail for scaffolding
JP3046573B2 (en) Temporary seats and how to assemble them
JP2807858B2 (en) Mountable work stage
JPH0211554Y2 (en)
JP2655819B2 (en) Bounce scaffolding device for temporary scaffolds
JP2506631Y2 (en) Pillar scaffolding
JPH0246595Y2 (en)
JP3831247B2 (en) Integrated handrail frame for mounting temporary staircases and staircase openings
JPH0332675Y2 (en)

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060210

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060328

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060331

R150 Certificate of patent or registration of utility model

Ref document number: 3790521

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120407

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130407

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140407

Year of fee payment: 8

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees