JP3167384U - Blank feeding device from former to rolling machine - Google Patents

Blank feeding device from former to rolling machine Download PDF

Info

Publication number
JP3167384U
JP3167384U JP2011000820U JP2011000820U JP3167384U JP 3167384 U JP3167384 U JP 3167384U JP 2011000820 U JP2011000820 U JP 2011000820U JP 2011000820 U JP2011000820 U JP 2011000820U JP 3167384 U JP3167384 U JP 3167384U
Authority
JP
Japan
Prior art keywords
blank
pressure air
former
rolling machine
die
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2011000820U
Other languages
Japanese (ja)
Inventor
阪村 芳一
芳一 阪村
Original Assignee
株式会社阪村機械製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社阪村機械製作所 filed Critical 株式会社阪村機械製作所
Priority to JP2011000820U priority Critical patent/JP3167384U/en
Application granted granted Critical
Publication of JP3167384U publication Critical patent/JP3167384U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forging (AREA)

Abstract

【課題】フォーマーから転造機へのブランクの供給機構が簡単容易で、打痕なく確実にブランクの方向性を揃えて迅速かつ円滑に供給できるブランク供給装置を提供する。【解決手段】素材を粗から精へ成形するフォーマーから転造機へのブランク供給装置であって、フォーマー1の最終工程におけるダイ4の孔4aに、前工程で成形されたブランクAの挿通を許しかつ最終工程の後方位置に設けた転造機8の供給口部分に延びるブランク供給通路11を配設する。最終工程におけるパンチ6に高圧エアーによりブランクAを、ブランク供給通路11を介して転造機8に直接供給するための高圧エアー吐出通路12を設けると共に、吐出通路12に連通されかつ吐出通路12に高圧エアーを送り込む高圧エアー供給機13を設けた。【選択図】図1Provided is a blank supply device in which a mechanism for supplying a blank from a former to a rolling machine is simple and easy, and the direction of the blank is surely aligned without any dents, and the blank can be supplied quickly and smoothly. Kind Code: A1 A blank supply device for forming a material from coarse to fine from a former to a rolling machine, wherein a blank A formed in a previous process is inserted into a hole 4a of a die 4 in a final process of the former 1. In addition, a blank supply passage 11 extending to a supply port portion of the rolling machine 8 provided at a position behind the final step is provided. In the final step, a high-pressure air discharge passage 12 for directly supplying the blank A to the punching machine 8 through the blank supply passage 11 through the blank supply passage 11 is provided to the punch 6, and a high-pressure air discharge passage 12 is provided in the discharge passage 12. A high-pressure air supply device 13 for feeding air was provided. [Selection diagram] Fig. 1

Description

本考案は、フォーマーから転造装置へのブランク供給装置、詳しくは複数の圧造ステーションによって素材を粗から精へ成形するフォーマーで製造されたブランクを転造機に供給するためのブランク供給装置に関するものである。  The present invention relates to a blank supply device from a former to a rolling device, and more particularly to a blank supply device for supplying a blank produced by a former that forms a material from rough to fine by a plurality of forging stations to a rolling machine. is there.

各種のパーツ類を成形するフォーマーは、相対向するダイとパンチとを備えた複数の圧造ステーションで粗から精に素材を圧造成形するものであるが、たとえば軸状のブランクの外周部分に溝やねじなどが形成されたパーツ部品を成形する際には、通常、素材から所定形状のブランクを成形するフォーマーと共に後工程で溝切りやねじ切りを行うために転造機が用いられる。その場合、フォーマーの最終圧造ステーションで所定の形状に成形されたブランクは最終段のダイから押し出されたのち、ダイ下方に位置するシュータや搬送ベルトなどの搬送手段上に落下され、この搬送装置を介して搬送され、かつ整列されたのち転造機に送りこまれて溝切りやねじ切りが施されている。  A former that molds various parts is forging a material from rough to fine at a plurality of forging stations equipped with opposing dies and punches. When forming a part part in which a screw or the like is formed, a rolling machine is usually used for grooving or threading in a subsequent process together with a former that forms a blank having a predetermined shape from a material. In that case, the blank formed into a predetermined shape at the final forging station of the former is pushed out of the final stage die and then dropped onto a transport means such as a shooter or a transport belt located below the die, and this transport device is After being conveyed and aligned, they are fed into a rolling machine for grooving and threading.

実開平06−41941公報  Japanese Utility Model Publication No. 06-41941

しかし、上記した従来のフォーマーから転造機へのブランクの供給方法では、ブランクが最終段のダイから押し出されシュータや搬送ベルトなどの搬送手段上に落下したときに、落下衝撃によって打痕が入り、品質が低下する虞があるし、また、搬送手段上に落下したブランクを整列させたのちにその方向を揃えながら転造機に送り込む必要があるため、その供給機構や供給経路が非常に複雑となり、その上、その供給が迅速かつ円滑に行えない問題を有していた。  However, in the above-described conventional method of supplying a blank from a former former to a rolling machine, when the blank is pushed out from the final stage die and dropped onto a conveyance means such as a shooter or a conveyance belt, a dent is caused by a drop impact, There is a risk that the quality may deteriorate, and it is necessary to send the blanks that have fallen on the transport means to the rolling machine while aligning the directions, so the supply mechanism and supply path become very complicated, In addition, there is a problem that the supply cannot be performed quickly and smoothly.

そこで本考案は、上記の打痕発生をなくすと共に、フォーマーから転造機へのブランクの供給機構が簡単容易で、しかも、確実にブランクの方向性を揃えて迅速かつ円滑に供給することができるフォーマーから転造機へのブランク供給装置の提供を課題とする。  Accordingly, the present invention eliminates the occurrence of the above-mentioned dents, and a simple and easy supply mechanism of blanks from the former to the rolling machine, and also can ensure that the direction of the blanks are aligned and can be supplied quickly and smoothly. An object of the present invention is to provide a blank supply device from a machine to a rolling machine.

上記した問題を解決するため、本願の請求項1記載の考案は、複数の圧造ステーションによって素材を粗から精へ成形するフォーマーから転造機へのブランク供給装置であって、フォーマーの最終工程におけるダイの孔に、前工程で所定形状に成形されたブランクの挿通を許しかつ最終工程の後方位置に設けた転造機の供給口部分に延びるブランク供給通路を配設する一方、最終工程におけるパンチに高圧エアーによりブランクを、上記ブランク供給通路を介して転造機に直接供給するための高圧エアー吐出通路を設けると共に、この吐出通路に連通されかつ該吐出通路に高圧エアーを送り込む高圧エアー供給機を設けたことを特徴とする。  In order to solve the above-described problem, a device according to claim 1 of the present application is a blank feeding device from a former to a rolling machine that forms a material from coarse to fine by a plurality of forging stations, and includes a die in a final process of the former. In this hole, a blank supply passage that allows insertion of a blank formed into a predetermined shape in the previous process and extends to the feed port portion of the rolling machine provided at the rear position of the final process is disposed, while a high pressure is applied to the punch in the final process. A high-pressure air discharge passage is provided for supplying a blank by air directly to the rolling machine via the blank supply passage, and a high-pressure air supply device is provided that communicates with the discharge passage and feeds the high-pressure air into the discharge passage. It is characterized by that.

また、本願の請求項2記載の考案は、請求項1記載の高圧エアー供給機に、最終工程のパンチによるブランクのダイの孔内への前進移動が終わったタイミングで高圧エアーの吐出を開始し、パンチがダイから後退するタイミングで高圧エアーの吐出を停止する吐出制御機構を設けたことを特徴とする。  In addition, the device according to claim 2 of the present application starts discharging high-pressure air to the high-pressure air supply device according to claim 1 at the timing when the forward movement into the hole of the blank die by the punch in the final process is finished. A discharge control mechanism for stopping high-pressure air discharge at the timing when the punch moves backward from the die is provided.

本考案のフォーマーから転造機へのブランク供給装置によれば、上記した構成により所定形状に成形されたブランクを、最終工程のパンチから吐出される高圧エアーにより最終工程のダイに設けられたブランク供給通路を介し確実に方向性を揃えて転造機に直接供給できる。これにより従来のような打痕発生をなくすと共に、フォーマーから転造機へのブランクの供給機構を簡素化し、しかも、確実に方向性を揃えて迅速かつ円滑に供給することができる。  According to the blank supply device from the former of the present invention to the rolling machine, the blank formed into the predetermined shape by the above-described configuration is supplied to the blank of the final process by the high pressure air discharged from the punch of the final process. It can be directly supplied to the rolling machine with a uniform direction through the passage. This eliminates the occurrence of dents as in the prior art, simplifies the mechanism for supplying blanks from the former to the rolling machine, and ensures that the direction is aligned and can be supplied quickly and smoothly.

また、高圧エアー供給機に、最終工程のパンチによるブランクのダイの孔内への前進移動が終わったタイミングで高圧エアーの吐出を開始し、パンチがダイから後退するタイミングで高圧エアーの吐出を停止する吐出制御機構を設けているから、最終工程のパンチによるブランクのダイの孔内への押し込みが通常通り良行に行えると共に、パンチがダイから後退するタイミングで高圧エアーの吐出を停止することになるので、高圧エアーがダイの前面周りに吹き出して素材移送チャックによるブランクの移送などに悪影響を与えるといったことがない。  In addition, high-pressure air supply begins to discharge high-pressure air at the timing when the forward movement of the blank die into the hole of the die is finished, and stops high-pressure air discharge when the punch moves backward from the die. Since the discharge control mechanism is provided, the blank die can be pushed into the hole of the die by the punch in the final process as usual, and the discharge of the high-pressure air is stopped when the punch moves backward from the die. Therefore, the high-pressure air does not blow around the front surface of the die and does not adversely affect the blank transfer by the material transfer chuck.

本考案に係るフォーマーから転造機へのブランク供給装置の一部省略縦断側面図である。It is a partially omitted vertical side view of a blank supply device from a former to a rolling machine according to the present invention. 同ブランク供給装置の動作を説明する要部の縦断側面図である。It is a vertical side view of the principal part explaining operation | movement of the blank supply apparatus.

以下本考案の実施の形態を図に基づいて説明する。  Embodiments of the present invention will be described below with reference to the drawings.

図1及び図2は、本考案に係るフォーマーから転造機へのブランク供給装置を示し、フォーマー1には、機台2の所定位置にダイブロック3が設けられ、ダイブロック3に複数のダイ(図では最終のダイのみ示す)4が装備される。このフォーマー1においては周知のように、上記の各ダイ4に対応してラム5がダイブロック3の前面位置は位置されると共に、ラム5に各ダイ4に対応して同数のパンチ(図では最終のパンチのみ示す)6が設けられることにより、各ダイ4とパンチ6とによって複数の圧造ステーションが形成されている。
そして、ラム5の前進によって各圧造ステーションにおいて棒状の切断素材が順次圧造成形され、図に示すような両端部が小径で中間部が大径となる軸状のブランクAになるように構成されている。なお、図示していないが、隣接する圧造ステーション間にわたって切断素材を移送するための素材移送用チャック(図では最終のチャックのみ示す)7がダイブロック3側に備えられている。また、転造機8は、固定平ダイス8aと移動平ダイス8bを備え、フォーマー1で成形された軸状のブランクAの大径部の外周に複数の環状溝a…aを形成するもので、フォーマー1の最終工程のダイ4後方位置に配設される。
1 and 2 show a blank supply device from a former to a rolling machine according to the present invention. The former 1 is provided with a die block 3 at a predetermined position of a machine base 2, and a plurality of dies ( (Only the last die is shown in the figure) 4 is equipped. As is well known in the former 1, the ram 5 is positioned at the front surface of the die block 3 corresponding to each die 4 and the same number of punches (corresponding to each die 4 in the ram 5) By providing 6 (only the final punch is shown), each die 4 and punch 6 form a plurality of forging stations.
Then, as the ram 5 advances, rod-shaped cutting materials are sequentially forged at each forging station, and are configured to be an axial blank A with both ends having a small diameter and an intermediate portion having a large diameter as shown in the figure. Yes. Although not shown, a material transfer chuck (only the final chuck is shown in the figure) 7 for transferring a cutting material between adjacent forging stations is provided on the die block 3 side. The rolling machine 8 includes a fixed flat die 8a and a moving flat die 8b, and forms a plurality of annular grooves a ... a on the outer periphery of the large-diameter portion of the shaft-shaped blank A formed by the former 1. It is disposed at a position behind the die 4 in the final process of the former 1.

そして、図1に示すようにフォーマー1の最終工程に、フォーマー1から転造機8へブランクAを供給するブランク供給装置10が設けられている。ブランク供給装置10としては、フォーマー1の最終工程におけるダイ4の孔4aに、前工程にて成形された軸状のブランクAの挿通を許しかつ最終工程の後方位置に設けた転造機8の供給口80部分に延びるパイプ管からなるブランク供給通路11を配設する一方、最終工程におけるパンチ6に高圧エアーによりブランクAを、上記ブランク供給通路11を介して転造機8に供給するための高圧エアー吐出通路12を設けると共に、この吐出通路12に連通されかつ該吐出通路12に高圧エアーを送り込むコンプレッサーなどの高圧エアー供給機13を設けたものである。  As shown in FIG. 1, a blank supply device 10 that supplies blank A from the former 1 to the rolling machine 8 is provided in the final process of the former 1. As the blank supply device 10, supply of the rolling machine 8 that allows the insertion of the shaft-shaped blank A formed in the previous process into the hole 4a of the die 4 in the final process of the former 1 and is provided at the rear position of the final process. While providing a blank supply passage 11 made of a pipe pipe extending to the port 80 portion, high pressure air for supplying the blank A to the punch 6 in the final process by high pressure air to the rolling machine 8 through the blank supply passage 11. A discharge passage 12 is provided, and a high-pressure air supply device 13 such as a compressor that communicates with the discharge passage 12 and feeds high-pressure air into the discharge passage 12 is provided.

また、高圧エアー供給機13には、最終工程のパンチ6によるブランクAのダイ4の孔4a内への前進移動が終わったタイミングで高圧エアーの吐出を開始し、パンチ6がダイ4から後退するタイミングで高圧エアーの吐出を停止する吐出制御機構14を設けている。この吐出制御機構14は、ラム5の前進移動終了を検出するセンサー15からの検出信号に基づいて高圧エアー供給機13を制御するもので、前進移動が終わったタイミングで高圧エアーの吐出を開始させ、パンチ6がダイ4から後退し始めたタイミングで高圧エアーの吐出を停止させるように高圧エアー供給機13を制御するようになされている。  The high-pressure air supply 13 starts discharging high-pressure air at the timing when the forward movement of the blank A into the hole 4 a of the die 4 by the punch 6 in the final process is finished, and the punch 6 moves backward from the die 4. A discharge control mechanism 14 that stops the discharge of high-pressure air at a timing is provided. The discharge control mechanism 14 controls the high-pressure air supply unit 13 based on a detection signal from a sensor 15 that detects the end of forward movement of the ram 5, and starts discharging high-pressure air at the timing when the forward movement ends. The high pressure air supply unit 13 is controlled so as to stop the discharge of the high pressure air at the timing when the punch 6 starts to retract from the die 4.

次に、上記したブランク供給装置の作用について説明する。  Next, the operation of the above-described blank supply device will be described.

まず、フォーマー1の各圧造ステーションにおいて棒状の切断素材が順次圧造成形され、両端部が小径で中間部が大径となった軸状のブランクAを、図2に示すように最終工程のダイ4前方に素材移送チャック7により移送する。次に、パンチ6が前進してブランクAを図1に示すようにダイ4内に押し込む。そして、このパンチ6の前進移動が終わったタイミングで、パンチ6の吐出通路12から高圧エアー供給機13による高圧エアーの吐出が開始される。これにより、高圧エアーによりブランクAを、ダイ4に設けられたブランク供給通路11を介して転造機8に直接供給する。その後、転造機8に送られたブランクAは固定平ダイス8aと移動平ダイス8bにて大径部の外周に複数の溝a…aが形成され、パーツ部品が完成される。  First, in each forging station of the former 1, rod-shaped cutting materials are sequentially forged, and a shaft-shaped blank A having a small diameter at both ends and a large diameter at the middle portion is used as a final die 4 as shown in FIG. The material is transferred forward by the material transfer chuck 7. Next, the punch 6 advances and pushes the blank A into the die 4 as shown in FIG. Then, at the timing when the forward movement of the punch 6 is finished, discharge of the high pressure air from the discharge passage 12 of the punch 6 by the high pressure air supply machine 13 is started. Thereby, the blank A is directly supplied to the rolling machine 8 via the blank supply passage 11 provided in the die 4 by high-pressure air. Thereafter, the blank A sent to the rolling machine 8 is formed with a plurality of grooves a ... a on the outer periphery of the large-diameter portion by the fixed flat die 8a and the moving flat die 8b, and the parts are completed.

このように、本考案のブランク供給装置10によれば、前工程で軸状に成形されたブランクAを、最終工程のパンチ6から吐出される高圧エアーにより最終工程のダイ4に設けられたブランク供給通路11を介し確実に方向性を揃えて転造機8に直接供給できる。その結果、従来のような打痕発生をなくすと共に、フォーマー1から転造機8へのブランクAの供給機構を簡素化し、しかも、確実に方向性を揃えて迅速かつ円滑に供給することができる。  As described above, according to the blank supply device 10 of the present invention, the blank A formed in the shaft shape in the previous process is provided on the die 4 in the final process by the high-pressure air discharged from the punch 6 in the final process. It is possible to supply directly to the rolling machine 8 with the direction being surely aligned through the supply passage 11. As a result, it is possible to eliminate the occurrence of dents as in the prior art, simplify the supply mechanism of the blank A from the former 1 to the rolling machine 8, and reliably and promptly supply the blank A with uniform orientation.

また、高圧エアー供給機13には、最終工程のパンチ6によるブランクAのダイ4の孔4a内への前進移動が終わったタイミングで高圧エアーの吐出を開始し、パンチ6がダイ4から後退するタイミングで高圧エアーの吐出を停止する吐出制御機構14を設けているから、最終工程のパンチ6によるブランクAのダイ4の孔4a内への押し込みが通常通り良行に行えると共に、パンチ6がダイ4から後退するタイミングで高圧エアーの吐出を停止することになるので、高圧エアーがダイ4の前面周りに吹き出して素材移送チャックによるブランクAの移送などに悪影響を与えるといったことを防止できる。  The high-pressure air supply 13 starts discharging high-pressure air at the timing when the forward movement of the blank A into the hole 4 a of the die 4 by the punch 6 in the final process is finished, and the punch 6 moves backward from the die 4. Since the discharge control mechanism 14 that stops the discharge of the high-pressure air at the timing is provided, the punch 6 in the final process can be pushed into the hole 4a of the die 4 in the blank 4 as usual, and the punch 6 can be used in the die 4 as usual. Since the discharge of the high-pressure air is stopped at the timing of retreating, the high-pressure air can be prevented from blowing around the front surface of the die 4 and adversely affecting the transfer of the blank A by the material transfer chuck.

上記した実施の形態では、転造機8により軸状のブランクAの外周に溝aを形成する場合について説明したけれども、この他転造機8により適宜形状のブランクの外周にねじなどを形成する場合であってもよいこと勿論である。  In the above-described embodiment, the case where the groove a is formed on the outer periphery of the shaft-shaped blank A by the rolling machine 8 has been described. However, in this case, a screw or the like is formed on the outer periphery of the appropriately shaped blank by the rolling machine 8. Of course there may be.

1 フォーマー
4 ダイ
6 パンチ
8 転造機
9 切断ナイフ
10 ブランク供給装置
11 ブランク供給通路
12 高圧エアー吐出通路
13 高圧エアー供給機
14 吐出制御装置
A ブランク
DESCRIPTION OF SYMBOLS 1 Former 4 Die 6 Punch 8 Rolling machine 9 Cutting knife 10 Blank supply device 11 Blank supply passage 12 High-pressure air discharge passage 13 High-pressure air supply device 14 Discharge control device A Blank

Claims (2)

素材を粗から精へ成形するフォーマーから転造機へのブランク供給装置であって、フォーマーの最終工程におけるダイの孔に、前工程で所定形状に成形されたブランクの挿通を許しかつ最終工程の後方位置に設けた転造機の供給口部分に延びるブランク供給通路を配設する一方、最終工程におけるパンチに高圧エアーによりブランクを、上記ブランク供給通路を介して転造機に直接供給するための高圧エアー吐出通路を設けると共に、この吐出通路に連通されかつ該吐出通路に高圧エアーを送り込む高圧エアー供給機を設けたことを特徴とするフォーマーから転造機へのブランク供給装置。  A blank feeding device from a former to a rolling machine that forms a raw material from coarse to fine, and allows insertion of a blank formed in a predetermined shape in the previous process into the die hole in the final process of the former and behind the final process. High-pressure air discharge for supplying a blank with high-pressure air to the punch in the final process and supplying the blank directly to the rolling machine through the blank supply passage, while providing a blank supply passage extending to the feed port portion of the rolling machine provided at the position A blank supply device from a former to a rolling machine, characterized in that a high-pressure air supply device is provided which is provided with a passage and which is connected to the discharge passage and feeds high-pressure air into the discharge passage. 高圧エアー供給機に、最終工程のパンチによるブランクのダイの孔内への前進移動が終わったタイミングで高圧エアーの吐出を開始し、パンチがダイから後退するタイミングで高圧エアーの吐出を停止する吐出制御機構を設けたことを特徴とする請求項1記載のフォーマーから転造機へのブランク供給装置。  Discharge that starts high-pressure air discharge at the timing when the forward movement of the blank die into the hole of the die is finished by the punch in the final process and stops high-pressure air discharge when the punch moves backward from the die. 2. A blank feeding device from a former to a rolling machine according to claim 1, further comprising a control mechanism.
JP2011000820U 2011-01-31 2011-01-31 Blank feeding device from former to rolling machine Expired - Fee Related JP3167384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011000820U JP3167384U (en) 2011-01-31 2011-01-31 Blank feeding device from former to rolling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011000820U JP3167384U (en) 2011-01-31 2011-01-31 Blank feeding device from former to rolling machine

Publications (1)

Publication Number Publication Date
JP3167384U true JP3167384U (en) 2011-04-21

Family

ID=54878475

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011000820U Expired - Fee Related JP3167384U (en) 2011-01-31 2011-01-31 Blank feeding device from former to rolling machine

Country Status (1)

Country Link
JP (1) JP3167384U (en)

Similar Documents

Publication Publication Date Title
US3222765A (en) Method for producing welded disk wheels
US8485013B2 (en) Method and tooling for headed pilot pointed bolts
PH12015500575B1 (en) Precision forged cartridge case
CN107214518A (en) A kind of copper rod forges trimming equipment automatically
CN105665612A (en) Screw heading machine
CN107186117A (en) A kind of ring continuous bend former
JP2008168963A (en) Work transportation passage length change-over mechanism
US7975522B2 (en) Fastener manufacturing assembly and method
JP3167384U (en) Blank feeding device from former to rolling machine
CN104014702B (en) A kind of processing unit (plant) of uniform internal diameter hollow shaft
KR20200087019A (en) Manufacturing apparatus and manufacturing method of gas cartridge by multi-stage mold system
US9616476B2 (en) Device and method for rolling of pipe blanks
CN102514229B (en) Blowing device of multi-station pressure machine
KR101583390B1 (en) Dual sided and dual process bandolier
KR101872936B1 (en) A method of manufacturing a stud welding pin
CN204975016U (en) High -efficient automatic automobile parts mould
KR101592253B1 (en) Manufactuirng method of glow plug housing with extra long hollow hole
JP2012179652A (en) Device for treating terminal of wire in former
US2042375A (en) Machine for making button backs and the like
KR102463749B1 (en) Method and multi-stage press for manufacturing forming parts
JP2013237087A (en) Metal sheet press working method
CN107598582A (en) A kind of integrated equipment for machine for rolling parts of being remained silent for nut self-piercing riveting
JP3947821B2 (en) Inclusive molding former of different materials
JP5603158B2 (en) Horizontal forging machine
JP2008087048A (en) Workpiece conveying apparatus

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees