CN211769725U - A compensating beam for hoisting large-scale feed bin - Google Patents

A compensating beam for hoisting large-scale feed bin Download PDF

Info

Publication number
CN211769725U
CN211769725U CN202020123459.1U CN202020123459U CN211769725U CN 211769725 U CN211769725 U CN 211769725U CN 202020123459 U CN202020123459 U CN 202020123459U CN 211769725 U CN211769725 U CN 211769725U
Authority
CN
China
Prior art keywords
steel pipes
hoisting
pull rod
steel pipe
core plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020123459.1U
Other languages
Chinese (zh)
Inventor
刘胜峰
娄战士
张永昌
赵慧霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Eleventh Chemical Construction Co Ltd
Original Assignee
China Eleventh Chemical Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Eleventh Chemical Construction Co Ltd filed Critical China Eleventh Chemical Construction Co Ltd
Priority to CN202020123459.1U priority Critical patent/CN211769725U/en
Application granted granted Critical
Publication of CN211769725U publication Critical patent/CN211769725U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model belongs to the technical field of the chemical industry feed bin installation, specifically disclose a compensating beam for hoisting large-scale feed bin, including setting up in the circular well core plate that compensating beam central point put, set up in a plurality of support steel pipes of well core plate lower part and well core plate fixed connection, a plurality of support steel pipes are circular radial evenly distributed along well core plate centre of a circle, still be equipped with the pull rod steel pipe between per two adjacent support steel pipes, every supports steel pipe top surface and bottom surface position and evenly is equipped with the board-type lug of a plurality of compensating beams along supporting steel pipe length direction, this compensating beam has simple structure, high durability and convenient operation, easy dismouting, convenient moving's advantage, the difficult problem of hoisting group to major diameter thin wall shell ring or cone has.

Description

A compensating beam for hoisting large-scale feed bin
Technical Field
The utility model belongs to the technical field of the chemical industry feed bin installation, especially, relate to a compensating beam for hoisting large-scale feed bin.
Background
In petrochemical engineering construction, a storage bin for storing solid particles of raw materials of a chemical device cannot be manufactured in a factory due to the fact that the diameter of a transport vehicle is large (the general diameter is more than 10 m), and only can be assembled, welded and installed on site, when the storage bin for storing the solid particles with the large diameter is manufactured on site, the problems that the equipment diameter is large, the cylinder wall is thin, the rigidity of a cylinder or a cone is small, and the assembling difficulty is large are often encountered, for example, when the diameter of a cylinder section of the equipment is phi 15000mm, the height is 1.5-2 m, the wall thickness is 6mm at the thinnest, the weight of a single piece after the assembly is not more than 40 tons, and when the two sections of the cylinder body are assembled, the allowable deviation of the levelness, the; when the hoisting rigging is selected, the number design and the position of the hoisting points are designed, and whether the hoisting rigging is selected reasonably and directly influences the deformation problem of the cylinder or the cone in the assembling process, and when the cone is assembled, the diameter of the equipment is smaller and smaller, and a plurality of balance beams matched with the various diameters of the cone are needed.
Disclosure of Invention
The utility model aims at providing a compensating beam for hoisting large-scale feed bin has solved feed bin shell ring and the higher problem of cone group to the required quality, and simple structure, safe and reliable, be suitable for multiple diameter shell ring and cone group to using.
In order to achieve the above purpose, the utility model adopts the technical scheme that:
the utility model provides a compensating beam for hoisting large-scale feed bin, is including setting up in the circular well core plate of compensating beam central point and putting, sets up in a plurality of support steel pipes of well core plate lower part and well core plate fixed connection, and a plurality of support steel pipes are circular radial evenly distributed along well core plate centre of a circle, still is equipped with the pull rod steel pipe between per two adjacent support steel pipes, evenly is equipped with a plurality of plate-type lugs of compensating beam along supporting steel pipe length direction on every support steel pipe, the position all is equipped with the lewis hole about the plate-type lug of compensating beam.
Furthermore, a plurality of pull rod steel pipes which are arranged in parallel are arranged between every two adjacent supporting steel pipes.
Furthermore, the number of the support steel pipes is 8, two pull rod steel pipes which are arranged in parallel are arranged between every two adjacent support steel pipes, and the pull rod steel pipes are welded on the support steel pipes in a saddle type.
Further, the length of the supporting steel pipe is larger than the radius of the storage bin.
The utility model has the advantages that:
1. the balance beam has the advantages of simple structure, convenient operation, easy disassembly and assembly and convenient movement, and solves the problem of assembling a large-diameter thin-wall cylindrical section or cone by hoisting;
2. the balance beam hoisting method is simple, safe and reliable, and the balance beam can bear radial component force generated by inclined hoisting, so that deformation generated by the radial force borne by equipment during hoisting is avoided;
3. because the utility model is provided with a plurality of balance beam plate type lifting lugs on the supporting steel pipe, the structure is suitable for the assembly of cylinder sections and cones with various diameters, can be put into use at one time, completes the assembly and hoisting of the cylinder sections and the cones with various diameters, can be used repeatedly, improves the stress condition of the lifting lugs, enhances the safety and reliability during hoisting, and prevents the component from dangerous deformation;
4. the utility model discloses reduce the height of lifting by crane of davit, shortened and binded the time of lifting by crane equipment, improved efficiency.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a reference diagram of the usage state of the present invention.
1. A center plate; 2. supporting the steel pipe; 3. a pull rod steel pipe; 4. the balance beam plate type lifting lug; 5. a plate-type lifting lug; 6. a snap ring; 7. a steel cord.
Detailed Description
As shown in the figure, the balance beam for hoisting the large-scale storage bin comprises a circular central plate 1 arranged at the central position of the balance beam, and a plurality of supporting steel pipes 2 which are arranged at the lower part of the central plate 1 and fixedly connected with the central plate 1, wherein the supporting steel pipes 2 are uniformly distributed along the circle center of the central plate 1 in a circular radial manner, a pull rod steel pipe 3 is also arranged between every two adjacent supporting steel pipes 2, a plurality of balance beam plate type lifting lugs 4 are uniformly arranged on each supporting steel pipe 2 along the length direction of the supporting steel pipe 2, lifting holes are formed in the upper and lower positions of each balance beam plate type lifting lug 4, so that the lifting of equipment with various different diameters can be facilitated, a plurality of parallel pull rod steel pipes 3 are arranged between every two adjacent supporting steel pipes 2, and the arrangement of the pull rod steel pipes 3 plays a role of reinforcing ribs and; the number of the support steel pipes 2 is 8, two pull rod steel pipes 3 which are arranged in parallel are arranged between every two adjacent support steel pipes 3, the pull rod steel pipes 3 are welded on the support steel pipes 2 in a saddle mode, and the length of each support steel pipe 2 is larger than the radius of the storage bin.
During the specific use, at first on waiting to lift by crane the board-like lug of welding equipment on the equipment, on-the-spot preparation, guarantee that lug pinhole and the board-like lug 4 of compensating beam are arranged unanimously from top to bottom, guarantee that the steel wire atress back is perpendicular, do not harm equipment, earlier with a plurality of wire rope of lifting by crane respectively with every compensating beam board-like lug 4 that supports 2 top surfaces of steel pipe through the ligature of snap ring 6 fixed, then will support 2 bottom surfaces of steel pipe compensating beam board-like lugs 4 and wait to lift by crane and connect respectively with snap ring 6 on the board-like lug 5 on the equipment, the same wire rope 7 of many reuse length will support 2 bottom surfaces of steel pipe compensating beam board-like lugs 4's snap ring 6 and rather than the position on the board-like lug 5.

Claims (4)

1. The utility model provides a compensating beam for hoisting large-scale feed bin which characterized in that: the steel tube type lifting device comprises a circular center plate arranged at the center of a balance beam, and a plurality of supporting steel tubes arranged at the lower part of the center plate and fixedly connected with the center plate, wherein the supporting steel tubes are in circular radial uniform distribution along the center of the center plate, a pull rod steel tube is further arranged between every two adjacent supporting steel tubes, a plurality of balance beam plate type lifting lugs are uniformly arranged on each supporting steel tube along the length direction of the supporting steel tube, and lifting holes are formed in the upper position and the lower position of each balance beam plate type lifting lug.
2. The equalizing beam for hoisting the large-sized storage bin according to claim 1, wherein: a plurality of pull rod steel pipes which are arranged in parallel are arranged between every two adjacent supporting steel pipes.
3. The equalizing beam for hoisting the large-sized storage bin according to claim 2, wherein: the number of the support steel pipes is 8, two pull rod steel pipes which are arranged in parallel are arranged between every two adjacent support steel pipes, and the pull rod steel pipes are welded on the support steel pipes in a saddle type.
4. The equalizing beam for hoisting the large-sized storage bin according to claim 3, wherein: the length of the supporting steel pipe is larger than the radius of the storage bin.
CN202020123459.1U 2020-01-19 2020-01-19 A compensating beam for hoisting large-scale feed bin Active CN211769725U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020123459.1U CN211769725U (en) 2020-01-19 2020-01-19 A compensating beam for hoisting large-scale feed bin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020123459.1U CN211769725U (en) 2020-01-19 2020-01-19 A compensating beam for hoisting large-scale feed bin

Publications (1)

Publication Number Publication Date
CN211769725U true CN211769725U (en) 2020-10-27

Family

ID=72894565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020123459.1U Active CN211769725U (en) 2020-01-19 2020-01-19 A compensating beam for hoisting large-scale feed bin

Country Status (1)

Country Link
CN (1) CN211769725U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118125274A (en) * 2024-04-10 2024-06-04 山西阳煤化工机械(集团)有限公司 Top cover type lifting device for thin-wall equipment and processing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118125274A (en) * 2024-04-10 2024-06-04 山西阳煤化工机械(集团)有限公司 Top cover type lifting device for thin-wall equipment and processing method thereof

Similar Documents

Publication Publication Date Title
CN201573764U (en) Adjustable buttress device
CN211769725U (en) A compensating beam for hoisting large-scale feed bin
CN102001579B (en) Lifting appliance for lifting steel lining of containment vessel in nuclear power station
CN100590206C (en) Revolving furnace integral parallel move hydraulic pressure fallback construction method
CN110273039B (en) Blast furnace surrounding pipe hoisting structure and installation method thereof
CN114293475B (en) Split ring sleeving construction method for variable-section large-section pier tower reinforcement cage segment
CN213351278U (en) Lifting device for flip-chip welding of tank wall of vertical storage tank
CN110963408B (en) Hoisting method for replacing high-altitude vertical equipment
CN210884876U (en) Hoisting tool for marine low-speed diesel engine cylinder liner
CN215558278U (en) Nuclear power station steel lining frustum hoisting device
CN114875909B (en) Offshore wind power jacket positioning pile construction method
CN202643086U (en) Hoisting tool of hydroxylation reactor
CN217780544U (en) Center post handling frock
CN217194925U (en) Assembly fixture for reinforcing back ring of cylinder sleeve of large-cylinder-diameter low-speed diesel engine
CN110757398B (en) Baffle rod tube bundle propeller and construction method thereof
CN209875384U (en) Novel wind power tower cylinder convenient to build equipment
CN103924811A (en) Method for manufacturing large cylindrical material storing tank
CN213290051U (en) Graphite shell ring splicing apparatus
CN206128606U (en) Platform is used in extra -large -size polygon coal bunker crowd's tied in a bundle cone steel coal scuttle installation
CN215326475U (en) Tail lifting lug structure suitable for thin-wall slender equipment
CN216940240U (en) Ship rapid carrying and supporting structure
CN215854589U (en) Hoisting brace rod structure for marine ultra-long steel pipe pile
CN219885446U (en) Hoisting stay bar for large-span large-tonnage structure
CN218757982U (en) Reinforced concrete column ring plate node structure
CN212609007U (en) Detachable bearing type balance beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant