CN202900175U - Pressure measuring well completion pipe string for suspension pressure gauge of gas storage - Google Patents
Pressure measuring well completion pipe string for suspension pressure gauge of gas storage Download PDFInfo
- Publication number
- CN202900175U CN202900175U CN 201220366128 CN201220366128U CN202900175U CN 202900175 U CN202900175 U CN 202900175U CN 201220366128 CN201220366128 CN 201220366128 CN 201220366128 U CN201220366128 U CN 201220366128U CN 202900175 U CN202900175 U CN 202900175U
- Authority
- CN
- China
- Prior art keywords
- pipe
- oil pipe
- gas storage
- pressure
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000725 suspension Substances 0.000 title claims description 8
- 210000002445 nipple Anatomy 0.000 claims abstract description 14
- 238000009530 blood pressure measurement Methods 0.000 claims abstract description 11
- 239000007788 liquid Substances 0.000 claims description 5
- 238000003801 milling Methods 0.000 claims description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 6
- 239000012530 fluid Substances 0.000 abstract description 5
- 238000000034 method Methods 0.000 abstract description 4
- 238000004458 analytical method Methods 0.000 abstract description 3
- 230000001681 protective effect Effects 0.000 abstract description 3
- 238000004873 anchoring Methods 0.000 abstract description 2
- 238000007789 sealing Methods 0.000 abstract description 2
- 238000012360 testing method Methods 0.000 abstract description 2
- 238000002347 injection Methods 0.000 abstract 2
- 239000007924 injection Substances 0.000 abstract 2
- 235000017166 Bambusa arundinacea Nutrition 0.000 abstract 1
- 235000017491 Bambusa tulda Nutrition 0.000 abstract 1
- 241001330002 Bambuseae Species 0.000 abstract 1
- 235000015334 Phyllostachys viridis Nutrition 0.000 abstract 1
- 239000011425 bamboo Substances 0.000 abstract 1
- 239000007789 gas Substances 0.000 description 16
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 2
- 241000935974 Paralichthys dentatus Species 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000003345 natural gas Substances 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 239000003209 petroleum derivative Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a gas storage hangs pressure gauge pressure measurement well completion tubular column, shut off, protective case and monitor well bottom pressure in succession in order to realize the pit fast and design, its top-down by oil pipe, flowing nipple joint A, subsurface safety valve, flowing nipple joint B, oil pipe, circulation sliding sleeve, oil pipe, the sealed assembly of anchoring, the permanent packer of hydraulic pressure seat seal, mill and extend a section of thick bamboo, oil pipe, shutoff seat and connect, oil pipe, perforated pipe, hang and connect and the horn mouth is constituteed. After the pipe column is put into the gas storage reservoir injection and production well, the requirements of quick turn-off and protection of the injection and production well can be met, a circulation channel of fluid in the well is established, the upper part and the lower part of the pipe column are isolated mutually, procedures such as sealing pressure test and packer setting are completed, and technical support is provided for later-stage snubbing operation. The pipe column is matched with the hanging and seating joint, so that the underground electronic pressure gauge can be conveniently fished, the underground dynamic pressure measurement is implemented, and technical measures are provided for the safe operation analysis of the gas storage.
Description
Technical field
The utility model relates to a kind of gas storage and hangs pressure gauge pressure measurement completion tubular column, belongs to gas well completion string technology field.
Background technology
Setting up gas storage is a kind of effective measures of guaranteeing natural gas safety and steady air feed, can regulate the imbalance between supply and demand of summer in winter on the one hand, when accident appears in long-distance transport pipes, can bring into play the effect of emergent air feed on the other hand.Gas storage also is the important leverage of national energy security, has great importance to promoting quick, the safe and orderly development of national petroleum gas business.
Summary of the invention
The purpose of this utility model is to provide a kind of gas storage to hang pressure gauge pressure measurement completion tubular column; this tubing string energy protective casing; turn-off fast the realization down-hole; implement for protection liquid and continuous monitoring bottom pressure, satisfy that the gas storage injection-production column jacket is simple in structure, performance safety, reliable in function and cheaply requirement.
Concrete technical scheme of the present utility model is as follows:
Gas storage hangs pressure gauge pressure measurement completion tubular column from top to bottom by forming with lower member:
Oil pipe+pipe nipple A+ the storm valve that the flows+pipe nipple B+ oil pipe+circulation slide sleeve+oil pipe+grappling seal assembly+hydraulic setting permanent packer+milling exntension tubs+oil pipe+shutoff of flowing is located joint+oil pipe+pipe with holes+suspension and is located joint+horn mouth;
Flow pipe nipple A and mobile pipe nipple B and storm valve with the footpath; Storm valve connects ground control system by liquid controling pipe line; The grappling seal assembly connects the hydraulic setting permanent packer in the insert-seal mode; Suspension is located and is hung downhole electronic pressure bomb in the joint.
After this tubing string is lowered to the gas storage injection-production well, can satisfy that gas field gas storage injection-production well turn-offs fast and the demand of protective casing, can set up the circulation canal of borehole fluid with the circulation slide sleeve of string matching, for all kinds of cycle operations provide condition.Throw stifled blanking plug by steel wire operation and be located the joint in shutoff, can make the tubing string upper and lower part isolated mutually, finish the operations such as sealing pressure testing and packer setting, for the later stage snubbing serving provides technical support.The string matching suspension is located joint and can be made things convenient for the pulling downhole electronic pressure bomb, implements the down-hole dynamic pressure measurement, for the gas storage Safety Operation Analysis provides technical measures.
Description of drawings
Fig. 1 is that gas storage hangs pressure gauge pressure measurement completion tubular column structural representation.
The specific embodiment
With reference to Fig. 1 embodiment of the present utility model is further specified:
Embodiment:
Gas storage hangs pressure gauge pressure measurement completion tubular column from top to bottom by forming such as lower member:
The mobile pipe nipple B13+ oil pipe 1 circulation slide sleeve 4+ oil pipe 1+ grappling seal assembly 5+ hydraulic setting permanent packer 6 milling exntension tubs 7+ oil pipe 1+ shutoff of the mobile pipe nipple A2+ storm valve 3+ of oil pipe 1+ are located joint 8+ oil pipe 1+ pipe 9+ suspension with holes and are located joint 10+ horn mouth 11.
Flow pipe nipple A2 and mobile pipe nipple B13 and storm valve 3 with the footpath, can reduce notes, adopt process mesohigh fluid to the erosion of storm valve 3, prolong the application life of storm valve 3.
By steel wire operation, utilize special tool open and close circulation slide sleeve 4, can realize that oil jacket is communicated with, and reaches the purpose of liquid-circulating in the well.
Utilize the anchor fluke anchoring string of grappling seal assembly 5, and adopt the insert-seal mode to be connected with hydraulic setting permanent packer 6 upper ends, realize the fixing of tubing string, reduce and annotate displacement and the wriggling of adopting tubing string in the process.Realize this packer setting in sleeve pipe by the hydraulic setting mode, realize the purpose of shutoff oil jacket annular space.
In later stage kill-job or the not kill-job well workover process, after hydraulic setting permanent packer 6 top tubing strings trip out, can be lowered to special tool the packing element outer wall of hydraulic setting permanent packer 6 is carried out milling, simultaneously can connect milling exntension tubs 7, hydraulic setting permanent packer 6 and bottom tubing string thereof are tripped out smoothly.
Steel wire operation is lowered to special instrument, can be located joint 8 places in shutoff and realize shutoff in the tubing string, but the fluid,matching compacting shows setting of hydraulic setting permanent packer 6, can be used with circulation slide sleeve 4, sets up liquid-circulating in the well; Also can cooperate operation device under pressure to realize with pressure lower tubular column.
By the steel wire operation mode, downhole electronic pressure bomb 12 instruments such as grade can be lowered to, hang on to hang and be located in the joint 10, realize dynamic pressure measurement and the various functions of downhole instrument, for the gas storage Safety Operation Analysis provides technical measures.After joint 10 shutoff were located in suspension, pipe 9 with holes can be set up down-hole notes, gas production circulation road.
Horn mouth 11 can be reserved larger chamfering in the completion tubular column lower end, be convenient to being lowered to and tripping out in oil pipe of through tubing equipment or equipment.
Claims (1)
1. a gas storage hangs pressure gauge pressure measurement completion tubular column, it is characterized in that this tubing string is from top to bottom by forming such as lower member:
Oil pipe (1)+pipe nipple A (the 2)+storm valve (3) that flows+pipe nipple B (13)+oil pipe (1)+circulation slide sleeve (4)+oil pipe (1)+grappling seal assembly (5)+hydraulic setting permanent packer (6)+milling exntension tubs (7)+oil pipe (the 1)+shutoff of flowing is located joint (8)+oil pipe (1)+pipe with holes (9)+suspension and is located joint (10)+horn mouth (11);
Pipe nipple A (2) and mobile pipe nipple B (13) and storm valve (3) together footpath flow; Storm valve (3) connects ground control system by liquid controling pipe line; Grappling seal assembly (5) connects hydraulic setting permanent packer (6) in the insert-seal mode; Suspension is located and is hung downhole electronic pressure bomb (12) in the joint (10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220366128 CN202900175U (en) | 2012-07-26 | 2012-07-26 | Pressure measuring well completion pipe string for suspension pressure gauge of gas storage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220366128 CN202900175U (en) | 2012-07-26 | 2012-07-26 | Pressure measuring well completion pipe string for suspension pressure gauge of gas storage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202900175U true CN202900175U (en) | 2013-04-24 |
Family
ID=48120858
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220366128 Expired - Fee Related CN202900175U (en) | 2012-07-26 | 2012-07-26 | Pressure measuring well completion pipe string for suspension pressure gauge of gas storage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202900175U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104879167A (en) * | 2015-04-27 | 2015-09-02 | 中国石油天然气股份有限公司 | Method for rebuilding gas storage and layered injection and production system thereof |
CN106285498A (en) * | 2015-05-29 | 2017-01-04 | 中国石油天然气股份有限公司 | Gas storage injection and production string and method using same |
CN106401537A (en) * | 2016-11-16 | 2017-02-15 | 中国石油大学(华东) | Well completion pipe string of underground gas storage well and well completion method |
CN107060703A (en) * | 2017-06-28 | 2017-08-18 | 中国石油集团渤海钻探工程有限公司 | Multiple expansion sand control screen well completion technique tubular pile in a kind of sleeve pipe |
CN112647857A (en) * | 2019-10-12 | 2021-04-13 | 中国石油化工股份有限公司 | Injection-production string and well completion method using same |
CN116006159A (en) * | 2021-10-22 | 2023-04-25 | 中国石油化工股份有限公司 | Monitoring device for gas storage monitoring well and application method thereof |
-
2012
- 2012-07-26 CN CN 201220366128 patent/CN202900175U/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104879167A (en) * | 2015-04-27 | 2015-09-02 | 中国石油天然气股份有限公司 | Method for rebuilding gas storage and layered injection and production system thereof |
CN106285498A (en) * | 2015-05-29 | 2017-01-04 | 中国石油天然气股份有限公司 | Gas storage injection and production string and method using same |
CN106285498B (en) * | 2015-05-29 | 2018-10-16 | 中国石油天然气股份有限公司 | Gas storage injection and production string and method using same |
CN106401537A (en) * | 2016-11-16 | 2017-02-15 | 中国石油大学(华东) | Well completion pipe string of underground gas storage well and well completion method |
CN107060703A (en) * | 2017-06-28 | 2017-08-18 | 中国石油集团渤海钻探工程有限公司 | Multiple expansion sand control screen well completion technique tubular pile in a kind of sleeve pipe |
CN112647857A (en) * | 2019-10-12 | 2021-04-13 | 中国石油化工股份有限公司 | Injection-production string and well completion method using same |
CN112647857B (en) * | 2019-10-12 | 2022-11-25 | 中国石油化工股份有限公司 | Injection-production string and well completion method using same |
CN116006159A (en) * | 2021-10-22 | 2023-04-25 | 中国石油化工股份有限公司 | Monitoring device for gas storage monitoring well and application method thereof |
CN116006159B (en) * | 2021-10-22 | 2024-09-24 | 中国石油化工股份有限公司 | Monitoring device for gas storage monitoring well and application method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202900175U (en) | Pressure measuring well completion pipe string for suspension pressure gauge of gas storage | |
CN101775977B (en) | Dual-tube injection well safety production string | |
CN204703876U (en) | Bridge type concentric separate injection pipe column | |
CN202731863U (en) | Long-acting separate-layer water injection string for directional well | |
CN103643931A (en) | Completion and fracture integrated pipe column of offshore openhole horizontal well and construction method of pipe column | |
CN102454381B (en) | Oil-gas reservoir barefoot well cementing and completion method and device | |
CN204457756U (en) | Horizontal well segment pressure and pressure drop test pipe column | |
CN203756146U (en) | Sleeve protecting setting water injection integrated pipe column | |
CN203626759U (en) | Production pipe column with electric submersible pump and jet pump jointly lifted | |
CN203452734U (en) | Integrated production and wax removing and prevention pipe column for high-pressure gas well | |
CN103806878B (en) | Not kill-job of sea electric pump lifting technology tubing string | |
CN205858311U (en) | A kind of bore hole staged fracturing completion tubular column | |
CN104179477B (en) | Coiled tubing hangs electric motor drive oil pump system process pipe string | |
CN201620768U (en) | Self-spraying and lifting combined pipe column | |
CN203939477U (en) | Integrated tubular column for oil testing and well completion operation | |
CN203394480U (en) | Oil-water well layering acidizing device | |
CN201679489U (en) | Double-pipe separated injection safety production pipe column | |
CN204371262U (en) | Balanced type throttler | |
CN204082115U (en) | Based on the horizontal well volume fracturing tubing string of conventional oil pipe dragging with pressure | |
CN202745939U (en) | Coiled tubing hanger | |
CN201620839U (en) | Pressurized operation production string for natural gas well | |
CN205225206U (en) | A pumping device for beam -pumping unit well surveying well | |
CN205297515U (en) | Coiled tubing drags hydraulic jet fracturing unit | |
CN204782960U (en) | Integrated tubular column of water water injection sand control is adopted to individual well | |
CN203626689U (en) | Well head protection sealing connection device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130424 Termination date: 20210726 |