This directory hold some preliminary results from various stages of the development.
Please document the circumstances under which the results were produced in this Readme.
This is a run fuzzing the TLI2C circuit with the newly implemented full JQF (level 2) with a separate coverage map. The results look incredibly good, achieving 95% mux toggle coverage compared to the 25% achieved by the base line (counting only valid inputs). We will need to verify whether these results are credible...
Git SHA: ad844b0f15547fafbf08e0e3507b09ad24acb322
We were able to reproduce the coverage from 4.jqf2.i2c
by fuzzing for an hour.
This time it took ~40min to reach the same coverage as the previous run achieved
in ~4min. However at least it seems reproducible.
Some early rocket results from running it in simulation for about 2h @ ~16kHz.